Prospect Reserve Critical Watermain Renewal – Base-Estimate Evaluation Clarifications
General Pricing-Schedule & Programme Clarifications (G-Series)
G1.1 – Activity Schedule vs P6 Programme Alignment
- Issue: Several activities showing time in Primavera P6 had no dollar values in the Activity Schedule.
- CW Response (R1): Submitted mapping doc “20038913 _Pricing Schedule and Activity Mapping” showing:
- Milestone & Project-Management (PM) tasks intentionally carry cost in the schedule because their costs are rolled into monthly PM line-items.
- Claimed this is a logical, efficient way to track PM progress.
- Status: Closed after SWC noted receipt of mapping on 17 Apr 25.
G1.2.1 – Missing DABC Milestone
- Definition: DABC = Detailed Analysis & Business Case; SWC internal step releasing project funds.
- Issue: DABC date absent in schedule.
- CW R1: Hidden inside Activity RFQ-PRM-120 – SW Review & Approval; argued lack of visibility because it is SWC-controlled.
- SWC R2: Management Specification §3.4.1 demands an explicit DABC milestone; gave target .
- CW R3: Re-issued P6 programme with DABC on the specified date.
- Status: Closed.
G1.2.2 – Distribution of PM Costs
- Issue: PM costs spread evenly each month → SWC feared difficulty verifying earned value.
- SWC requirement: Costs must correspond to observable deliverables, map to Activity Schedule, and allow monthly payment certification.
- CW R3: Re-aligned programme, activity schedule, and pricing schedule; provided resource breakdown analogous to Group 8 template.
- Status: Closed.
G1.2.3 – Absence of a Risk Activity
- Principle: Management Spec §3.5.2 expects explicit risk activities or allowances traceable to Risk Register.
- CW R1: Cost of risk distributed across affected tasks (lump-sum contract logic).
- SWC R2: Requested clarified allowances + full risk register.
- CW R3: Submitted risk register (Group 8 format) and agreed to include escalation line.
- Status: Open pending escalation update.
G1.2.4 – NOA/NTP Lag
- Definitions:
- NOA = Notice of Award
- NTP = Notice to Proceed
- Issue: Only 3 weeks allowed between DABC and NTP.
- SWC requested 6 weeks → fixed NTP milestone .
- CW: Programme amended.
- Status: Closed.
G1.2.5 – Orphan Activities & Critical Path
- Activities without successors:
- Environmental Sediment Controls
- Site Mobilisation & Compound Setup
- Traffic Management (CH 900 → 935)
- Risk: Breaks Critical-Path integrity.
- CW: Added relationships; critical path unaffected; updated P6 file submitted.
- Status: Closed.
G1.2.6 – CESMM4 & WBS Depth
- Requirement (since 1 Jul 24): Estimates using ECC Option A must reach WBS Level 7 (Cost Estimating & Cost Control) to align with CESMM4 coding.
- CW defence: RFQ predates 01 Jul 24; compliant with WBS Rev-12 approved in Implementation Plan.
- SWC accepted.
- Status: Closed.
G1.3 – First-Principles & Sub-contract Quotations
- SWC needs granular data to build SWC Bill-of-Quantities (BoQ).
- CW supplied “Basis of Estimate” with sub-contractor comparison.
- Example given during 06 Apr 25 meeting: Discrepancy between DGB20 back-fill quantities in quotes vs CW baseline.
- Status: Closed after submission.
Indirect Cost Clarifications (I-Series)
I1.1 – PM & Supervision Breakdown
- Deliverable: Resource-loaded WBS to Level 7 matching Group 8 template (shows PM labour, margin, Workers-Welfare, risk, Long-Service-Levy).
- CW initially non-compliant; later provided activity schedule; SWC confirmed sufficiency.
- Status: Closed.
I1.2 – Quantum of PM Costs (\$4.28 M)
- SWC view: High given heavy subcontracting; especially daily burn during site investigations.
- CW justification:
- Option A contract shifts more contractual/quality risk to head contractor.
- Contamination management (waste classification) needs dedicated resources.
- Compared to Jasper Rd CWM (4 yrs ago) costs are actually lower.
- CW supplied detailed cost file; SWC accepted explanation with minor reservations.
- Status: Closed.
Direct Cost Clarifications (DC-Series)
Procurement Governance Reminder
- SWC Procurement Guidelines: ≥3 quotes for each supplier package >\$50k, plus tender analysis whenever lowest quote not chosen.
DC1.1 – Sub-contract & Supplier Quotes
- CW initially cited Option A confidentiality; SWC insisted.
- Quotes delivered; SWC satisfied.
- Status: Closed.
DC1.2 – Civil Sub-contract Selection (RA Smith vs Jonishan)
- Delta: Jonishan cheaper.
- Non-conformances cited by CW:
- No traffic-management provision.
- No haulage / tipping of spoil.
- Temporary restoration limited to 50 m.
- One crew only → longer duration ⇒ higher indirect cost.
- Revised procurement strategy & tender evaluation matrix submitted; SWC closed.
DC1.3 – MSCL Pipe Supply (Pipe Lining & Coating vs Steel Mains)
- PLC quote vs Steel Mains .
- Only 2 suppliers on SWC SP panel for this pipe calibre; 3rd quote impossible.
- CW rationale for higher-priced supplier: “conservative approach”; willingness to revisit at NTP.
- Documentation provided; Closed.
DC1.4 – Installation Rate
- SWC flagged as excessive (sub-contract lump sum vs CW install price ).
- CW detailed production-rate model:
- Typical productivity: 3 × 6 m lengths/crew/day ⇒ market rate.
- Prospect Reserve constrained:
- CW allowed (two crews) = overall.
- Concrete-encased sections (>2.5 m deep) drop to 1 length ≈6 m/day.
- Option A risk premium & contingency added.
- SWC to evaluate in final estimator’s report.
- Status: Pending SWC final cost assessment.
DC1.5 – Overall Rate for 2.4 km
- SWC couldn’t reconcile with past projects.
- CW delivered full first-principles workbook (Direct + Indirect + Provisional).
- SWC to comment in final report.
- Status: Pending SWC final report.
Environmental & Heritage (DE-Series)
- DE1.1 – REF & s60 Controls
- REF = Review of Environmental Factors; s60 = Heritage Act approval.
- CW confirmed proposal must change due to:
- Experienced archaeologist to monitor all excavations.
- Soil-amendment works around pine trees on William Lawson Dr, 6 months pre-construction.
- Full-time arborist monitoring those excavations.
- Implication: Additional time & cost risk to be loaded into programme and risk register.
- Status: Closed after acknowledgement.
Risk Register Clarifications (R-Series)
- R1.1 – Time & Cost-Loaded R&O Register
- Spec §3.5.2 requires:
- Clear distinction between inherent vs contingent risks.
- Quantified and cost/float provisions.
- Transparent basis of estimate (BoE) per risk scenario.
- CW provided Group-8-style register; still needs:
- SWC risk overlays.
- Re-calibrated Groundwater-Sensitive Waste (GSW) & rock excavation allowances.
- Status: Open – awaiting resubmission.
Key Technical & Contractual Concepts Explained
Option A (NEC-ECC)
- Lump-sum with activity schedule; payment upon completion of listed activities. Shifts quantity risk to Contractor but still requires transparent cost build-up for SWC funding governance.
CESMM4 Coding & WBS Level 7
- Ensures estimates are measurable, comparable, and traceable; Level 7 captures specific resources (labour, plant, material) enabling & cost-control reporting.
Productivity Assumptions
- Market norm: 3 × 6 m = 18 m/day/crew.
- CW conservative: 10 m/day/crew due to environmental constraints.
- Concrete-encased (>2.5 m depth) sections: 6 m/day/crew.
Risk Quantification Metrics
- : Probability distribution median ⇒ expected cost/time.
- : High-confidence allowance; only 10 % chance of exceedance.
- Registers record & in per risk.
Scheduling Milestones
- DABC Approval:
- NOA: Immediately after DABC.
- NTP: (6 week administrative lead time).
Practical & Governance Implications
Accurate alignment between Programme, Activity Schedule and Pricing Schedule is vital for:
- Monthly payment certification (Option A).
- Cash-flow forecasting for both SWC and Contractor.
- SWC DABC funding release.
Non-conforming sub-contract bids can’t be chosen merely on price; missing scope items can inflate SWC’s risk if later added by variation. Ethical procurement demands transparent tender evaluation.
Environmental & heritage obligations (archaeologist, arborist, soil amendment) not only add cost but can trigger schedule float consumption; must be mirrored in risk & programme to avoid latent claims.
High PM cost scrutiny reflects public-sector accountability; Contractor must demonstrate value-for-money while acknowledging increased Option A risk profile.
Numerical / Statistical References & Formulae
- Pipe-installation cost flagged: .
- Overall project rate questioned: .
- Productivity allowances:
- Normal:
- Allowed:
- Concrete-encased: .
- Administrative lag: post-DABC.
Outstanding Actions Summary
- CW to update Risk Register (SW risks, GSW & rock).
- SWC to issue final estimator’s report covering DC1.4 & DC1.5 cost reasonableness.
- CW to upload revised escalation figures (noted in G1.2.3).
- Confirmation that amended P6 file (with all G-series fixes) is accepted by SWC planning.