Intro to PM

Projects are everywhere

Cooking a meal for yourself vs. the entire town

Plan, Gather resources, Timeline → Proper management


Project Management in a nutshell: Knowing what you want to achieve, how to achieve it, how much time it will take to achieve

SMART goal (about the why) needs to be measurable


Phases of a project

Initiation, planning, execution, monitoring & controlling, and closing.

Initiation - brainstorming the goal you wish to achieve, identifying stakeholders(project charter & documents, stakeholder anaylsis)

Planning - arranging all strategies, resources, deadlines, and communication(time, costs, resources, risks, stakeholder management, procurement management)

Execution - Starting the project & make sure everything is running

Monitoring & Controlling - Keeping an eye on the project’s development and take steps when problems appear. Requires feedback and

Closing - Reporting the information, resources, and lessons learned for future owners(Contract closure, lessons learned, final reporting, document archival)

-note ; Implementation phase = Execution + Monitor & Controlling

Helps you learn how to make an effective workflow, find the right people for the right job, and learn how to adapt in adverse situations.


What is a project

  • Unique product or service; something you’re working on unique to you

  • Time-limited; Has a start and end date(can’t go on forever)

  • Project ends when the objectives are achieved or abandoned; Clean end, or sometimes stakeholders run out of time and money, or the project was out of scope, or the goal has changed


Project Success

  • Traditionally: on time, within budget and delivers the promised scope

  • Modern Approach: More effective measure: satisfied customer


Project Constraints

Cost

  • Anything needed to be bought

Scope

  • what is included and excluded. the amount of the idea you wish to achieve. exclusion


Quality

  • customer satisfaction

Risk

  • risks that may arise

  • an event that occurs that can either have a positive or negative impact

Resources

Time


Triple Constraint

  • Schedule

  • Scope

  • Cost

(Scope - Cost - Schedule) = Quality

Must regulate all three in tandem because they can have an effect on eachother

Quality is the reflection of how well you manage all three


PMBOK is a library of the best workflows, practices, terms & guidlines that are publicly accepted as a benchmark in the project management industry

PMI a non-profit institute for project managers where they can learn and get the PMP certification, and are also in charge of updating the PMBOK

PMP is a certification for project managers that reflects proof that one has leadership expertise in any way of working(takes 3 years of experience)


(WBS) Work Breakdown Structure

  • a work breakdown structure is the breakdown of the deliverables into manageable units of work(you need to breakdown the task)

  • essentially have a manageable workload that you can schedule and accomplish


Stakeholder Management

  • Stakeholders are people or organizations who will impact or be impacted by the project.

  • Always include: Project Sponsor, Project team

  • May include…



Project Management Methodologies

Types of methodologies

  • PRINCE2

  • Traditional methodologies: Waterfall, Critical Path Method,

  • SCRUM

  • KANBAN



Video

PM - application of knowledge, skills, tools, & techniques to meet requirements of a project

allows projects to deliver their desired outcomes


Organize, Budget, & Maintain


Poor Project Management

  • miss deliver dates

  • budget miscalculations

  • goals missed


Program managers - people that manage multiple projects


Always keep in mind what your project is trying to accomplish

Always help managing tasks for team members and other parts of the project

Different tools, techniques, and methodologies can be used together to make managing more effective



Culture & Project Management


  • Organizational culture: values, attitudes and beliefs of team members

  • Five approaches to conflict - avoidance, accommodation, competition, compromise, collaboration


Project Charter - An official must have “contract” created in the first week of the project; describing the goal of the project, it’s scope and more

  • Done in Initiation

  • SMART goal

  • Scope

  • Stakeholders


Team Formation

  • Forming - formation of teams and goals

  • Storming - conflicts will occur happen

  • Norming - resolving conflicts, getting along

  • Performing - acting out the plan/ideals

  • Adjourning - The conclusion of the project


Stakeholder Anaylsis

  • Knowing them allows you to keep them happy/satisfied, and benefit from them


Stakeholder register

  • A file to record and document everything(timeline, stakeholders, schedule, etc.)

  • manage all stakeholder interactions


Project Initiation: Identify Stakeholders, goals &

  • Top management

  • Your manager

  • Peers

  • Resource Managers

  • Internal Customers(b2b)

  • External Customers(b2c)

  • Government

  • Contractors, Subcontractors, Suppliers

  • Others


Project Sponsor

  • Person/Group responsible for enabling success

  • May be inside, but usually outside the project

  • Signs off that the project is complete(final phase) - the one the PM has to satisfy

  • Person responsible for escalating issues that are beyond control of the PM

  • Significant role in developing the initial charter & project plan


Politics of Projects

  • Environment

  • Goal of each stakeholder or group - goals that are open/clear or hidden agendas?

  • Power


Stakeholder management tools

  • Power/interest matrix**

  • Cooperation- Threat matrix

  • Stakeholder analysis template

  • Stakeholder Register**

  • Communication Plan


Power/Interest Matrix(Grid)



Engagement Levels

Stakeholders who are:

  • Unaware: Some customers

  • Resistant

  • Neutral

  • Supportive

  • Leading


SMART

  • Specific, Measurable, Achievable, Realistic, Time based


By the end of the fall semester, I will have enough strength to do 15 pull-ups in a row by training back exercises for 3 hours each week and steadily increasing my pull-up count every 3 weeks.


Traditional Approach to PM

  • Waterfall method

  • Completing tasks & phases in a linear manner

  • Each stage must be completed before starting the next

  • Downsides - Not that flexible, and time restrictions may get skewed



Work Breakdown Structure Creation *MIDTERM*

  • ALWAYS follow a numbering plan for direction (Start at 0.0 for Main, 1.0 - n.0 for tasks to achieve it, then n.1 - n.n) * you may make sub boxes for the sub boxes for more explanation

  • Each box should have a verb/actionable item to complete)

  • Can also be in outline format

  • May be very complex for a large project

  • 100% rule(all sub = whole cost)

Break down the main project into workable parts, and then have sub-categories to work on those parts

**The combination of boxes of the parent should be done 100% to be considered as accomplished


Difference between WBS & Gantt chart

  • Time based dependencies for Schedules (Gantt)

  • Breakdown of tasks into workable parts(WBS)


Task Dependencies

  • Types of tasks that have relations to other tasks being done chronologically

  • Finish to start

  • Start to Start

  • Finish to Finish


Leads & Lags

  • Lag: One task must wait in relation to another

  • Lead: Task must start before the predecessor does


The Network Diagram

The Critical Path

  • Found on the Network Diagram

  • The path with the longest duration

  • If any task on the critical project is delayed, the project is delayed

  • List letters on the critical path

  • Numbers represent days


Slack

  • amount of time a task can be delayed without delaying total completion of the project

  • What tasks can have slack


Resource Planning

  • most important resource is human resources


Estimating

  • Bottom-up estimating*


Bottom Up Estimation

  • WBS Structure with different work packages on different levels

- Costs for the college event

Small outdoor meet & greet event

for 200 people for 4 hours

: Security detail (25 per guard/hour) 2 guards for 4 hours → 50 × 4 = 200, Food & Drinks 4 for pizza 1$ soda → 5$ x 200 = $1000, Sound/Audio DJ $100 per hour → $400,

Total → $200 + $1000 + $400 = $1600

Resource Leveling

  • Adjusting schedule because multiple activities need to use the same resource


Gold Plating

  • project team

  • adding features to the project without people asking you

  • unnecessary addition

  • might not meet customer needs

  • more pressure on resources


Managing Budget

Cash flow

  • make a plan of when money moves, so that it is always available for key purchases


Reporting Progress

Budgeted Cost vs Actual Cost

Budgeted at Completion

  • Total budgeted costs that you were supposed to spend

Actual Cost

  • The Actual cost you spent money on.

Tracked on a Project Cost Chart


Schedule Variance:

Positive #Value:

  • Project is ahead of schedule

Neutral #Value(0):

  • Project is on time

Negative #Value:

  • Project is behind schedule


Procurement Management

  • The Make or Buy decision: Expertise, Resource availability, Licensing regulatory requirements

  • Acquisition of products/services not made/delivered by the project team

  • Fixed Price, Cost reimbursable, Time & Materials


Fixed Price Contract


Cost Reimbursable Contract



Nothing in research goals

Food included, speakers included, dj not include(ex.)

first 3 sections



Risk Appetite

  • Degree of uncertainty an entity is willing to take on in anticipation of a reward

Risk Tolerance

  • The degree, amount, or volume of risk that an organization or individual with will withstand(how much your willing to risk)

Risk Threshold

  • Point above which a stakeholder or organization is no longer willing to accept the level of uncertainty or impact(where you draw the line)

Risk Breakdown Structure(RBS)

  • Sorting actionable items into their risks at the end





Probability & Impact Matrix

  • Likelihood of something vs. It’s impact

  • High likelihood & high impact = probably happening & having an effect


Qualitative

  • High-Medium-Low arrangements


Quantitative Risk Anaylsis

  • Numbers

  • Multiplication of impact in probability


Quality Planning

  • Definition

  • Grade - a measure of quality(quantifiable items)

  • Statistics - Control limit(upper and lower standards)(measurements)


Project completion

Contract Closure

  • Ensure all documentation is up-to-date

  • Completion of testing should be noted

  • Provide formal notice that deliverables are satisfactory(or not)

  • Release the project team

  • Final Payments

  • Post-Project Evaluations

  • Reflection: Why might the project not meet the final deliverable satisfaction?


Lessons Learned

  • recorded information that reflects on both the positive and negative experiences of a project.

  • need to be relevant and retrievable for said project

  • Useful to reflect on what transpired and use to improve future projects and future stages of the current projects.


  • Identify, Document, Analyze, Store, Retrieve


Document Archival

  • Mail, Email, Discord, Github etc.



Case Study Video

Lamborari

Mid sized company


strengths - engineering(low repair rates), customer satisfaction

decline in sales(revenue decline) - competitive market

potential losses- profit, revenue, layoff hr


possible smart goal - increase profit by 30% in next 6 months



3 day plan

sales manager leading sessions

2 initiatives to increase sales

  1. Advertising campaign- trips to exotic places offering good experiences towards wealthy customers

  2. Build a Showroom in a trendy Area - show exhibitions of new models(new technology - augmented reality) interactive engaging way to show customers in an appealing way


Key responsibility to Project Sponsor

  • Feasibility Study

  • Project Charter created and presented to ceo


Identify who can lead projects(**Second one is important as its a new endeavor)

  • Interest in business analyst(Ray)

Go through object and activities(deliverables) to draft plans


Features the Cars & Exhibition should have - Scope Planning

Easy access for people to buy, Cool Features to see modular design


Creating a timeline for deliverables(Time Estimations)

Car creation, Engineering, Building


Don’t need expertise in all fields

  • Engineering, HR


Methodologies

  • Systems of practice used to guide a project from initiation to closing

  • Showing a framework of how a project should be managed


  • Waterfall most standard

  • Not used as much for developers because it’s not as flexible, takes a lot of resources & planning


Process based project management

  • 6 stages


Types of Process based project management

  • PRINCE2

  • Lean Project Management

  • Six Sigma

  • Lean Six Sigma


PRINCE2

  • Projects in Controlled Environments

  • 7 principles, 7 processes, 7 themes

6 Aspects

  • Scope, Timescale, Risk, Quality, Benefits, Cost


SAAS

  • Software as a service

  • Cloud based Software System hosted by third parties for customers to use in license

  • Ex. Microsoft 365

Risks

  • Cultural differences, Language barriers, Legal approaches to software &/or piracy


Lean Project Management

  • mindset for paving continuous improvement

  • delivering maximum value by cutting out anything unnecessary

  • reducing waste across all business processes(time, money, resources)

  • results in cost and time reductions

  • improves quality and profit


PDCA

  • Plan

  • Do

  • Check

  • Act

  • (Continuous Improvement at the Centre)


Make a plan & Test it out a few times, then check if its working and then act on it if its not so you can optimize it.


Six Sigma

  • A sigma rating that shows yield/percentage of defect-free products a plan/process creates

  • Six sigma means a defect free product 99.99966% of the time;

  • meaning 3.4 errors per one million opportunities.

  • Useful in Engineering & Pharmacy, Nuclear Industry, Bug Fixing, Financial Transactions

  • A Target statistic

DMADV


Lean Six Sigma

  • combination of reducing waste and improving quality

  • Customers, Processes, Employees

  • Customers - center of everything an organization does and support the development of the outcome

  • Processes - Business processes require a rework or evaluation, changing to an outside-in approach based on the value chain

  • Employees: Clear business processes are required across all levels of the organization.




Agile

  • Mindset and Philosophy, vs. waterfall - methodology

  • iterative approach to managing projects

  • Incremental development & releases


Before Agile

  • Software took longer to develop

  • Sometimes wouldn’t meet the needs of customers as time changed

  • 3 years to push out software to market


Scrum

  • Working with a team led by a leader

Scrum Master

  • completes work required, remove obstacles

  • Similar to a Project Manager

Product Owner

  • Focuses on the product development

  • Scrum master focuses on process

Kanban

  • Project Framework

  • Visualization of project management process

  • Sticky Notes for Work needed, Work done, work in process( To Do(WBS), Doing(Process), Done)

Scrumban

  • Two Agile methodologies combined


Backtrack to Lean Project Management - Video

Lean Manufacturing

  • making products fast, cheaper, and better

  • making do with the scarce materials they had

  • modeled company on supermarket flow(make enough to to be used in the first place, then make more as they deplete) - “just in time” process

  • Kanban

  • “Kaizen” method - improve for the better

  • as teams identified problems, they iteratively solved them and had improvements to their system

  • Gradual increase in vehicle production

  • Mass production avoiding waste striving for constant improvement

  • Exploring AI in the ER

  • Changed the way people approached production


Extreme Programming(XP) - Methodology

Agile - Manifesto


Extreme Programming

  • Agile framework to produce improved quality through simplicity, communication and feedback



In-text Citations For the Assignments


Innovation - Adding new or improved ideas that weren’t originially discussed or thought of

  • Trying new things & thinking outside the box

  • Analyzing user problems


Design management is a cross-field practice which combines innovative creation and a proper flow of management. This practice is human centered to reach as many targets as possible within scope. There is also collective intelligence where people share their individual perspectives to get the bigger picture of an idea.



What is a user journey map

  • A user journey map is a timeline that shows the steps, thoughts, and emotional experience someone has as they interact with a product or service

  • Problems students might have when searching for study spaces are available rooms and locations and their noise level

  • Our target audience are students who need a quick, easy to use way of finding available locations of spaces to study either by themselves or in groups.