Material handling & excavation
Material handling & cranes
- Focus: delivery, movement, storage, and control of materials on construction sites.
- Key equipment involved in material handling: excavators, cranes, forklift trucks, lifting devices, etc.
- Cranes
- Defined as lifting devices designed to raise materials by rope operation and move the load horizontally within the machine's limitations (Chudley & Greeno 2014, p. 221).
- Central role in material handling due to their ability to lift and place heavy loads with reach and precision.
- Material handling (general concept)
- Encompasses the design, planning, and execution of the movement of materials on site to improve efficiency and safety.
Crane selection criteria and types
- Crane selection criteria (to be considered when choosing a crane):
- Loads to be lifted
- Height requirements
- Horizontal distance to be covered
- Time period(s) of lifting operations
- Utilisation factors
- Degree of mobility required
- Self-propelled cranes
- Mobile cranes mounted on a wheeled chassis
- Have only one operator position from which the crane is controlled and the vehicle is driven
- Material handling safety emphasis
- Always refer to best practice guidelines when designing material handling systems
- Safety should be a primary consideration in design and operation
- Source note
- A number of references and links are provided (including http://geolines.ru/netcat_files) to illustrate practical examples and best practice guidance.
- Purpose of the table
- Compare lifting parameters of mobile cranes to the assembly parameters of precast elements (e.g., columns, frames, roof slabs).
- Parameters include: boom length, radius, lifting capacity, lifting height, and working radius, and how these relate to the assembly heights and dimensions.
- Selected working parameters (conceptual)
- The table presents two crane options used for comparison with precast assembly tasks:
- Option 1: Crawler crane (RDK-25 with main boom and extended jib)
- Option 2: Mobile crane (Liebherr LTM 1030)
- Notes on data
- The table includes detailed numerical values for each crane option and comparisons to assembly tasks (e.g., columns, frames, roof slabs).
- The exact numeric values in the transcription are partially garbled; refer to the source table (Table 4.3, Sutt et al. 2013, p.84) for the complete figures.
- General content covered in the table (structure)
- Model of mobile crane
- Technical parameters: length of boom (m), radius (m), lifting capacity (t), lifting height (m)
- Assembly parameters: lifting height vs. assembly height (m), units lifted by the crane, working radius (m)
- Each option relates the crane capabilities to the specific precast elements (columns, frames, roof slabs)
- Key takeaway
- The table is used to assess whether the chosen crane can safely and efficiently handle the precast elements within the project’s assembly constraints.
- Source
Waste management on construction sites
- Waste management (Chudley & Greeno 2014, p. 220)
- Aim: effective management and reduction of construction waste
- Emphasis on minimizing waste through planning and process control
- Site Waste Management Plan / Resource Recovery Management
- Planning mechanism to manage waste streams effectively on site and promote recovery/reuse where possible
- Resources and examples
- Waste management on site can be explored via related media:
- Site waste management plan/resource recovery management (conceptual)
- Helpful videos:
- "Waste on construction sites" (5.5 mins): https://www.youtube.com/watch?v=w_8ByOwjp2U
- "What happens to construction waste?" (1.37 mins): https://www.youtube.com/watch?v=GDau-oaKNwg
Excavation: classification by material
- Common classification method (by material):
- Topsoil excavation – removal of the exposed layer of the earth’s surface
- Earth excavation – removal of the layer of soil directly beneath topsoil
- Rock excavation – removal of material using special methods (drilling/blasting)
- Muck excavation – removal of excessively wet material and soil unsuitable for stockpiling
- Unclassified excavation – removal of a combination of the above materials
- Reference
- Andres & Smith 2009, p. 66
- Terminologies: excavation terminologies video
- Link: https://www.youtube.com/watch?v=EIthR6akGtw
Excavating machines
- Excavating machines cover a wide range of designs and sizes and can be categorized into three broad groups:
- Universal Excavators – cover most forms of excavators; share common functional factors
- Multi-purpose Excavators – capable of performing several excavating functions with both front and rear attachments
- Additional online references
- Example visuals: http://i.ytimg.com/ and http://www.volvoce.com
Scaffolding: functional requirements
- Functional requirements of scaffolding
- Provide a safe horizontal working platform
- Provide safe horizontal and vertical access to buildings
- Scaffolding safety video
- Video: Scaffolding safety (9.5 mins)
- Link: https://www.youtube.com/watch?v=Gmtgxr6aRwY
Scaffolding and temporary supports on existing buildings
- Scaffolding is also required for work on existing buildings, including:
- Repair, maintenance, and refurbishment projects
- Worksites that are near public access areas for pedestrian safety
- Foundational references
- Emmitt & Gorse 2014, p.16
Scaffolding components and loading considerations
- Scaffolding components
- Constructed from aluminium or steel tubes and clips
- Timber or metal scaffold planks used to form a secure and level working platform
- Reference
- Emmitt & Gorse 2014, p.17
Cantilever scaffolding: key elements and loading considerations
- Head plate
- Through tie
- Adjustable steel strut (must be secure)
- Sole plate
- Guard rail
- Fibre reinforced sheeting tied to scaffold
- Minimum toe board: 150 mm
- Ledgers and Ledger bracing
- Outer standard
- Cantilevered steel beam designed to transfer loads
- Notes on design and safety
- High stress concentration – adequacy of the structure must be checked
- Visual reference in the text
- Figure 2.14 Cantilever scaffolding (Emmitt & Gorse 2014, p.31, 38)
- Structural adequacy note
- Adequacy of the existing structure to support the loads applied by the scaffold and cantilever beam must be checked
- Source
- The University of Newcastle, Australia
Additional references and reminders
- The material above summarizes material handling, crane selection, waste management, excavation classifications, scaffolding, and cantilever scaffolding as presented in the provided transcript.
- Where specific numeric values are presented in the original table (Table 4.3), the transcription here notes their existence and relative relationships; for precise figures, refer to Table 4.3 in the source: Sutt et al. (2013), p.84.
- All URLs mentioned above are included in the notes for further reading and video demonstrations.