Project Setup and WBS Structures in SAP S/4HANA

Modifying Profit Plans

  • Profit plans must be constantly adjusted based on project modifications, contract value changes, and spending.

  • Adjustments can involve lowering profit plans due to overspending or increasing them when the project performs well.

Work Breakdown Structure (WBS)

  • A WBS is an organized breakdown of the statement of work within a project.

  • In SAP S/4HANA, WBS is used for cost collection.

  • In the COBRA tool, WBS is used for earned value management reporting.

  • WBS elements are individual components of the WBS structure, which can be concrete tasks or aspects of a task.

  • Customer contract WBS or earned value management requirements can dictate the WBS structure.

  • The WBS structure determines how costs are broken down in SAP S/4HANA.

  • It's crucial to collaborate with contract representatives and program managers to set up projects correctly.

MS One ERP Project Setup Guide

  • This guide helps determine the project type and RA (Result Analysis) project type.

  • When using the guide, read from left to right.

  • The guide helps determine if a project is international or domestic.

Example: Domestic Program in Salt Lake City

  • Domestic programs are recognized as "90".

  • Legal entity is narrowed down based on selections in the guide.

  • The category is determined in coordination with the contract administrator (e.g., a direct project).

  • The masking ID is determined (e.g., A-).

  • Project profile (e.g., NG00100) is based on the company code and category.

  • The project profile cannot be changed after project creation in S/4HANA.

Intercompany Work Order (IOW)
  • An IOW has a different category and project profile.

  • Selecting the wrong project profile requires canceling the project and creating a new one.

Project Type

  • Project type differs from project profiles.

  • There are three project types: fixed, time and material, and cost type.

Project Types

Fixed
  • In fixed contracts, cost and sales are recognized simultaneously.

  • Every time costs are incurred, sales are also collected.

Time and Material:
  • Requires billing labor mapping (BLC).

  • Billing occurs for every material ordered.

Cost Type:
  • Costs are not immediately recognized.

  • Costs are recognized when a bill is submitted to the customer.

  • Natural profit plans are used.

Network Profile and Network Type

  • These help determine the network profile to select.

  • For a fixed contract:

    • select fixed.

    • RA key on the PS upload template is cost to cost.

    • The network profile is 20.

PS Upload Template

  • Found under the MSPS help request form.

  • It's a macro file.

  • Click the cactus icon to open.

Yellow Banner Issue

  • Save the file to your desktop to resolve the "checkout required" banner.

  • Save the file as soon as you get the project number to prevent data loss.

Sector and Project Charging

  • Indicate the sector (e.g., MS sector).

  • If the work belongs to a different sector, select the Y box.

  • Specify if it is IPC (Inter-Project Charging) or SPC (Single Project Charging).

Project Type Groups

  • Two primary types: Contract Direct and Contract IOWs.

Project Setup Link Guide

  • Use this guide when setting up your project.

Direct Project Types

  • Cost redeterminable cost type projects

  • Fixed price projects

  • Intercompany risk work (RWA)

  • International or direct or no sales

Indirect Project Types

  • BIN proposals (BNPs)

  • IRAD (research and development)

  • Marketing and sales (MNS)

  • Capital based projects

  • MRP group default

  • MRP group WBS

  • Corporate benefits

  • Corporate environmental

  • Capability investment

  • OTA, MTA allowable

  • Miscellaneous

  • ATL costs

  • Collectors

Entity Code

  • Determined from the MS one ERP project setup guide (e.g., 90).

Rate Segment

  • Based on the personnel charging into the program.

  • Different employees may have different charging rate segments.

  • Duplicate WBS structures may be needed for different rate segments (e.g., EBS and ISY).

  • Example: Engineering support (ISY) vs contract support (EBS) under the same work package.

Major Product Category

  • Determines the rates applied to the project.

  • Consolidated with PA has a higher rate (e.g., 300300 per hour).

  • Consolidated with no PA has a lower rate (e.g., 200200 per hour).

  • Excluded major product category has the bare minimum rates.

  • Collaborate with contract representatives and PMs to ensure correct rates.

Plant Code

  • Example: Salt Lake City's plant code is P118.

Levels

  • Levels are critical to project setup.

  • Levels create the parent/child hierarchy of WBS elements.

  • Level one shares the same format as the project definition.

  • PCAs may relevel a WBS element for corrections within the same RA structure.

International Plants

  • International projects settle costs back to a domestic project.

WBS Levels

  • Review WBS levels when creating or adding to a project.

  • PS upload template checks the accounting assignment box.

Examples

No Summary Line
  • Level one: A-0B4645 Coruscant

  • Level two: RA key indicates where costs roll up to.

Summary Line
  • Level one, level two, and level three.

  • RA line at level three.

  • Further broken down by level four, level five, and level six.

Network WBS

  • The WBS that has a network created and is tiered to it must be the lowest level of any leg of your structure.

  • Example: Discrete task and rate segment (e.g., EBS or SYST).

RA Structure

  • Masking ID:

    • Limited to 24 characters

    • Sector-specific masking goes away, becomes A- (except capital projects use C-)

  • RA letters are required in the RA level of the project structure.

  • Summary levels are optional.

Smart Coding

  • WBS element example (smart coding): A-88649-001_RA1

  • Activity description: ETD based off of CLIN 1.

  • First 001 indicates the first CLIN (Contract Line Item).

  • Second 001 indicates the first charge code created identifying where this WBS element is and where it lines up.

Non-Smart Coding

  • Without smart coding, WBS elements can get jumbled.

  • Doesn't easily identify CLINs or where costs are going.

  • Benefits: Easy identification of CLINs.

POPCA Smart Coding

  • POPCA smart coding uses indicators for customer, government, or other (C, G, or X).

RA Key Types

  • Cost is the new RA key naming convention; CTOC is used for projects prior to January 2023 (cost to cost).

  • Point in time fixed - Is related to when we ship the project. (limited use).

  • RWA: Risk Work Authorization (RWA or RWAC depending on the class).

Revenue Recognition

  • C901 checklist form is used.

  • Process requirements for programs 30,000,00030,000,000 or greater or 100,000,000100,000,000 or greater.

Performance Obligation (New Rollout)

  • Represents the nature of the promises in the contract, accumulation of revenues and costs, and measurement of income.

  • EAC: Estimation at completed level with one SAP profit center and the same profit plan booking rate for all RA WBSs.

WBS Element and Description

  • Character limit of 24 characters.

  • Level one includes masking A- and a five-digit number.

  • RA WBS includes A-, five-digit code, and -RA (or -001RA for multiple RAs).

  • Network WBS includes masking ID, project number, CLIN, and network counter.

  • WBS descriptions are limited to 40 characters (including spaces).