Material handling & excavation

Material handling & cranes

  • Focus: delivery, movement, storage, and control of materials on construction sites.
  • Key equipment involved in material handling: excavators, cranes, forklift trucks, lifting devices, etc.
  • Cranes
    • Defined as lifting devices designed to raise materials by rope operation and move the load horizontally within the machine's limitations (Chudley & Greeno 2014, p. 221).
    • Central role in material handling due to their ability to lift and place heavy loads with reach and precision.
  • Material handling (general concept)
    • Encompasses the design, planning, and execution of the movement of materials on site to improve efficiency and safety.

Crane selection criteria and types

  • Crane selection criteria (to be considered when choosing a crane):
    • Loads to be lifted
    • Height requirements
    • Horizontal distance to be covered
    • Time period(s) of lifting operations
    • Utilisation factors
    • Degree of mobility required
  • Self-propelled cranes
    • Mobile cranes mounted on a wheeled chassis
    • Have only one operator position from which the crane is controlled and the vehicle is driven
  • Material handling safety emphasis
    • Always refer to best practice guidelines when designing material handling systems
    • Safety should be a primary consideration in design and operation
  • Source note
    • A number of references and links are provided (including http://geolines.ru/netcat_files) to illustrate practical examples and best practice guidance.

Table 4.3: Lifting parameters of chosen mobile cranes compared to assembly parameters (Summary of content)

  • Purpose of the table
    • Compare lifting parameters of mobile cranes to the assembly parameters of precast elements (e.g., columns, frames, roof slabs).
    • Parameters include: boom length, radius, lifting capacity, lifting height, and working radius, and how these relate to the assembly heights and dimensions.
  • Selected working parameters (conceptual)
    • The table presents two crane options used for comparison with precast assembly tasks:
    • Option 1: Crawler crane (RDK-25 with main boom and extended jib)
    • Option 2: Mobile crane (Liebherr LTM 1030)
  • Notes on data
    • The table includes detailed numerical values for each crane option and comparisons to assembly tasks (e.g., columns, frames, roof slabs).
    • The exact numeric values in the transcription are partially garbled; refer to the source table (Table 4.3, Sutt et al. 2013, p.84) for the complete figures.
  • General content covered in the table (structure)
    • Model of mobile crane
    • Technical parameters: length of boom (m), radius (m), lifting capacity (t), lifting height (m)
    • Assembly parameters: lifting height vs. assembly height (m), units lifted by the crane, working radius (m)
    • Each option relates the crane capabilities to the specific precast elements (columns, frames, roof slabs)
  • Key takeaway
    • The table is used to assess whether the chosen crane can safely and efficiently handle the precast elements within the project’s assembly constraints.
  • Source
    • (Sutt et al. 2013, p84)

Waste management on construction sites

  • Waste management (Chudley & Greeno 2014, p. 220)
    • Aim: effective management and reduction of construction waste
    • Emphasis on minimizing waste through planning and process control
  • Site Waste Management Plan / Resource Recovery Management
    • Planning mechanism to manage waste streams effectively on site and promote recovery/reuse where possible
  • Resources and examples
    • Waste management on site can be explored via related media:
    • Site waste management plan/resource recovery management (conceptual)
    • Helpful videos:
      • "Waste on construction sites" (5.5 mins): https://www.youtube.com/watch?v=w_8ByOwjp2U
      • "What happens to construction waste?" (1.37 mins): https://www.youtube.com/watch?v=GDau-oaKNwg

Excavation: classification by material

  • Common classification method (by material):
    • Topsoil excavation – removal of the exposed layer of the earth’s surface
    • Earth excavation – removal of the layer of soil directly beneath topsoil
    • Rock excavation – removal of material using special methods (drilling/blasting)
    • Muck excavation – removal of excessively wet material and soil unsuitable for stockpiling
    • Unclassified excavation – removal of a combination of the above materials
  • Reference
    • Andres & Smith 2009, p. 66
  • Terminologies: excavation terminologies video
    • Link: https://www.youtube.com/watch?v=EIthR6akGtw

Excavating machines

  • Excavating machines cover a wide range of designs and sizes and can be categorized into three broad groups:
    • Universal Excavators – cover most forms of excavators; share common functional factors
    • Multi-purpose Excavators – capable of performing several excavating functions with both front and rear attachments
  • Additional online references
    • Example visuals: http://i.ytimg.com/ and http://www.volvoce.com

Scaffolding: functional requirements

  • Functional requirements of scaffolding
    • Provide a safe horizontal working platform
    • Provide safe horizontal and vertical access to buildings
  • Scaffolding safety video
    • Video: Scaffolding safety (9.5 mins)
    • Link: https://www.youtube.com/watch?v=Gmtgxr6aRwY

Scaffolding and temporary supports on existing buildings

  • Scaffolding is also required for work on existing buildings, including:
    • Repair, maintenance, and refurbishment projects
    • Worksites that are near public access areas for pedestrian safety
  • Foundational references
    • Emmitt & Gorse 2014, p.16

Scaffolding components and loading considerations

  • Scaffolding components
    • Constructed from aluminium or steel tubes and clips
    • Timber or metal scaffold planks used to form a secure and level working platform
  • Reference
    • Emmitt & Gorse 2014, p.17

Cantilever scaffolding: key elements and loading considerations

  • Head plate
  • Through tie
  • Adjustable steel strut (must be secure)
  • Sole plate
  • Guard rail
  • Fibre reinforced sheeting tied to scaffold
  • Minimum toe board: 150 mm
  • Ledgers and Ledger bracing
  • Outer standard
  • Cantilevered steel beam designed to transfer loads
  • Notes on design and safety
    • High stress concentration – adequacy of the structure must be checked
  • Visual reference in the text
    • Figure 2.14 Cantilever scaffolding (Emmitt & Gorse 2014, p.31, 38)
  • Structural adequacy note
    • Adequacy of the existing structure to support the loads applied by the scaffold and cantilever beam must be checked
  • Source
    • The University of Newcastle, Australia

Additional references and reminders

  • The material above summarizes material handling, crane selection, waste management, excavation classifications, scaffolding, and cantilever scaffolding as presented in the provided transcript.
  • Where specific numeric values are presented in the original table (Table 4.3), the transcription here notes their existence and relative relationships; for precise figures, refer to Table 4.3 in the source: Sutt et al. (2013), p.84.
  • All URLs mentioned above are included in the notes for further reading and video demonstrations.