10. project management

what is a project

a set of activities with a defined start and send state which persues a defined goal and uses a defined set of resources

what are project managers

they perform a variety of functions such as facilitating teamwork to acheive outcomes and managing the process it is the application of knowlage, skills tools and techniques to project activties to meet project requirements

slack defines it inot 6 stages

  1. understanding the project environment- internal and external factors

  2. defining the project

  3. planning

  4. technical execution

  5. project control

  6. learning

project stakeholder analysis

we can put this into a power interest matrix

project stakeholders are indivisuals groups or entities that have an interest in the project process or outcome

  • internal- client sponser managers

  • external- customers suppliers

how are projects defined

  • objectives

  • scope

  • strategy

work breakdown structure

this is acheived by structuring the project inot a family tree, that specifies major tasks or sub projects

these are then defined into smaller tasks until a manageable series of tasks is found

each work package can be allocated its objectives in terms of time cost and quality

WBS activity identification

generating the WBS looks simple but the decisions are fundemental for success

it provices the first attempt at modelling the projects process

each activity is allocated with a duration and resources

a time plan for project

after identifying activities we can formulate an activty-on-node AON diagram and critical path anlaysis

AON technique- the construction of the project plan combines the WBS to identify all activitires, the sequence they need to be perfomred in and thr estimated duration of each activity

tasks depend on AON, start to finish

our end time is our start time + duration

critical path method CPM

popular project scheduling technique for network analysis

  • calculate project completion time

  • identify critical acitivites in the project

  • most project mangers use AON to analys the network

  • this is applicable to projects without any resource constraint


how to calcualte a critical path diagram

we put the activities in the AON based on the duration and succdss

the duration for our start and finish tasks is always 0, and the start time of our start tast is also 0

  1. calculate the forward pass by calculating each acitvities Earliest start time and earliest finsih time

    EF=ES+ACTIVITY DURATION

  2. calculate the backwards pass, start on the right side and move left, use the largest EF as the LF for all ending activities. if an activity has multiple immedridtley following activities set the activities LF equal to the smallest LS of the following activities

    LS=LF-ACTIVITY TIME

    LF=EF

    TF=LF-ED

project control earn value management EVM

this is a technique that was proposed in the US military as a formal prpoject management and control technique to monitor projects in process

it allows the projct manager to measure the amount of work actually performed on a project beyond the basic review of cost and scheduled reports