- Memory Hierarchy Configuration:
- Instruction Cache (I-cache): Read access time = 2ns, Hit ratio = 0.8
- Data Cache (D-cache): Read access time = 2ns, Hit ratio = 0.9
- Level 2 Cache (L2-cache): Read access time = 8ns, Hit ratio = 0.9
- Main Memory: Read access time = 90ns
- System Operational Policies and Assumptions:
- Read policy: Referred-word-first
- Write policy: Write-back
- Cache Mapping: Direct-mapped for all caches
- Dirty bit status: Always 0 for all blocks in the caches
- Workload Characteristics:
- Instruction Fetch (I-cache access): 60% of total memory reads
- Memory Operand Fetch (D-cache access): 40% of total memory reads
- Average Read Access Time Result:
- Under the specified operational conditions, the calculated average read access time across the memory hierarchy is 4.072ns.
Fundamentals of Parallel Processing
- Definition:
- Parallel processing refers to the simultaneous execution of data processing operations to enhance computational speed and system throughput.
- Classification of Parallel Processing Techniques:
- Vector Processing
- Array Processing
- Pipeline Processing (Pipelining)
Pipeline Processing Principles and Execution Trace
- Concept and Mechanics:
- Pipelining is a technique used to decompose a sequential processing task into sub-operations.
- Each sub-operation is executed in a dedicated segment or stage of the pipeline.
- Each segment performs its respective sub-operation concurrently on different inputs in parallel.
- Pipelining is particularly useful when the same processing sequence is repeatedly applied over a large batch of inputs.
- Sequential vs. Pipelined Manufacturing Example (Shirt Making):
- Sub-operations required for one shirt:
- Cutting: 10min
- Stitching: 10min
- Finishing: 10min
- Packing: 10min
- Sequential (Non-pipeline) System:
- Total time required per shirt = 10min+10min+10min+10min=40min.
- Segmented Pipeline System:
- Segment 1 (S1): Cutting (10min)
- Segment 2 (S2): Stitching (10min)
- Segment 3 (S3): Finishing (10min)
- Segment 4 (S4): Packing (10min)
- Number of segments (k) = 4
- Timing Trace Across Clock Pulses for n=5 Inputs:
- Clock Pulse 1: Segment S1 processes Task 1.
- Clock Pulse 2: Segment S1 processes Task 2; Segment S2 processes Task 1.
- Clock Pulse 3: Segment S1 processes Task 3; Segment S2 processes Task 2; Segment S3 processes Task 1.
- Clock Pulse 4: Segment S1 processes Task 4; Segment S2 processes Task 3; Segment S3 processes Task 2; Segment S4 processes Task 1.
- Clock Pulse 5: Segment S1 processes Task 5; Segment S2 processes Task 4; Segment S3 processes Task 3; Segment S4 processes Task 2.
- Clock Pulse 6: Segment S2 processes Task 5; Segment S3 processes Task 4; Segment S4 processes Task 3.
- Clock Pulse 7: Segment S3 processes Task 5; Segment S4 processes Task 4.
- Clock Pulse 8: Segment S4 processes Task 5.
- Formula for Total Clock Cycles:
- Cycles=k+n−1
- For k=4 stages and n=5 inputs: Cycles=4+5−1=8cycles.
- Time Comparison Across Task Batch Sizes (1cycle=10min):
- For n=5 inputs:
- Non-pipeline execution time: 5×40min=200min
- Pipeline execution time: 8×10min=80min
- For n=6 inputs:
- Non-pipeline execution time: 6×40min=240min
- Pipeline execution time: (6+4−1)×10min=9×10min=90min
- For n=7 inputs:
- Non-pipeline execution time: 7×40min=280min
- Pipeline execution time: (7+4−1)×10min=10×10min=100min
- For n=8 inputs:
- Non-pipeline execution time: 8×40min=320min
- Pipeline execution time: (8+4−1)×10min=11×10min=110min
- Pipeline Cycle Time (tp):
- Defined as the minimum time interval required for all pipeline segments to finish their respective sub-operations concurrently in parallel.
- Mathematical Formulation of Processing Time:
- Pipeline Processing Time:
- Time required to process the 1st input = k×tp
- Time required for the remaining (n−1) inputs = (n−1)tp
- Total clock cycles required = k+n−1
- Total execution time in pipeline: (k+n−1)tp
- Non-Pipeline Processing Time:
- For a non-pipeline system taking time tn to perform one complete task:
- Total execution time in non-pipeline: n×tn
- Speed Up Ratio (S):
- Quantifies the performance gain achieved by employing a pipeline system over a non-pipeline system.
- S=Pipeline timeNon-pipeline time=(k+n−1)tpn×tn
- Asymptotic and Ideal Speed Up:
- When the number of inputs is extremely large (n≫k):
- The initial k−1 cycles required to fill the pipeline become negligible and are ignored.
- The pipeline effectively outputs 1 task per cycle, taking n cycles (n×tp execution time).
- Ideal Speed Up (S_{\ideal}):
S_{\ideal} = \frac{t_n}{t_p}
- Special Case where single task execution time is identical in both systems (tn=k×tp):
- S_{\ideal} = \frac{k \times t_p}{t_p} = k
- Default Evaluation Rule:
- If the value of n is omitted or ideal conditions are presumed, speedup is computed as S=tptn.
Synchronous Pipeline Cycle Time and Register Delays
- Role of Intermediate Buffers/Registers:
- In a synchronous pipeline, intermediate registers or buffers are placed between consecutive stages to latch sub-operation outputs.
- Registers are used exclusively in pipeline architectures and are absent in non-pipeline systems.
- Determining Pipeline Cycle Time (tp):
- Without Register Delay:
tp=max(τ1,τ2,…,τk)
where τi represents the time delay of segment i$.\n * With Register/Buffer Delay (t_r):\n t_p = \max(\tau_1, \tau_2, \dots, \tau_k) + t_r\n* Equivalent Non-Pipeline Processing Time (t_n):\n * Sum of all individual segment delays without register delays:\n t_n = \sum_{i=1}^{k} \tau_i\n * Practical Relationship:\n t_n \le k \times t_p\n* Pipeline Optimization Criterion:\n * For optimal pipeline efficiency and performance, individual segment delays must be almost equal or close to each other.\n\n# Numerical Problems and Optimization Techniques\n\n* Problem 1: Basic Speedup and Asymptotic Convergence\n * Given Parameters:\n * Non-pipeline processing time t_n = 50\,\text{ns}\n * Number of pipeline segments k = 6\n * Pipeline clock cycle time t_p = 10\,\text{ns}\n * Question 1: Determine speedup ratio for n = 100 tasks.\n S = \frac{100 \times 50}{(6 + 100 - 1) \times 10} = \frac{5000}{105 \times 10} = \frac{5000}{1050} \approx 4.76\n * Question 2: Maximum theoretical speedup achievable (S_{\ideal}).\n S_{\ideal} = \frac{t_n}{t_p} = \frac{50}{10} = 5\n * Speedup Convergence Progression across Task Volumes:\n * For n = 100 \implies S = 4.76\n * For n = 1000 \implies S = \frac{1000 \times 50}{(6 + 1000 - 1) \times 10} = \frac{50000}{10050} \approx 4.97\n * For n = 100000 \implies S = \frac{100000 \times 50}{(6 + 100000 - 1) \times 10} = \frac{5000000}{1000050} \approx 4.9997\n\n* Problem 2: Pipeline Processing Time with Variable Segment Delays\n * Given Parameters:\n * Number of segments k = 6\n * Segment delays: \tau_1 = 20\,\text{ns},\tau_2 = 23\,\text{ns},\tau_3 = 21\,\text{ns},\tau_4 = 21\,\text{ns},\tau_5 = 24\,\text{ns},\tau_6 = 25\,\text{ns}\n * Task volume n = 1000\n * Step 1: Calculate pipeline cycle time t_p:\n t_p = \max(20, 23, 21, 21, 24, 25) = 25\,\text{ns}\n * Step 2: Calculate total processing time:\n \text{Total Time} = (k + n - 1)t_p = (6 + 1000 - 1) \times 25\,\text{ns} = 1005 \times 25\,\text{ns} = 25125\,\text{ns} = 25.125\,\mu\text{s}\n\n* Problem 3: Pipeline Processing Time including Register Delays\n * Given Parameters:\n * Four segments (k = 4)withdelays:t_1 = 50\,\text{ns},t_2 = 30\,\text{ns},t_3 = 95\,\text{ns},t_4 = 45\,\text{ns}\n * Interface register delay t_r = 5\,\text{ns}\n * Task volume n = 100\n * Step 1: Calculate pipeline cycle time t_p:\n t_p = \max(50, 30, 95, 45) + 5 = 95 + 5 = 100\,\text{ns}\n * Step 2: Calculate total processing time:\n \text{Total Time} = (4 + 100 - 1) \times 100\,\text{ns} = 103 \times 100\,\text{ns} = 10300\,\text{ns}\n\n* Problem 4: Decomposing Bottleneck Segments for Execution Acceleration\n * Objective: Reduce total execution time to approximately one-half of Problem 3's time (10300\,\text{ns}).\n * Optimization Technique: Decompose segment 3 (t_3 = 95\,\text{ns}) into two separate segments:\n * Segment 3.1 delay t_{31} = 50\,\text{ns}\n * Segment 3.2 delay t_{32} = 45\,\text{ns}\n * New Pipeline Parameters:\n * Total segments k_{\text{new}} = 5\n * Segment delays: t_1 = 50\,\text{ns},t_2 = 30\,\text{ns},t_{31} = 50\,\text{ns},t_{32} = 45\,\text{ns},t_4 = 45\,\text{ns}\n * Register delay t_r = 5\,\text{ns}\n * Step 1: Calculate new cycle time t_{p,\text{new}}:\n t_{p,\text{new}} = \max(50, 30, 50, 45, 45) + 5 = 50 + 5 = 55\,\text{ns}\n * Step 2: Calculate new execution time for n = 100 tasks:\n \text{New Time} = (5 + 100 - 1) \times 55\,\text{ns} = 104 \times 55\,\text{ns} = 5720\,\text{ns}\n * Step 3: Compute speedup ratio of new pipeline relative to old pipeline:\n \text{Speedup} = \frac{\text{Old Pipeline Time}}{\text{New Pipeline Time}} = \frac{10300\,\text{ns}}{5720\,\text{ns}} \approx 1.8\n\n# Practice and Homework Exercises\n\n* Homework Problem Formulation:\n * Initial Pipeline: A 6-stage pipeline with delays 2\,\text{ns},4\,\text{ns},3\,\text{ns},5\,\text{ns},3\,\text{ns},and4\,\text{ns}.\n * Upgraded Pipeline: Upgraded to a new 8-segment pipeline where each segment delay is equal to 2\,\text{ns}.\n * Task Batch Size: n = 100 tasks.\n* Homework Question 1:\n * Calculate the total time saved using the new upgraded pipeline over the old pipeline for processing 100 tasks.\n* Homework Question 2:\n * Calculate the speedup ratio achieved by the new upgraded pipeline compared to the old pipeline for processing 100$$ tasks.