study guide flash cards
4.1 Distinguish between Job Order Costing and Process Costing
Job order costing (JOC) is the optimal costing method for producing custom goods or when it is easy to identify the cost directly with the product.
A JOC system assigns costs to each individual job as the costs are incurred, so that at all points in the manufacturing process, the costs assigned to that particular job are known.
4.2 Describe and Identify the Three Major Components of Product Costs under Job Order Costing
Direct materials are requested on a materials requisition form and recorded on the job cost sheet when transferred from raw materials inventory to the work in process inventory.
Time tickets are used to accumulate the labor associated with particular jobs and assigned to those jobs on the job cost sheet.
Manufacturing overhead costs are accumulated in the manufacturing overhead account and assigned to the individual jobs using the predetermined overhead rate.
4.3 Use the Job Order Costing Method to Trace the Flow of Product Costs through the Inventory Accounts
Materials used in production include the beginning raw materials inventory and purchases, less the ending inventory. This amount is the amount added to the work in process inventory.
The cost of goods manufactured includes the beginning work in process inventory, the materials used in production, the direct labor assigned to each job, and the manufacturing overhead costs assigned, less the costs remaining in the work in process inventory. This amount is transferred to the finished goods inventory.
The cost of goods sold include the beginning finished goods inventory and the cost of goods manufactured during the period, less the ending inventory.
When the job is completed, the costs are transferred from the work in process inventory to the finished goods inventory.
When the jobs are sold, the costs are transferred from the finished goods inventory to the cost of goods sold.
4.4 Compute a Predetermined Overhead Rate and Apply Overhead to Production
Expenses are recognized when they have a direct relationship with the associated revenue, when there is a systematic and rational method to allocate them, or immediately when there is no expected benefit.
The estimated activity base is typically direct labor dollars or direct labor hours, and is based on an allocation base that increases or decreases as overhead increases or decreases.
The predetermined overhead rate is the estimated overhead divided by the activity base:
4.5 Compute the Cost of a Job Using Job Order Costing
Costs from the materials requisition sheet and time tickets are recorded on the job cost sheet.
Overhead is allocated from the manufacturing overhead account to the individual jobs and recorded on the job cost sheet.
Each job has its own job cost sheet, showing the materials, labor, and overhead for each job.
4.6 Determine and Dispose of Underapplied or Overapplied Overhead
Overhead is allocated to individual jobs based on the estimated overhead costs for the year and may be overapplied or underapplied for the year.
Overhead is underapplied when not all of the costs accumulated in the manufacturing overhead account are applied during the year.
Overhead is overapplied when more overhead is applied to the jobs than was actually incurred.
The amount of overhead overapplied or underapplied is adjusted into the cost of goods sold account.
4.7 Prepare Journal Entries for a Job Order Cost System
Job cost sheets record the material, labor, and overhead costs for each job, whereas journal entries actually transfer the costs into the work in process inventory, the finished goods inventory, and cost of goods sold.
4.8 Explain How a Job Order Cost System Applies to a Nonmanufacturing Environment
Job order costing can be used in nonmanufacturing companies and with the same techniques, even though there are not any inventory accounts.
5.1 Compare and Contrast Job Order Costing and Process Costing
The three categories of costs incurred in producing an item are direct material, direct labor, and manufacturing overhead.
Process costing is the system of accumulating costs within each department for large-volume, mass-produced units.
Process costing often groups direct labor and manufacturing overhead as conversion costs.
Costs under GAAP are categorized as period costs when they are not related to production and instead cover a time period.
Selling and administrative costs are period costs related to the sales of products and management of the company and are not directly tied to a specific product.
Process costing determines the cost per unit through the use of equivalent units, or the number of units that would have been produced if production was sequential instead of in batches.
5.2 Explain and Identify Conversion Costs
Conversion costs are the costs of direct labor and manufacturing overhead used to convert raw materials into a finished product.
Materials are added during various stages of the manufacturing process, while conversion of the product from raw material into finished goods is considered to occur uniformly through the process. Thus, it is possible for a product to have all of its materials and not be complete.
Equivalent units for direct materials can be different than the equivalent units for conversion costs because materials are added in steps through the manufacturing process, while conversion costs are incurred evenly throughout the process.
5.3 Explain and Compute Equivalent Units and Total Cost of Production in an Initial Processing Stage
Process costing has a work in process inventory account for each department.
Equivalent units of production for materials may differ from the equivalent units for conversion costs.
The total units to account for is the number of units in the beginning work in process inventory plus the number of units started into production; this total also represents the sum of the number of units completed and the number of units in the ending work in process inventory.
The cost per equivalent unit for materials is the total of the material costs for the beginning work in process inventory and the total of material costs incurred during the period.
The cost per equivalent unit for conversion costs is the total of the conversion costs for the beginning work in process inventory and the total of conversion costs incurred during the period.
The cost of units transferred to the next department is the number of units transferred times the total of the cost per equivalent unit of material plus the cost per equivalent unit for conversion costs.
5.4 Explain and Compute Equivalent Units and Total Cost of Production in a Subsequent Processing Stage
The total units to account for is the number of units in the beginning work in process inventory plus the number of units transferred from the prior department; this total also represents the number of units completed plus the number of units in the ending work in process inventory.
The cost per equivalent units for materials is the total of the material costs for the beginning work in process inventory plus the cost of material transferred in to the department plus the total of material costs incurred during the period.
The cost per equivalent unit for conversion costs is the total of the conversion costs for the beginning work in process inventory plus the conversion costs transferred in plus the total of conversion costs incurred during the period.
5.5 Prepare Journal Entries for a Process Costing System
Traditional journal entries show the purchase of material and the incurring of overhead costs.
Each department records the transfer of material from the storeroom into production, its direct labor costs, the application of overhead, and the transfer of goods to the next department or finished goods.
The value of the inventory transferred to the next department or to finished goods equals the amount listed as transferred on the production cost report.
6.1 Calculate Predetermined Overhead and Total Cost under the Traditional Allocation Method
Manufacturing overhead is estimated for the upcoming period.
An activity base is selected to allocate overhead. This is traditionally direct labor hours, direct labor cost, or machine hours.
A predetermined overhead rate is calculated by dividing the estimated overhead by the allocation base.
Overhead is allocated to each product based on the estimated predetermined overhead rate and the number of units in the selected activity base.
6.2 Describe and Identify Cost Drivers
Overhead costs are analyzed and grouped based on similar activity bases. A cost driver, such as inspections, machine setups, or order taking, is selected for each cost grouping.
Analysis of cost drivers allows for better selection of true overhead cost drivers and more appropriate allocation of overhead.
6.3 Calculate Activity-Based Product Costs
Costs can be traced to the unit level or batch level.
There are five steps in the ABC process:
identify activities needed for production
assign overhead expenses
assign a cost driver for each expense
determine a predetermined overhead rate
allocate overhead to each product
6.4 Compare and Contrast Traditional and Activity-Based Costing Systems
Traditional allocation assigns overhead based on a single overhead rate, while ABC assigns overhead based on several cost pools and the activities that drive costs.
Traditional allocation is optimal when the manufacturing process is labor driven and overhead increases based on traditional activity bases, such as direct labor hours, direct labor dollars, or machine hours.
ABC costing is optimal when the manufacturing process is technology driven and overhead increases based on various activities that differ for each product.
6.5 Compare and Contrast Variable and Absorption Costing
Absorption costing assigns all manufacturing costs to products, whereas variable costing only assigns variable costs to the products.
Income statements from both methods can be reconciled by starting with the net income or loss using variable costing and adding the amount of fixed costs included in ending inventory and subtracting the fixed costs included in beginning inventory.
Variable costing is not considered GAAP compliant but lends itself to cost-volume-profit analysis.
7.1 Describe How and Why Managers Use Budgets
A good budgeting system assists management in reaching their goals through the planning and control of cash inflows through revenue and financing and outflows through payment and expenses.
There are various budgeting strategies including bottom-up, top-down, and zero-based budgeting.
A static budget is prepared at one level of activity, while a flexible budget allows the variable expenses to be adjusted for various levels of activity.
A master budget includes the subcategories of operating budgets and financial budgets.
A master budget is developed at the estimated level of activity.
7.2 Prepare Operating Budgets
The sales budget is the first budget developed, and the estimated sales in turn guide the production budget.
The production budget shows the quantity of goods produced for each time period and leads to computing when and how much direct material needs to be ordered, when and how much labor needs to be scheduled, and when and how much manufacturing overhead needs to be planned.
The sales and administrative budget plans for the nonmanufacturing expenses.
All operating budgets combine to develop the budgeted income statement.
7.3 Prepare Financial Budgets
The financial budgets include the capital asset budget and the cash budget. The cash collections schedule and cash payments schedule are computed and combined with the other budgets to develop the cash budget.
Information from the other budgets and the budgeted income statement are used to develop the budgeted balance sheet.
7.4 Prepare Flexible Budgets
A master budget and related budgets are prepared as static budgets for the estimated level of activity.
A flexible budget adjusts the budgets for various levels of activity and allows for the actual results to be evaluated at the actual volume of activity.
7.5 Explain How Budgets Are Used to Evaluate Goals
Management’s evaluations of the actual results versus the estimated budgetary results help plan for the future.
Favorable variances occur when sales are higher or expenses are lower than budgeted.
Unfavorable variances occur when sales are lower or expenses are higher than budgeted.
8.1 Explain How and Why a Standard Cost Is Developed
Standards are budgeted unit amounts for price paid and amount used.
Variances are the difference between actual and standard amounts.
A favorable variance is when the actual price or quantity is less than the standard amount.
An unfavorable variance is when the actual price or amount is greater than the standard amount.
8.2 Compute and Evaluate Materials Variances
There are two components to material variances: the direct materials price variance and the direct materials quantity variance.
The direct materials price variance is caused by paying too much or too little for material.
The direct materials quantity variance is caused by using too much or too little material.
8.3 Compute and Evaluate Labor Variances
There are two labor variances: the direct labor rate variance and the direct labor time variance.
The direct labor rate variance determines if the rate paid is greater than or less than the standard rate.
The direct labor time variance determines if the actual hours used are greater than or less than the standards that should have been used.
8.4 Compute and Evaluate Overhead Variances
There are two sets of overhead variances: variable and fixed.
The variable variances are caused by the overhead application rate and the activity level against which the rate was applied.
The variable overhead rate variance is the difference between the actual variable manufacturing overhead and the variable overhead that was expected given the number of hours worked.
The variable overhead efficiency variance is driven by the difference between the actual hours worked and the standard hours expected for the units produced.
There are two fixed overhead variances. One is caused by spending too much or too little on fixed overhead. The other is caused by actual production being above or below the expected production level.
8.5 Describe How Companies Use Variance Analysis
The key to analyzing variances is to determine why the variance occurred.
If a company cannot determine why there is a variance, it will not know if the variance is indicative of a problem or not.
All firms—manufacturing, retail, and service—use standards and variances.
9.1 Differentiate between Centralized and Decentralized Management
Management control systems allow managers to develop a reporting structure to help the organization meet its strategic goals.
In centralized organizations, primary decisions are made by the person or persons at the top of the organization.
Decentralized organizations delegate decision-making authority throughout the organization.
Daily decision-making involves frequent and immediate decisions.
Strategic decision-making involves infrequent and long-term decisions.
9.2 Describe How Decision-Making Differs between Centralized and Decentralized Environments
Segments are uniquely identifiable components of the business that facilitate the effective and efficient operation of the business.
Organizational charts are used to graphically represent the authority structure of an organization.
The CEO of a centralized organization will establish the strategy and make decisions that will be implemented throughout the organization.
The CEO of a decentralized organization will establish strategic goals and empower managers to achieve the goals.
9.3 Describe the Types of Responsibility Centers
A responsibility accounting structure helps management evaluate the financial performance of the segments in the organization.
Responsibility centers are segments within a responsibility accounting structure.
Five types of responsibility centers include cost centers, discretionary cost centers, revenue centers, profit centers, and investment centers.
Cost centers are responsibility centers that focus only on expenses.
Discretionary cost centers are responsibility centers that focus only on controllable expenses.
Revenue centers are responsibility centers that focus on revenues.
Profit centers are responsibility centers that focus on revenues and expenses.
Investment centers are responsibility centers that consider the investments made by the responsibility center.
Return on investment (ROI) is a particular type of investment center structure that calculates a responsibility center’s profit percentage relative to the center’s investment.
Residual income is a particular type of investment center structure that evaluates investments using a common cost of capital rate amongst all responsibility centers.
9.4 Describe the Effects of Various Decisions on Performance Evaluation of Responsibility Centers
Uncontrollable costs are costs that management or an organization has little or no ability to influence.
Controllable costs are costs that managers or an organization can influence.
Managers in a responsibility accounting structure should only be evaluated based on controllable costs.
Businesses with segments that provide goods to other segments within the business often use a transfer pricing structure to record the transaction.
The general transfer pricing model considers the opportunity costs involved in selling to internal rather than external customers. This method is difficult to implement and businesses often choose other methods.
The market price model uses market prices that would be used for external customers as the basis for internal transfers.
The cost approach uses the company’s cost to make the product as the basis for establishing the transfer price.
The negotiated model allows the selling and buying segments within the business to determine the transfer price.
Transfer price arrangements are more difficult in international businesses because of complexities related to taxes, duties, and currency fluctuations.
10.1 Identify Relevant Information for Decision-Making
Decision-making involves choosing between alternatives.
A critical step in the decision-making process is identification of all the relevant information for each alternative. Relevant information is any information that would have an impact on the decision.
Relevant information can come in the form of costs or revenues, or be nonfinancial in form. For information regarding costs, this means determining which costs are avoidable and which are unavoidable.
10.2 Evaluate and Determine Whether to Accept or Reject a Special Order
Deciding to accept or reject a special order is a choice between alternatives.
Accepting or rejecting a special order involves comparing the purchase price associated with the special order to the cost to produce the items.
This decision is highly influenced by whether the firm being offered the special order is operating below or at capacity.
Qualitative factors would include consequences such as potential loss of current customers or displacement of jobs.
10.3 Evaluate and Determine Whether to Make or Buy a Component
Deciding to outsource a component of the operations or manufacturing of a business is a choice between alternatives.
Choosing whether to make or to buy a product, or choosing to have services performed by an outside company, are outsourcing decisions.
Outsourcing decisions involve comparing the cost to keep the product or service in-house to the cost of buying the product or service from an outside party.
An important consideration in these types of decisions is unavoidable costs.
10.4 Evaluate and Determine Whether to Keep or Discontinue a Segment or Product
Deciding to keep or discontinue a product line or a segment of a business is a choice between alternatives.
The choice to keep or eliminate involves comparing the business’s total operating income generated from keeping the product or segment and comparing this to the business’s total operating income generated if the product or segment is eliminated.
An important consideration in these types of decisions is allocated costs.
10.5 Evaluate and Determine Whether to Sell or Process Further
Deciding to do more work on a product to develop it into a new product is a choice between alternatives.
Choosing whether to sell a product as is or to process it further involves comparing the selling price without further processing (at split-off) to the net price (selling price less additional processing costs) that would be obtained if the product were processed further.
An important consideration in these types of decisions is the realization that the costs incurred up to the split-off point are irrelevant to the decision.
10.6 Evaluate and Determine How to Make Decisions When Resources Are Constrained
Deciding to how to use scare resources is a choice between alternatives.
Scarce resources can include anything that limits productive capacity, such as machine-hours or labor hours.
Choosing how to use the scarce resource involves determining the contribution margin for each product or service that uses the constrained resource. The products or services with the highest contribution margin have the largest impact on income.
Choosing how to manage the scarce resource will help reduce bottlenecks.