Chapter Two: Written Contract Form and Substance

Chapter Two: Written Contract Form and Substance

2.1 Introduction

The American Institute of Architects (AIA), the Engineers Joint Contract Documents Committee (EJCDC), and Consensus Docs TM publish the standard form construction contracts that are most commonly encountered in the United States. The AIA documents represent a comprehensive suite of standard form construction contracts that address all aspects of construction projects, establishing them as the most widely used standard form contracts in the industry.

Consensus Docs TM constitutes a distinct suite of construction contracts developed through consensus from various industry groups, including representatives from owners, contractors, and designers. This development evolved from the original Associated General Contractors (AGC) suite of contracts. Both AIA and Consensus Docs TM primarily focus on commercial design and construction, although they are adaptable for residential construction projects, particularly larger residential developments. Conversely, EJCDC has a suite of standard form construction contracts that are more tailored toward industrial, heavy civil, and highway design and construction rather than commercial or residential applications.

Most contractors will adjust these standard form contracts to align with their specific purposes or may opt to draft unique contracts altogether. It is common for contractors to prefer specific terminology in their written contracts; nevertheless, crucial contracting issues remain consistent across contracts, irrespective of wording variation. These common issues encompass:

  • Responsibilities of the owner, contractor, subcontractors, and designer

  • Payment and completion

  • Concealed or unknown conditions

  • Changes

  • Timing

  • Interpretation of contract documents

  • Suspension and termination

  • Claims and dispute resolution

  • Insurance and surety bonds.

Understanding these key contracting issues is vital for comprehending the essence of a written construction contract. This chapter emphasizes the form and substance of written contracts typical in residential construction, commercial construction, heavy civil construction, and alternative project delivery methodologies.

2.2 The Fully Integrated Agreement

Forming a construction contract proceeds through two primary processes. The initial phase often culminates in a verbal agreement, which may arise either upon notification of award to a successful bidder or through a letter of intent following contract negotiations. Although some documentation may exist between parties during negotiations, these writings do not equate to a complete written contract.

The second phase usually concludes later, often significantly later, with the drafting of a written contract. Typically, a written construction contract is an extensive, formal document requiring signatures from both parties. A properly constructed construction contract will incorporate a clause referencing the term "entire and integrated agreement," known as a merger clause. This merger clause affirms that the written contract represents a complete accord between the parties, assuming it addresses all standard components of a similar contract.

A written contract containing a valid merger clause is regarded as a fully integrated agreement and stands alone. In cases where courts analyze the meaning of fully integrated agreements, the parol evidence rule applies. This rule dictates that the contract's meaning must be discerned solely from the document itself, with no prior verbal or written agreements permitted as evidence for interpretation. After signing a fully integrated agreement, the written contract assumes independent legal significance, nullifying any prior verbal or written agreements between the parties.

Conversely, when courts investigate the meaning of partially integrated agreements, they may reference previous verbal or written agreements to ascertain the parties' original intent. If a written contract is silent regarding an issue normally included or lacks a merger clause, courts may classify it as a partially integrated agreement, leading to more complicated interpretations, possibly resulting in conclusions neither party expected.

The standard form construction contracts from the AIA, EJCDC, or Consensus Docs generally include merger clauses and encompass all typical components of construction contracts. Hence, these standard contracts are typically construed as fully integrated agreements, underscoring the importance of utilizing these forms.

The Contract Documents

A written construction contract is essentially a compilation of documents, referred to as contract documents. These documents include various parts such as:

  • Agreement

  • Conditions

  • Drawings

  • Specifications

  • Additional documents.

All contract documents collectively form the written construction contract, and the law interprets these documents as a cohesive whole, where each part contributes meaning to the overall agreement.

Owner Contractor Agreement

The owner contractor agreement, as one component of the contract documents, contains significant information:

  • Date of the agreement

  • Project name

  • Identities of parties involved (owner, owner representative, contractor, contractor representative, designer)

  • Contract amount, unit prices, and allowances

  • Conditions regarding liquidated damages for late completion

  • Payment conditions (progress and final payments)

  • Commencement date and substantial completion date

  • Signatures of the owner and contractor.

The owner contractor agreement outlines the contractor's obligations to provide labor, materials, equipment, insurance, bonds, and all services mandated by the contract documents. It also defines the contractual scope by enumerating each included contract document by number and title or referencing a specification that lists them. The term owner contractor agreement may refer to the larger written construction contract, the array of contract documents, or specifically to the agreed portion of the contract documents, depending on context.

Conditions of the Contract

The conditions section of the contract is extensive, encompassing instructions, information, and guidelines crucial for the parties involved to manage their relationship effectively. This section includes legal conditions, which must be satisfied before any contractual obligations arise. Standard form contracts from AIA, EJCDC, and Consensus Docs provide detailed general conditions that facilitate familiarity among owners, contractors, and designers across projects.

Specifications

Specifications comprise written descriptions of the contract work and are generally included in a project manual. The term 'specification' broadly encompasses all contract documents excluding drawings. Specifications may delineate procurement and contractor requirements or relay technical information.

In 2004, the Construction Specifications Institute (CSI) master format TM was reorganized from its previous 16 divisions into its current structure of 50 divisions, facilitating standardized construction document classification. Bid documents, such as Invites for Bids (IFB) or Requests for Proposals (RFP), along with contractor bids or proposals and any related addenda are typically categorized under additional documents.

An IFB serves as a collection of documents soliciting sealed competitive bids for construction at fixed prices, while an RFP gathers documents necessary to solicit proposals prior to contract negotiation. Addenda signify any changes to IFB or RFP before the contract award.

Most owner contractor agreements exclude bid documents from the contract documents due to the parol evidence rule, which eliminates prior written or verbal agreements from contract interpretation. Caution is necessary; bid documents mentioned as additional documents may inadvertently become part of the contract documents, leading to conflicting interpretations.

In cases where bid documents align with the CSI master format, they fall within division zero, which is designated for procurement and contracting, allowing for clearer exclusion from contract documents when so formatted. The technical specifications span divisions zero-two to four-nine, each covering specific trade responsibilities.

Modifications and Change Orders

Modifications to the agreement occurring post-signature are executed through change orders that revise the contract work and price. While valid change orders stand independently as contract documents, many parties prefer a comprehensive summary of all modifications within the owner contractor agreement.

2.3 Roles and Responsibilities

The Owner

An owner may be an individual, a commercial entity, or a government agency, and the term "contractor" is interchangeable with general contractor or prime contractor. The contractor is a business entity who enters into a written contract with an owner and typically holds a general contractor's license. The contractor's written contract delineates mutual responsibilities but also extends to subcontractors, who may also be referred to as specialty contractors, trade contractors, or prime trade contractors.

Subcontractors perform designated construction tasks and may further subcontract with other subcontractors, leading to multiple tiers of contractors on a project. The term subcontractor as used encompasses all layers of subcontracting involved. The written contract between the owner and contractor also addresses subcontractors' responsibilities, despite their nonparty status in the overall owner contractor agreement, given that they execute various services during construction.

The Designer

The designer refers to either an architect or an engineer. The role of leading design responsibilities may shift between architects, responsible for residential and commercial building designs, or engineers, focusing on infrastructure and large-scale construction projects. Both architects and engineers must possess appropriate state licensure to practice. Although not a legal party to the owner contractor agreement, the designer's responsibilities must be highlighted as they perform essential services on behalf of the owner.

Legal Authority

Both the owner and contractor must possess legal capacity to sign the construction contract. In business contexts, this authority is typically vested in an officer or agent, and government agency contects establish signatories with proper authority. The owner’s representative assumes daily management responsibilities on the project, while the owner's legal description of the property must be accurate to enforce mechanic liens effectively.

Construction by Owner or Separate Contractors

Owners may engage multiple contractors for differing segments of a project or even use in-house employees for certain tasks. Coordination among the owners, contractors, and any other project activities is essential to ensure smooth progress and mitigate delays. When contractor’s work interacts with that of other contractors, it may necessitate clear communication and delineation of responsibilities.

The Contractor

Like the owner, the contractor needs legal authority to enter into the construction agreement and, similarly to the owner, assigns responsibility for day-to-day activities to a designated representative. This representative will operate as the decision-maker for the contractor, akin to the owner's representative. The contractor must maintain appropriate licensing, as unlicensed contractors cannot enforce contracts or mechanics' liens, denying them payment for performed work.

The contractor bears the financial responsibility for obtaining necessary permits, fees, and inspections following the contract agreement, while the owner usually manages zoning and other regulatory approvals.

Performance Obligations

Contractors are obligated to perform work conforming to contract documents even if inspections or approvals originate from the designer. They undertake warranty responsibilities extending past project completion, ensuring compliance with local codes during ongoing inspections, and handling any required reports on design deficiencies promptly.

Health and Safety

General responsibility for construction safety rests with the contractor, tasked with safeguarding workers, materials, and adjacent properties. Contractors must adhere to legal safety mandates and secure all necessary insurance coverage for different aspects of construction activities, including workers' compensation and general liability.

The contractor must also have mechanisms to mitigate risks posed by hazardous materials, promptly halting work and notifying involved parties if such materials are discovered. Follow-up on these situations often necessitates thorough negotiation for changes to contracts reflecting any resulting shutdown or remediation efforts from hazardous materials.

The Designer's Role

The designer's role is intricately linked to overseeing compliance with contractual agreements, necessitating akin responsibilities within the owner contractor agreement. This authority, however, is not comprehensive; the designer does not direct contractor operations. Instead, their duties include evaluating contractor requests for payment, managing submittals, and ensuring compliance with scheduling without assuming liability for contractor actions.

Conclusion

Understanding the intricacies of construction contracts, their form, and the defined roles and responsibilities of all parties involved is fundamental for effective project management. The highlights of this chapter serve to delineate the essential nuances that govern construction agreements, fostering informed discussions and decisions as projects evolve.