Comprehensive Punch List Status and Job Site Review for Mark and Charlie
Overview of Punch List Coordination
Mark and Charlie conducted a status review of a specific punch list for an ongoing construction and electrical project.
The primary focus was on identifying completed tasks, items in progress, and outstanding issues related to material shortages, accessibility, and third-party coordination.
Detailed Punch List Status (Items through )
Item : Status is not done.
Item : Status is done.
Item : Status is not done.
Item : Status is not done.
Item : Status is not done.
Charlie is currently missing blanks for this item.
Action: Mark suggested putting this on a separate order to avoid it being missed repeatedly.
Item (Trendel P Tech): (Mentioned separately) Status involves specific technical equipment.
Item : Mostly complete.
Exception: The bubble covers are not yet installed.
Item : Not done. This item is dependent on VCC (the contractor).
Item : Status is done.
Item (Trim Out Units): Mostly complete.
Exception: Charlie is missing the necessary switches for the completion of the floor.
Item : Status is done.
Item : Done, with the exception of the switches.
Item : Status is done.
Item : Currently in progress.
Item (Pool Can Cover): Not done.
Constraint: Charlie needs to repair his grinder before finishing this part. He has ordered a part for the grinder. He may borrow Louie's grinder to expedite this.
Item : Status involves the installation of everything except the covers.
Item : Status is done.
Item : Status is done.
Item : Relates to the fire alarm riser components.
Item : The fire alarm riser work is done, but the team is currently working on the Fire Alarm Control Panel (FACP) today.
Item : Check valve covers installation is done.
Item : Not done. Access is currently restricted; Charlie cannot work in that area.
Item and : Status is done.
Item : Status is done.
Item : Not painted out.
Item : Access denied per VCC instructions.
Item : Status is not applicable (N/A).
Item : Not painted; therefore, it cannot be finished.
Item (1st Floor): Currently in progress.
Item : Status is done. Includes the uplights and well lights for VCC.
Item and (Canopy Repair and Conduit):
The larger conduit is taken care of.
The smaller conduit still requires repair.
Item (Pool Bathroom): Status is done.
Item : Status is not applicable (N/A).
Item : Status is pending due to missing panel parts. Mark will follow up on this.
Item : Status is pending. Missing parts for the frame of the pillar panel and components for the fire pump and standpipe.
Item : Under the jurisdiction of Diablo Engineering (referred to as "And Diablo"). Mark will reach out to them to ensure they have what they need.
Item (Ground Level HP , , and ):
Anchorage has not been installed yet.
Underground work is finished.
Logic: Disconnects (discos) will be set once backfilling is complete and plants are in. Charlie has most discos and ordered another today (Mark was CC'd on the order).
Item : Currently in progress.
Item (Water Heater Room): Access denied; Charlie cannot enter.
Item (1st Floor, Left Room): Access denied.
Item : EV (Electric Vehicle) equipment is provided and installed by VCC's own installers. Charlie's team is only responsible for feeding power to the units.
Item : Rectified. Work was swapped or traded for work on a light pole/post light.
Item : Dependent on VCC.
Item : Lighting Control Panel (LCP) installation is stalled until access is granted to the electric room.
Item (Trash Enclosure): Nearly done.
Exception: Waiting on the "InstaHut" product. Charlie needs to set a switch and run liquid tight once the product arrives.
Item (Generator Work): Significant progress made.
Status: String and mill tape have been pulled all the way back through the conduits; it is ready for the wire pull.
Item (Trellis and Wall Packs):
Charlie cannot proceed until the pool gunite (sprayed concrete) is completed.
Work Type: Involves "red iron" work (thick metal drilling and anchoring).
RFI (Request for Information): Charlie is waiting on a response regarding the specific height and type of wall packs for the trellis to determine wiring and box requirements.
Item : Currently in progress.
Item (Sump Pump):
Underground completed today.
Next Steps: Setting the interior box, exterior alarm, and disconnect tomorrow.
Item : Status is done.
Resource and Labor Estimates
Item (Trash Enclosure): Requires approximately for worker once the material arrives.
Item (Trellis/Red Iron): Estimated at approximately or more. This requires pre-drilling and anchoring through thick metal, likely requiring workers to be efficient.
Item : Estimated completion time of approximately for worker.
Item (Sump Pump): Estimated between to .
Item (Elevator Room):
Current Status: All piping is done, wire is pulled, and disconnects are finished.
Remaining tasks: Putting on "stack ons," cramping down, and finishing wire terminations to the heater assembly and GFI.
Estimated time: Approximately .
Site Materials and Issues
Time Clock: Charlie accidentally requested a single station instead of a double station. He needs to update the material list after the call.
Landscape/Site Work: Mostly complete. All site pulls, corrections, and repours are finished with the exception of the HP , , and the pump.
The Christie (Subgrade Box): Located on the backside of the site. It was likely crushed or buried by an excavator during site work and is currently subgrade; Charlie needs to relocate it and bring it back to grade.
Electric Room Bottleneck: Access to the electric room is causing delays on multiple items (including Item ). Charlie expressed frustration that VCC or the relevant building management are not providing answers or access.
Questions & Discussion
Mark: Did you receive the email of the punch list?
Charlie: Yes, I did.
Mark: Should I just put that (missing blanks for Item ) on another order?
Charlie: I think you should. It's getting missed.
Mark: Did you were you able to Frankenstein that thing (Item )?
Charlie: I have to order a part for my grinder. It broke. As soon as it gets here, I'll take care of it. Maybe I'll grab Louie's if he's got one tomorrow.
Mark: How long is that (Item ) gonna take? Like, how many electricians?
Charlie: I'd say . One (worker) should be good.
Mark: In regards to the wall packs (Item ), what info do you need?
Charlie: I'm trying to get them to answer that RFI in regards to the wall packs and give me a height off the top of the trellis… it'll matter how I wire or what kind of boxes I use.
Mark: Is there anything else we should add, like another line item… any more concerns on-site?
Charlie: I think we've touched on everything. Landscapes are almost done… I did lose the Christie on the backside… I think they (excavator) squished it.
Mark: Any rumors about that electrical room?
Charlie: I don't know. These guys are terrible… they can't answer questions… nobody wants to put their name on anything.