Integrated Approach to Net Cash Flows and Parametric Cost Estimating Study Guide
Integrated Approach to Developing Net Cash Flows: Essential Elements
Conceptual Overview
- The development of net cash flows views the project as a holistic entity.
- Cash flow elements are categorized into inflows (money coming into the business) and outflows (money leaving the business).
Outflow Elements of Project Cash Flow
- Purchase of New Equipment: Refers to the actual monetary amount spent on purchasing new equipment. If the acquisition involves selling old equipment first, the net transaction (purchase price minus sale price) should be recorded.
- Manufacturing, Operating, and Maintenance (O&M) Costs: Includes labor, material, and factory overhead costs. These cover routine maintenance and emergency maintenance requirements.
- Leasing Expenses: Payments made for borrowing equipment instead of purchasing it.
- Interest Payment: Costs associated with borrowing capital; the interest paid on loans.
- Income Taxes: Mandatory payments to the government based on taxable income.
- Working Capital: Investment in assets such as inventory and accounts receivable (credits or money yet to be collected).
Inflow Elements of Project Cash Flow
- Borrowed Funds: Capital flowing into the business from loans or financing sources.
- Salvage Value: The estimated resale or residual value of an asset at the end of its useful life.
- Working-Capital Release: Occurs when the project is nearing termination and capital is recovered. This involves collecting receivables and selling off remaining inventories.
- Cost Saving: Any reduction in operational expenses is treated as a cash inflow.
Categorization of Cash Flow Activities
- Operating Activities: Includes Gross Income, manufacturing expenses, O&M, interest expenses, and income taxes.
- Investing Activities: Includes Initial investment (), salvage value (), investment in working capital (), release of working capital (), and capital gain tax.
- Financing Activities: Includes borrowed funds () and repayment of principal ().
Developing the Net Cash Flow Statement from the Profit-Loss Statement
Step A: Obtaining the Income Statement
- 1. Identify gross income generated by the project.
- 2. Subtract expenses: Cost of Goods Sold (COGS), debt interest, depreciation, and operating expenses.
- 3. Calculate Taxable Income.
- 4. Subtract taxes to determine Net Income.
Step B: Generating the Cash Flow Statement
- 1. Start with Net Income and add back Depreciation. Depreciation is added back because it is a non-cash expense representing accounting allocation rather than actual cash leaving the business.
- 2. Account for Working Capital Increase: Recorded as a negative value ().
- 3. Add Salvage Value: Recorded as a positive value ().
- 4. Add Borrowed Funds: Recorded as a positive value ().
- 5. Subtract Repayment of Borrowed Funds: Recorded as a negative value ().
- 6. Sum the components to obtain the Net Cash Flow.
Summary Table of Categories
- Operating Activities: Net Income (after tax) + Depreciation Working Capital (increasing receivables results in a entry).
- Investing Activities: Capital Investment Salvage Value.
- Financing Activities: Borrowed Funds Repayment of Principal.
- Net Cash Flow Calculation: The sum of Operating, Investing, and Financing activities.
Case Study: Multi-Year Income Statement Analysis
- Data Table (Currency Units: Rs.)
- Revenue:
- Year 1:
- Year 2:
- Year 3:
- Year 4:
- Less: Cost of Goods Sold (Materials, Labor, Factory Consumables):
- Year 1:
- Year 2:
- Year 3:
- Year 4:
- Less: Operating Expenses (Salaries, Lease, Rent, Travel):
- Year 1:
- Year 2:
- Year 3:
- Year 4:
- Less: Depreciation:
- Year 1:
- Year 2:
- Year 3:
- Year 4:
- Less: Interest to be Paid:
- Year 1:
- Year 2:
- Year 3:
- Year 4:
- Taxable Income Calculation:
- Year 1:
- Year 2:
- Year 3:
- Year 4:
- Less: Tax (Assumed 30%):
- Year 1:
- Year 2:
- Year 3:
- Year 4:
- Net Income Calculation:
- Year 1:
- Year 2:
- Year 3:
- Year 4:
- Revenue:
Case Study: Net Cash Flow Calculation (Yearly Breakdown)
Year 1 Calculations
- Operating Cash Flow: Net Income () Depreciation () Increase in Working Capital () = .
- Investing Cash Flow: Initial Investment () Salvage Value () = .
- Financing Cash Flow: Borrowed Funds () Loan Repayment () = .
- Net Cash Flow Year 1: .
Year 2 Calculations
- Operating Cash Flow: Net Income () Depreciation () Increase in Working Capital () = .
- Investing Cash Flow: (Salvage Value is ).
- Financing Cash Flow: Borrowed Funds () Loan Repayment () = .
- Net Cash Flow Year 2: .
Year 3 Calculations
- Operating Cash Flow: Net Income () Depreciation () Decrease in Working Capital () = .
- Investing Cash Flow: .
- Financing Cash Flow: Repayment ().
- Net Cash Flow Year 3: .
Year 4 Calculations
- Operating Cash Flow: Net Income () Depreciation () Decrease in Working Capital () = .
- Investing Cash Flow: Salvage Value ().
- Financing Cash Flow: Loan Repayment ().
- Net Cash Flow Year 4: .
Parametric Cost Estimating: Fundamentals and Benefits
Definition
- Parametric estimating is a technique that develops cost estimates by validating relationships between project characteristics. These include:
- Technical characteristics: Engineering and design specifics.
- Programmatic characteristics: Project milestones, schedule, and contract type.
- Cost characteristics: Inflation, geological drivers, and whether the estimate is for installation or operation.
- Resource consumption: Labor, materials, and equipment used during development, manufacture, or maintenance.
- Parametric estimating is a technique that develops cost estimates by validating relationships between project characteristics. These include:
Advantages of Parametric Cost Estimating
- Efficiency: Faster than bottom-up estimating. Alternatives can be evaluated in a fraction of the time.
- Consistency: Outcome is identical regardless of the person conducting the analysis, as long as inputs are the same. This contrasts with subjective estimates where individual experience might vary the predicted contingency.
- Flexibility: Easily extrapolated for different project sizes. Ideal for sensitivity analysis ("what if" scenarios) regarding design changes.
- Defensible: Models are grounded in statistical measures. High confidence is gained if the model consistently predicts costs within a specific error margin (e.g., ).
- Early Applicability: Highly reliable during the early phases of a project, outperforming consensus or apportion-based methods.
Development Phases of a Parametric Model
1. Database Development
- Collection of historical data (e.g., final cost reports from twenty underground gold mines).
- Data points to collect for an underground gold mine include:
- Volume of ore (tonnage).
- Ore Grade (e.g., , , or ).
- Extraction method (sub-level stoping, cut and fill, strip mining).
- Geotechnical conditions: Rock Mass Rating (RMR). Higher RMR usually correlates to lower support costs.
- Equipment used: Conveyor belts, truck haulage, loaders.
- Sub-surface drainage requirements.
2. Model Requirements
- Define the scope and the end-user's purpose.
- Justification: The model must save time or improve accuracy compared to bottom-up estimating.
- Specific cost considerations: Initial installment vs. operation vs. final rehabilitation stages.
- Example: A mine development cost model excludes land acquisition or access roads, focusing on shaft sinking and adits. A rehabilitation model must include Environmental Impact Assessments (EIA).
- Project Stage: Feasibility studies allow for lower accuracy ranges (e.g., a gold mine estimate range of to ).
3. Resolution of Model Architecture and Data Availability
- Selection of the cost estimating relationship (CER): Choice between look-up tables or algebraic equations.
- Mathematical Representation: .
- represents parameters such as tunnel length, support systems, or RMR.
- Variable Selection Rules:
- Parameters must have a direct causal relationship/high correlation with cost.
- Avoid including dependent parameters as independent variables. Example: Do not use both total excavation volume and drilling hours, as high volume naturally dictates high drilling hours.
- If RMR is included, do not separately include a broad "cost of support" variable if RMR already drives it.
- Do not include variables for which no historical data exists.
4. Model Development and Calibration
- Development of functional relationships, which may be linear, polynomials, power laws, or exponentials.
- Proper calibration is required before moving to validation.
5. Model Validation
- The goal is to demonstrate the model's reliability in predicting costs.
- Historical data can be "withheld" from the building process and used as test points to assess accuracy.
- If the model fails validation, the developer must return to the calibration stage.
6. Model Documentation and Updating
- Documentation: Models must be assigned version/model numbers. Documentation must highlight specific limits (e.g., the model becomes unreliable/breaks for tunnel lengths ).
- Updates: Necessary when new major cost drivers are identified or more predictive algorithms become available.
Cost Estimating in the Engineering Design Process
Development Phase
- Focus: Identify technologies and their availability. Costs are estimated based on existing similar facilities.
- Estimation Type: Bulk estimate.
- Output: Rough viability screening, initial capital range, and documentation of major assumptions/risks.
- Gold Mine Example: Examining a neighboring mine of similar depth and grade. If an existing mine cost , adjusting for inflation might lead to a estimate today.
Conceptual Design Phase
- Focus: Evaluate multiple technology or design alternatives identified in development.
- Estimation Method: Relies on parametric estimating or analogous projects.
- Example: Predicting cost per meter of development for a underground operation based on regional historical data.
- Output: Ranked alternatives with cost ranges; selection of promising alternatives.
Preliminary Design Phase
- Focus: Further develop a single selected alternative.
- Estimation Method: Piecewise estimate. While still using parametric elements, it uses specific headings for better accuracy.
- Gold Mine Detail: Calculating the specific cost to sink a shaft, developing drifts, tunnel support, and ventilation systems.
Detailed Design Phase
- Focus: Minute analysis of every project component.
- Estimation Method: Detailed bottom-up cost estimate based on full specifications and drawings.
- Output: Final project analysis for execution approval.