S5 PMP
Session Overview
- Welcome to session five of month three, step eight of the military PMP road map.
- Review of previous week's content and introduction to the current session.
- Accountability check: Status of PMP applications.
- Poll on completion of week five.
- Introduction of Susan for the session content.
Budget Planning Techniques
- Question 1: Early-stage budget estimation.
- Focus on determining the cost for the current stage.
- Correct Answer: Rolling wave planning.
- Explanation:
- Rolling wave planning is suitable for near-term horizons.
- Life cycle costing is for the entire project life cycle.
- Cost of delay focuses on the cost of waiting.
- Value engineering balances cost, function, and quality.
- Rolling wave planning can be used in both agile and predictive project management.
- Question 2: Budgetary allocation for risk.
- Understanding the use of reserves without affecting the project's baseline.
- Correct Answer: Contingency reserves.
- Explanation:
- Contingency reserves are for addressing risks if they occur.
- Cost baseline is for the entire project and doesn't include risk coverage.
- Project Manager has authority and control over contingency reserves.
- Management reserves are controlled by management.
- Bonus dollars often come from management reserves.
- Question 3: Ensuring expenditures align with financial resources.
- Focus on aligning the project plan with available funds.
- Correct Answer: Funding limit reconciliation.
- Explanation:
- Cost aggregation sums up estimated costs to determine the cost baseline.
- Incremental delivery breaks up the scope for better management but doesn't ensure alignment.
- Question 4: Precise budget estimation.
- Determining the total budget with a narrow range of variance.
- Correct Answer: Definitive estimate.
- Explanation:
- Rough order of magnitude estimates have a wide range of variance (e.g., -25% to +75%).
- Activity-based costing estimates a work package.
- Bottoms-up estimating is generally considered the most accurate.
- Definitive estimate has a narrow range of variance (e.g., -5% to +10%).
- S curve is a tool for tracking cost over time cumulatively.
Risk Management Planning Techniques
- Question 1: Document for identifying, assessing, and responding to risk.
- Looking for a structured approach to managing risk.
- Correct Answer: Risk management plan.
- Explanation:
- The risk register captures identified risks.
- The contingency plan outlines risk responses.
- The risk breakdown structure categorizes risks.
- Question 2: Prioritizing risks based on likelihood and potential effects.
- Focus on likelihood of occurrence and potential impact.
- Correct Answer: Probability impact matrix.
- Explanation:
- Probability impact matrix helps prioritize risks and identify the highest risks.
- Qualitative risk analysis is narrative based and subjective.
- Quantitative risk analysis involves numerical analysis.
- Question 3: Developing specific alternative plans.
- Prepare an alternative plan for when risks materialize.
- Correct Answer: Contingency planning.
- Explanation:
- Contingency planning involves specific alternative plans if identified risks occur.
- Risk response planning is a broader process of identifying and scoring risk.
- Fallback plan is used only if the original contingency plan doesn't work.
- Question 4: Identifying newly introduced risks due to chosen solutions.
- New risks that brought by the solution for the project.
- Correct Answer: Secondary risk.
- Explanation:
- Secondary risks are introduced by the chosen solution.
- Residual risks remain after contingency plans.
- Inherent risks exist before any controls or mitigation efforts.
Quality Planning Techniques
- Question 1: Aligning with the organization's commitment to quality.
- Referencing a document that is based on the organization's commitment to quality.
- Correct Answer: Quality policy.
- Explanation:
- Quality policy aligns with the organization's commitment to quality.
- The quality management plan details specific quality procedures.
- Question 2: Ensuring understanding of strict industry requirements.
- Compliance with mandatory and legal penalties
- Correct Answer: Regulations.
- Explanation:
- Regulations provide strict industry requirements with legal penalties.
- Quality metrics measure compliance.
- Standards are best practices, not legal requirements.
- Benchmarking compares performance to others.
- Question 3: Agreement on standards between parties.
- Establish quality standards between producers and payers.
- Correct Answer: Quality standards.
- Explanation:
- Quality standards are agreed upon by producers and payers.
- Quality metrics measure how well the standards are met.
- Quality policy is unique to the organization.
- The process improvement plan is for improving processes, not contracts.
- Question 4: Ensuring that the mandatory and legal regulations are met.
- Meeting the projects requirements for regulations.
- Correct Answer: Plan.
- Explanation:
- The proper planning ensure that all regulations are met.
Integration Planning and Managing Complexity
- Question 1: Quickly identifying and addressing failures.
- Implementing a strategy that addresses issues quickly.
- Correct Answer: Fail fast.
- Explanation:
- Fail fast strategy implements plans and tests them fast. Then evaluate after metrics are reported from the initiative.
- Fail safe is a fallback position that no harm will be done.
- Resilience is building a project to take impacts from the risks being identified.
- Tailoring picking the right tool for the context of the projext.
- Question 2: Minimizing the negative impacts of uncertainty.
- Building the project to minimize uncertainty and potential damage.
- Correct Answer: Resilience.
- Explanation:
- Resilience to build a project to have the ability to take an impact and still be stable.
- Adaptability is to pivot and not take on change fatigue and stay rolling with the punches
- Question 3: Reducing interdependencies in a complex project.
- Reducing the dependencies that are within the project.
- Correct Answer: Decoupling.
- Explanation:
- Decoupling separate things to plan out the components.
- Redundancy builds a second system that is dependent on the first system.
- Failsafe makes sure that you have a second system that will back up if there's a fail.
- Simulations shows the interdependencies.
- Quality Tools: Plan Do Check Act, Kaizen, Six Sigma.
- Managing Complexity: Simulations, Redundant Systems.
- Understanding the difference between adaptability and resilience.
- Change Management Plan.
Next Week's Study Plan
- Week six study guide is available.
Feedback and Wrap-up
- Poll for session feedback.
- Discussion on session objectives.
- Appreciation and acknowledgments.