Project Setup and WBS Structures in SAP S/4HANA
Modifying Profit Plans
Profit plans must be constantly adjusted based on project modifications, contract value changes, and spending.
Adjustments can involve lowering profit plans due to overspending or increasing them when the project performs well.
Work Breakdown Structure (WBS)
A WBS is an organized breakdown of the statement of work within a project.
In SAP S/4HANA, WBS is used for cost collection.
In the COBRA tool, WBS is used for earned value management reporting.
WBS elements are individual components of the WBS structure, which can be concrete tasks or aspects of a task.
Customer contract WBS or earned value management requirements can dictate the WBS structure.
The WBS structure determines how costs are broken down in SAP S/4HANA.
It's crucial to collaborate with contract representatives and program managers to set up projects correctly.
MS One ERP Project Setup Guide
This guide helps determine the project type and RA (Result Analysis) project type.
When using the guide, read from left to right.
The guide helps determine if a project is international or domestic.
Example: Domestic Program in Salt Lake City
Domestic programs are recognized as "90".
Legal entity is narrowed down based on selections in the guide.
The category is determined in coordination with the contract administrator (e.g., a direct project).
The masking ID is determined (e.g., A-).
Project profile (e.g., NG00100) is based on the company code and category.
The project profile cannot be changed after project creation in S/4HANA.
Intercompany Work Order (IOW)
An IOW has a different category and project profile.
Selecting the wrong project profile requires canceling the project and creating a new one.
Project Type
Project type differs from project profiles.
There are three project types: fixed, time and material, and cost type.
Project Types
Fixed
In fixed contracts, cost and sales are recognized simultaneously.
Every time costs are incurred, sales are also collected.
Time and Material:
Requires billing labor mapping (BLC).
Billing occurs for every material ordered.
Cost Type:
Costs are not immediately recognized.
Costs are recognized when a bill is submitted to the customer.
Natural profit plans are used.
Network Profile and Network Type
These help determine the network profile to select.
For a fixed contract:
select fixed.
RA key on the PS upload template is cost to cost.
The network profile is 20.
PS Upload Template
Found under the MSPS help request form.
It's a macro file.
Click the cactus icon to open.
Yellow Banner Issue
Save the file to your desktop to resolve the "checkout required" banner.
Save the file as soon as you get the project number to prevent data loss.
Sector and Project Charging
Indicate the sector (e.g., MS sector).
If the work belongs to a different sector, select the Y box.
Specify if it is IPC (Inter-Project Charging) or SPC (Single Project Charging).
Project Type Groups
Two primary types: Contract Direct and Contract IOWs.
Project Setup Link Guide
Use this guide when setting up your project.
Direct Project Types
Cost redeterminable cost type projects
Fixed price projects
Intercompany risk work (RWA)
International or direct or no sales
Indirect Project Types
BIN proposals (BNPs)
IRAD (research and development)
Marketing and sales (MNS)
Capital based projects
MRP group default
MRP group WBS
Corporate benefits
Corporate environmental
Capability investment
OTA, MTA allowable
Miscellaneous
ATL costs
Collectors
Entity Code
Determined from the MS one ERP project setup guide (e.g., 90).
Rate Segment
Based on the personnel charging into the program.
Different employees may have different charging rate segments.
Duplicate WBS structures may be needed for different rate segments (e.g., EBS and ISY).
Example: Engineering support (ISY) vs contract support (EBS) under the same work package.
Major Product Category
Determines the rates applied to the project.
Consolidated with PA has a higher rate (e.g., per hour).
Consolidated with no PA has a lower rate (e.g., per hour).
Excluded major product category has the bare minimum rates.
Collaborate with contract representatives and PMs to ensure correct rates.
Plant Code
Example: Salt Lake City's plant code is P118.
Levels
Levels are critical to project setup.
Levels create the parent/child hierarchy of WBS elements.
Level one shares the same format as the project definition.
PCAs may relevel a WBS element for corrections within the same RA structure.
International Plants
International projects settle costs back to a domestic project.
WBS Levels
Review WBS levels when creating or adding to a project.
PS upload template checks the accounting assignment box.
Examples
No Summary Line
Level one: A-0B4645 Coruscant
Level two: RA key indicates where costs roll up to.
Summary Line
Level one, level two, and level three.
RA line at level three.
Further broken down by level four, level five, and level six.
Network WBS
The WBS that has a network created and is tiered to it must be the lowest level of any leg of your structure.
Example: Discrete task and rate segment (e.g., EBS or SYST).
RA Structure
Masking ID:
Limited to 24 characters
Sector-specific masking goes away, becomes A- (except capital projects use C-)
RA letters are required in the RA level of the project structure.
Summary levels are optional.
Smart Coding
WBS element example (smart coding): A-88649-001_RA1
Activity description: ETD based off of CLIN 1.
First 001 indicates the first CLIN (Contract Line Item).
Second 001 indicates the first charge code created identifying where this WBS element is and where it lines up.
Non-Smart Coding
Without smart coding, WBS elements can get jumbled.
Doesn't easily identify CLINs or where costs are going.
Benefits: Easy identification of CLINs.
POPCA Smart Coding
POPCA smart coding uses indicators for customer, government, or other (C, G, or X).
RA Key Types
Cost is the new RA key naming convention; CTOC is used for projects prior to January 2023 (cost to cost).
Point in time fixed - Is related to when we ship the project. (limited use).
RWA: Risk Work Authorization (RWA or RWAC depending on the class).
Revenue Recognition
C901 checklist form is used.
Process requirements for programs or greater or or greater.
Performance Obligation (New Rollout)
Represents the nature of the promises in the contract, accumulation of revenues and costs, and measurement of income.
EAC: Estimation at completed level with one SAP profit center and the same profit plan booking rate for all RA WBSs.
WBS Element and Description
Character limit of 24 characters.
Level one includes masking A- and a five-digit number.
RA WBS includes A-, five-digit code, and -RA (or -001RA for multiple RAs).
Network WBS includes masking ID, project number, CLIN, and network counter.
WBS descriptions are limited to 40 characters (including spaces).