PROJECT MANAGEMENT – MASTER NOTES
1. ASSUMPTIONS VS. CONSTRAINTS
These are two different things that affect a project.
Assumption
An assumption is something we believe or expect to be true when planning a project, even though we haven't confirmed it.
Example:
We assume the supplier will deliver materials on time.
We assume the team will have enough employees.
We assume the customer will approve the design.
Remember: Assumption = Something we believe will happen.
Constraint
A constraint is a limitation or restriction that the project must work within.
Examples:
Limited budget.
Fixed deadline.
Limited number of employees.
Limited resources.
Remember: Constraint = Something that limits the project.
Assumption | Constraint |
|---|---|
Something we expect to be true | A limitation |
Supplier will deliver on time | Budget is only AED 10,000 |
Team will be available | Deadline is 2 months |
EXAM TIP:
Believe or expect = Assumption.
Limit or restriction = Constraint.
2. MOSCOW PRIORITIZATION
MoSCoW is a technique used to prioritize project requirements.
It helps the team decide which features are most important.
The four categories
M – Must Have
Essential requirements.
The project cannot succeed without them.
Example: A shopping application must allow customers to pay.
S – Should Have
Important requirements, but not absolutely essential.
The project can still work without them temporarily.
Example: Customers receive an order confirmation email.
C – Could Have
Nice additional features.
They are not very important.
Added only if there is enough time and budget.
Example: A special animation when opening the application.
W – Won't Have (this time)
Features that will not be included in the current project.
They might be considered in the future.
Example: Adding a live shopping feature in a later version.
Category | Meaning | Priority |
|---|---|---|
Must | Essential | Highest |
Should | Important | High |
Could | Nice to have | Lower |
Won't | Not included this time | Not planned |
EXAM TIP:
MoSCoW = Prioritizing requirements according to importance.
3. PROJECT SCOPE
Scope means the work included in a project.
It explains:
What the project will deliver.
What work needs to be completed.
What is included.
What is NOT included.
Example
Imagine a project to create a university website.
Included in the scope:
Student login.
Course information.
Online registration.
Excluded from the scope:
Creating a mobile application.
Building a new university campus.
Developing a student transportation system.
Remember:
Scope = What is included and excluded from the project.
Stable Scope
Stable scope means the project requirements and boundaries are clearly defined and are not expected to change frequently.
Example:
Renovating a classroom with an approved design, fixed materials, and a fixed budget.
Stable scope is commonly associated with predictive project management.
However, stable does not mean changes are impossible. Changes can still happen through formal change control.
4. PROJECT CHARTER
A project charter is an official document that formally authorizes the existence of a project.
It also gives the project manager authority to use organizational resources.
It usually includes:
Project purpose.
Main objectives.
High-level scope.
Major deliverables.
Budget and timeline estimates.
Key stakeholders.
Project manager's authority.
Major risks and assumptions.
Example:
A company officially approves a project to create a new online shopping application.
The project charter gives permission for the project to begin.
EXAM KEYWORDS:
Formally authorize.
Official approval.
Project manager authority.
Authorize the project.
5. SCOPE STATEMENT
A scope statement describes the project scope in more detail.
It explains:
Project deliverables.
Work included.
Work excluded.
Acceptance criteria.
Project boundaries.
Example:
A website project will include student login, course registration, and payment services, but will not include a mobile application.
Project Charter vs. Scope Statement
Project Charter | Scope Statement |
|---|---|
Officially authorizes the project | Defines the project scope in detail |
Explains why the project exists | Explains what work is included |
Gives authority to the PM | Defines boundaries and deliverables |
Remember:
Charter = Permission to start.
Scope statement = What the project includes and excludes.
6. WBS – WORK BREAKDOWN STRUCTURE
WBS stands for Work Breakdown Structure.
It divides a large project into smaller, manageable pieces of work.
Example: Organizing a university event.
Event planning
Select the date.
Select the location.
Marketing
Create posters.
Advertise the event.
Event preparation
Arrange chairs.
Prepare equipment.
Event execution
Welcome guests.
Manage activities.
Why use WBS?
Makes large projects easier to manage.
Helps identify all project work.
Helps estimate time and costs.
Helps assign responsibilities.
Remember:
WBS = Breaking a big project into smaller pieces of work.
7. REQUIREMENTS DOCUMENT
A requirements document explains what the customer or user needs from the project or product.
It records the requirements that must be satisfied.
Example: A customer wants a shopping application.
Requirements:
Users must be able to create an account.
Users must be able to search for products.
Users must be able to pay online.
Users must be able to track orders.
Two common types:
Functional requirements
What the system must DO.
Example: The application must allow users to log in.
Non-functional requirements
How well the system must WORK.
Example: The application must load within two seconds.
Security, performance, reliability, and usability.
Remember:
Requirements = What the customer needs.
8. SCOPE BASELINE
The scope baseline is the officially approved version of the project scope.
It is used to measure and control project performance.
It consists of three main parts:
Approved scope statement.
WBS.
WBS dictionary.
What is a WBS dictionary?
It provides additional details about the work packages in the WBS.
Example:
The WBS says "Create website."
The WBS dictionary explains:
What website features must be created.
Who is responsible.
What the work includes.
What the acceptance requirements are.
Remember:
Scope baseline = Approved scope statement + WBS + WBS dictionary.
9. SCOPE CREEP
Scope creep happens when extra work or requirements are added to a project without proper approval or control.
Example:
A customer asks a team to create a basic website.
Then the customer keeps asking for:
Extra pages.
Extra features.
A mobile application.
Additional payment options.
The project becomes bigger without properly adjusting the budget or deadline.
Consequences:
Delays.
Increased costs.
More workload.
Resource problems.
Remember:
Scope creep = Uncontrolled growth of project scope.
10. CHANGE LOG VS. ISSUE LOG VS. RISK REGISTER
These three are different!
Change Log
Records requested or approved changes to the project.
Example:
The customer requests an additional feature for the website.
The change log records:
What change was requested.
Who requested it.
Its status.
Whether it was approved or rejected.
Issue Log
Records problems that are happening RIGHT NOW.
Example:
The website developer is absent, and the project is delayed.
That is an issue because the problem already exists.
Risk Register
Records potential problems that MIGHT happen in the future.
Example:
The supplier might deliver materials late.
That is a risk because it has not happened yet.
Document | What does it record? |
|---|---|
Change Log | Requested and approved/rejected changes |
Issue Log | Current problems |
Risk Register | Possible future problems |
EXAM TIP:
Might happen = Risk.
Already happening = Issue.
Someone requests a change = Change log.
11. RACI MATRIX
RACI is a responsibility assignment tool.
It identifies who does what in a project.
R = Responsible
The person who actually DOES the work.
Example: The designer creates the website design.
A = Accountable
The person who is ultimately answerable for the result.
Makes sure the work is completed.
Ideally, one person is accountable for each task.
C = Consulted
People who provide advice, information, or expertise.
Communication goes BOTH ways.
Example: Asking the IT department for technical advice.
I = Informed
People who need to receive updates.
Communication usually goes ONE way.
Example: Informing the manager when the task is finished.
Easy example
Person | RACI role |
|---|---|
Website designer | Responsible |
Project manager | Accountable |
IT specialist | Consulted |
Company director | Informed |
Remember:
R = Does the work.
A = Owns the result.
C = Gives advice.
I = Receives updates.
12. PMI AND THE CODE OF ETHICS
PMI stands for Project Management Institute.
It is a professional organization for project management.
PMI provides:
Project management standards.
Professional certifications.
Educational resources.
Ethical guidelines.
One important example is the PMI Code of Ethics and Professional Conduct.
It includes four main values:
1. Responsibility
Taking ownership of your actions and decisions.
Example:
Admitting that you made a mistake.
Completing your assigned tasks.
Accepting responsibility for your decisions.
2. Respect
Treating others with dignity and valuing their opinions.
Example:
Listening to team members.
Respecting different opinions.
Not insulting or discriminating against colleagues.
3. Fairness
Making decisions objectively and treating people equally.
Example:
Giving all employees equal opportunities.
Not showing favoritism.
Selecting suppliers based on fair criteria.
4. Honesty
Being truthful and transparent.
Example:
Reporting project delays honestly.
Not hiding project problems.
Providing accurate information about progress.
Value | Remember |
|---|---|
Responsibility | Take ownership |
Respect | Treat others properly |
Fairness | Make unbiased decisions |
Honesty | Tell the truth |
EXAM TIP:
Admit your mistake = Responsibility.
Listen to different opinions = Respect.
No favoritism = Fairness.
Report accurate information = Honesty.
13. PROJECT MANAGEMENT PLAN VS. PRODUCT MANAGEMENT PLAN
These plans have different purposes.
Project Management Plan
Explains HOW the project will be managed and completed.
It can include:
Scope management plan.
Schedule management plan.
Budget/cost management plan.
Quality management plan.
Risk management plan.
Resource management plan.
Communication management plan.
Procurement management plan.
Example:
How will we manage the team, budget, deadlines, risks, and communication while creating an application?
Product Management Plan
Explains the product's direction, purpose, and development.
It focuses on the product itself.
It may include:
Product vision.
Product roadmap.
Market research.
Customer needs.
Product requirements.
Product features.
Product strategy.
It answers:
What should we build?
For whom are we building it?
Why are we building it?
Comparison
Project Management Plan | Product Management Plan |
|---|---|
Focuses on delivering the project | Focuses on the product |
How will we complete the work? | What should we build? |
Scope, schedule, budget | Vision, roadmap, market research |
Manages project execution | Guides product direction |
Important: The product management plan is a product-management planning concept, not one single mandatory document in every PMI project.
14. MILESTONE VS. TASK DURATION VS. RESOURCE PLANNING
Milestone
A milestone is an important point or event in the project.
It has ZERO duration.
Examples:
Project officially approved.
Website design completed.
Product launched.
Construction completed.
Task Duration
Task duration means how long a particular task takes to complete.
Examples:
Designing a website: 5 days.
Painting a room: 2 days.
Testing an application: 1 week.
Resource Planning
Resource planning means identifying what resources are needed to complete the project.
Resources include:
People.
Equipment.
Materials.
Money.
Technology.
Example:
A construction project needs 5 workers, 2 machines, building materials, and a specific budget.
Concept | Meaning |
|---|---|
Milestone | Important event (zero duration) |
Task duration | How long work takes |
Resource planning | What people and resources are needed |
15. RISK REGISTER – PROBABILITY AND IMPACT
A risk register is a document that records and tracks possible project risks.
It can include:
Risk description.
Probability.
Impact.
Risk owner.
Response strategy.
Risk status.
Probability
Probability means the likelihood or chance that a risk will happen.
Example:
There is a 70% chance that the supplier will deliver late.
Impact
Impact means how seriously the risk would affect the project if it happened.
Example:
If the supplier delivers late, the project could be delayed by two weeks.
Probability vs. Impact
Probability | Impact |
|---|---|
How likely is it to happen? | How serious will it be? |
Chance of happening | Consequence of happening |
Risk levels
Probability | Impact | Priority |
|---|---|---|
High | High | Very high |
High | Low | Depends on the scoring system |
Low | High | Depends on the scoring system |
Low | Low | Usually low |
A common method is:
Risk Score = Probability × Impact
Example:
Probability = 4/5
Impact = 5/5
Risk score = 20/25.
This would usually be a high-priority risk.
Risk response strategies
Avoid: Change the plan to eliminate the threat.
Mitigate: Reduce the probability or impact.
Transfer: Move the financial impact to another party, such as through insurance.
Accept: Acknowledge the risk and take no immediate action beyond monitoring or contingency planning.
Remember:
Probability = Chance.
Impact = How serious.
16. STAKEHOLDER REGISTER – POWER AND INTEREST
A stakeholder is a person or organization that can affect the project or be affected by it.
Examples:
Customers.
Employees.
Project manager.
Suppliers.
Government.
Project sponsor.
A stakeholder register records information about stakeholders.
It may include:
Names.
Roles.
Interests.
Expectations.
Influence.
Communication needs.
Power and Interest Matrix
Power = How much influence or authority the stakeholder has.
Interest = How interested they are in the project.
Four categories:
1. High Power + High Interest = Manage Closely
Give them frequent updates.
Involve them in important decisions.
2. High Power + Low Interest = Keep Satisfied
Provide important updates.
Make sure they remain satisfied.
3. Low Power + High Interest = Keep Informed
Give them regular information.
Listen to their feedback.
4. Low Power + Low Interest = Monitor
Monitor them occasionally.
Do not spend too much time communicating.
Remember:
High power + high interest = Manage closely.
High power + low interest = Keep satisfied.
Low power + high interest = Keep informed.
Low power + low interest = Monitor.
17. PROJECT CLOSURE AND TRANSITION
Project closure is the final stage of the project.
It means officially completing the project and ensuring everything is handed over properly.
Important activities:
1. Complete Documentation
Prepare and organize all final project documents.
Example:
Final reports.
Project results.
Financial records.
Lessons learned.
Final approvals.
2. Train and Transfer Knowledge
Train the people who will use or maintain the final product.
Example:
A company creates a new software system and trains employees on how to use it.
3. Fulfill Commitments
Make sure all agreed responsibilities and obligations are completed.
Example:
Complete the agreed deliverables.
Pay suppliers.
Obtain customer approval.
Close outstanding contracts.
4. Measure and Realize Value
Check whether the project achieved its intended benefits.
Example:
A new shopping application was created to increase online sales.
After launching it, the company checks whether online sales actually increased.
5. Transition / Handover
Transfer the completed product to the people who will operate, maintain, or use it.
Example:
The project team finishes a new website and hands it over to the company's IT department.
Remember:
Project closure = Finish, approve, document, transfer, and evaluate.
18. FISHBONE DIAGRAM
A Fishbone Diagram is also called an Ishikawa Diagram or Cause-and-Effect Diagram.
It is used to identify the possible root causes of a problem.
It looks like a fish skeleton.
Example:
Problem: Project delays.
Possible causes:
People: Not enough employees.
Process: Poor planning.
Equipment: Machines are not working.
Materials: Late deliveries.
Management: Poor communication.
Environment: Bad weather.
The head of the fish represents the problem.
The bones represent possible causes.
Remember:
Fishbone = Finding the possible root causes of a problem.
19. QUALITY MANAGEMENT
Quality management ensures that the project's deliverables meet the required standards and customer expectations.
It focuses on producing work that is fit for purpose.
Three important activities:
Quality Planning: Decide what quality standards are required.
Quality Assurance: Check whether the right processes are being followed.
Quality Control: Inspect the actual results to identify defects.
Example:
A company creates an application.
Planning: Decide that the application must be secure.
Assurance: Check that the development process follows security procedures.
Control: Test the application and find security problems.
Remember:
Quality = Making sure the result meets requirements and standards.
20. INTEGRATION MANAGEMENT
Integration management coordinates and connects all the different parts of a project.
It makes sure that scope, schedule, cost, resources, risks, and other areas work together.
Example:
The customer requests an additional feature.
The project manager must consider:
Will the feature increase the cost?
Will it delay the schedule?
Will more employees be needed?
Will it create additional risks?
The project manager coordinates these changes across the project.
Remember:
Integration management = Connecting and coordinating all project areas.
21. SCHEDULE VARIANCE (SV)
Schedule Variance is used in Earned Value Management (EVM).
Formula:
SV = Earned Value (EV) - Planned Value (PV)
What is Planned Value (PV)?
The value of the work that SHOULD have been completed by a certain date according to the plan.
What is Earned Value (EV)?
The budgeted value of the work that has ACTUALLY been completed.
Positive SV
EV is greater than PV.
The project is ahead of schedule.
Example:
EV = AED 8,000
PV = AED 6,000
SV = 8,000 - 6,000 = +2,000.
Positive = Ahead of schedule.
Negative SV
EV is less than PV.
The project is behind schedule.
Example:
EV = AED 4,000
PV = AED 6,000
SV = 4,000 - 6,000 = -2,000.
Negative = Behind schedule.
Zero SV
EV = PV.
The project is exactly on schedule in terms of earned value.
Remember:
Positive SV = Ahead.
Negative SV = Behind.
Zero SV = On schedule.
IMPORTANT:
Schedule variance is measured in monetary value, not days.
22. PROCUREMENT
Procurement means obtaining goods or services from external suppliers or vendors.
A project may need to purchase materials, equipment, or professional services.
Example:
A construction company needs cement, steel, and construction equipment.
It purchases these from suppliers.
Procurement activities include:
Identifying what needs to be purchased.
Finding suppliers.
Requesting quotations.
Comparing suppliers.
Selecting a supplier.
Managing contracts.
Checking deliveries and payments.
Remember:
Procurement = Buying or obtaining goods and services from outside the organization.
23. RBS – RISK BREAKDOWN STRUCTURE
RBS stands for Risk Breakdown Structure.
It organizes project risks into categories and smaller groups.
Example:
Project Risks:
Technical Risks
Software failure.
Technical errors.
Financial Risks
Budget overrun.
Unexpected expenses.
External Risks
Weather problems.
Supplier delays.
Organizational Risks
Employee shortages.
Poor communication.
Remember:
RBS = Organizing risks into categories.
Do not confuse:
RBS = Risk Breakdown Structure.
WBS = Work Breakdown Structure.
24. AGILE METHODOLOGIES AND FRAMEWORKS
Agile is an adaptive approach to project management.
It focuses on:
Flexibility.
Customer feedback.
Frequent delivery.
Continuous improvement.
Working in smaller increments.
1. Scrum
An Agile framework that organizes work into short periods called Sprints.
Important terms:
Product Backlog.
Sprint Backlog.
Sprint.
Daily Scrum.
Sprint Review.
Sprint Retrospective.
Example:
A team builds an application feature by feature using two-week Sprints.
2. Kanban
A method that visualizes work using a board.
Common columns:
TO DO → IN PROGRESS → DONE.
It limits work in progress (WIP) to help manage workflow.
Example:
A team uses sticky notes to show which tasks are waiting, being worked on, and completed.
Remember:
Kanban = Visual board + Continuous workflow + WIP limits.
3. XP – Extreme Programming
An Agile software development methodology that focuses on high-quality code and frequent feedback.
Practices include:
Pair programming.
Continuous integration.
Test-driven development.
Frequent releases.
Pair programming means two programmers work together on the same task.
Remember:
XP = Improving software quality through engineering practices.
4. SAFe – Scaled Agile Framework
SAFe helps larger organizations apply Agile practices across multiple teams.
Example:
A small team uses Scrum, but a large bank has many teams working on the same major product.
SAFe helps coordinate their work.
Remember:
SAFe = Scaling Agile across large organizations.
5. FDD – Feature-Driven Development
FDD stands for Feature-Driven Development.
It organizes software development around small, client-valued features.
Example:
Instead of saying "Build the entire shopping application," the team develops:
Login feature.
Search feature.
Payment feature.
Order tracking feature.
Remember:
FDD = Building software feature by feature.
6. Lean
Lean focuses on maximizing value and eliminating waste.
Waste means activities that use time, money, or resources without adding value.
Example:
A company removes unnecessary approval steps that delay production.
Remember:
Lean = Deliver more value while reducing waste.
7. Crystal
Crystal is a family of Agile methodologies that emphasizes:
People.
Communication.
Teamwork.
Frequent delivery.
Adapting methods to the project and team.
Remember:
Crystal = People and communication are very important.
Quick comparison
Method | Main focus |
|---|---|
Scrum | Sprints |
Kanban | Visual workflow |
XP | Software quality and engineering practices |
SAFe | Scaling Agile across teams |
FDD | Developing features |
Lean | Eliminating waste |
Crystal | People and communication |
25. ADAPTIVE VS. PREDICTIVE TRACKING
These are two ways of managing and tracking project progress.
Adaptive Tracking
Used in Agile projects where requirements can change.
The team checks progress frequently and adjusts its plans.
Example: Developing a mobile application.
The customer gives feedback.
The team changes features.
The team works in Sprints.
Progress is reviewed regularly.
Common tracking tools:
Burndown chart.
Velocity chart.
Sprint board.
Product backlog.
Predictive Tracking
Used when the project has a clearly planned scope, schedule, and budget.
Progress is compared with the original approved plan.
Example: Renovating a building.
The design is planned in advance.
The budget is estimated.
Tasks have planned start and finish dates.
Progress is compared with the schedule.
Common tracking tools:
Gantt chart.
Milestone chart.
Schedule variance.
Earned Value Management.
Comparison
Adaptive | Predictive |
|---|---|
Flexible | More fixed |
Changes are expected | Changes are controlled |
Short iterations | Planned phases |
Application development | Building renovation |
Burndown chart | Gantt chart |
Velocity | Schedule variance |
Remember:
Application development = Often adaptive.
Building renovation = Often predictive.
The choice depends on the project's uncertainty and requirements, not just the type of project.
26. ITERATION PLANNING
An iteration is a short period in which the team completes a selected amount of work.
Iteration planning means deciding what work the team will complete during that iteration.
The team considers:
What needs to be completed?
Which tasks are most important?
How much work can the team handle?
Who will do the work?
Example:
A team plans a two-week iteration to create a login page and a search feature.
Remember:
Iteration planning = Choosing and organizing work for the next short cycle.
27. BURNDOWN CHART
A burndown chart shows how much work remains over time.
It is commonly used in Scrum and Agile projects.
Example:
A team starts a Sprint with 40 tasks.
As the team completes tasks, the remaining work decreases.
40 → 30 → 20 → 10 → 0.
The goal is to complete the remaining work by the end of the Sprint.
Remember:
Burndown chart = Work remaining over time.
28. VELOCITY
Velocity measures how much work an Agile team completes during one Sprint.
It is often measured using story points.
Example:
Sprint | Completed story points |
|---|---|
Sprint 1 | 20 |
Sprint 2 | 25 |
Sprint 3 | 24 |
Average velocity = (20 + 25 + 24) ÷ 3 = 23 story points.
This helps the team estimate how much work it may complete in future Sprints.
Remember:
Velocity = Amount of work completed per Sprint.
IMPORTANT:
Velocity is a team planning tool, not a measure of individual employee productivity.
29. AGILE ARTIFACTS
Artifacts are important documents or visual tools that provide information about the project and its work.
Three official Scrum artifacts are:
1. Product Backlog
A prioritized list of all the work and features needed for the product.
Example:
Create login.
Add payment.
Add order tracking.
Improve security.
2. Sprint Backlog
The selected work for the current Sprint, together with the team's plan for completing it.
Example:
During Sprint 1, the team selects:
Create login.
Design homepage.
3. Increment
The usable product outcome created during a Sprint, combined with previous completed increments.
Example:
The first working version of the application with a functional login page.
Other Agile tracking tools
Burndown Chart
Shows remaining work over time.
Sprint Board
Shows the status of tasks.
To Do → In Progress → Done.
Velocity Chart
Shows how much work the team completes in each Sprint.
Remember:
Product Backlog = All product work.
Sprint Backlog = Current Sprint work.
Increment = Usable completed product work.
Burndown = Remaining work.
Sprint Board = Task status.
Velocity = Work completed per Sprint.
30. TECHNICAL WRITER
A technical writer is someone who creates clear documents that explain technical information.
Examples:
User manuals.
Instruction guides.
Technical reports.
Software documentation.
Troubleshooting guides.
Product instructions.
Example:
A company develops a new application.
The technical writer creates a user guide explaining how customers can register, log in, and use the application.
Remember:
Technical writer = Person who explains technical information through written documents.