Prospect Reserve Critical Watermain Renewal – Base-Estimate Evaluation Clarifications

General Pricing-Schedule & Programme Clarifications (G-Series)

  • G1.1 – Activity Schedule vs P6 Programme Alignment

    • Issue: Several activities showing time in Primavera P6 had no dollar values in the Activity Schedule.
    • CW Response (R1): Submitted mapping doc “20038913 _Pricing Schedule and Activity Mapping” showing:
    • Milestone & Project-Management (PM) tasks intentionally carry 00 cost in the schedule because their costs are rolled into monthly PM line-items.
    • Claimed this is a logical, efficient way to track PM progress.
    • Status: Closed after SWC noted receipt of mapping on 17 Apr 25.
  • G1.2.1 – Missing DABC Milestone

    • Definition: DABC = Detailed Analysis & Business Case; SWC internal step releasing project funds.
    • Issue: DABC date absent in schedule.
    • CW R1: Hidden inside Activity RFQ-PRM-120 – SW Review & Approval; argued lack of visibility because it is SWC-controlled.
    • SWC R2: Management Specification §3.4.1 demands an explicit DABC milestone; gave target 29/08/2529/08/25.
    • CW R3: Re-issued P6 programme with DABC on the specified date.
    • Status: Closed.
  • G1.2.2 – Distribution of PM Costs

    • Issue: PM costs spread evenly each month → SWC feared difficulty verifying earned value.
    • SWC requirement: Costs must correspond to observable deliverables, map to Activity Schedule, and allow monthly payment certification.
    • CW R3: Re-aligned programme, activity schedule, and pricing schedule; provided resource breakdown analogous to Group 8 template.
    • Status: Closed.
  • G1.2.3 – Absence of a Risk Activity

    • Principle: Management Spec §3.5.2 expects explicit risk activities or allowances traceable to Risk Register.
    • CW R1: Cost of risk distributed across affected tasks (lump-sum contract logic).
    • SWC R2: Requested clarified allowances + full risk register.
    • CW R3: Submitted risk register (Group 8 format) and agreed to include escalation line.
    • Status: Open pending escalation update.
  • G1.2.4 – NOA/NTP Lag

    • Definitions:
    • NOA = Notice of Award
    • NTP = Notice to Proceed
    • Issue: Only 3 weeks allowed between DABC and NTP.
    • SWC requested 6 weeks → fixed NTP milestone 10/10/2510/10/25.
    • CW: Programme amended.
    • Status: Closed.
  • G1.2.5 – Orphan Activities & Critical Path

    • Activities without successors:
    1. Environmental Sediment Controls
    2. Site Mobilisation & Compound Setup
    3. Traffic Management (CH 900 → 935)
    • Risk: Breaks Critical-Path integrity.
    • CW: Added relationships; critical path unaffected; updated P6 file submitted.
    • Status: Closed.
  • G1.2.6 – CESMM4 & WBS Depth

    • Requirement (since 1 Jul 24): Estimates using ECC Option A must reach WBS Level 7 (Cost Estimating & Cost Control) to align with CESMM4 coding.
    • CW defence: RFQ predates 01 Jul 24; compliant with WBS Rev-12 approved in Implementation Plan.
    • SWC accepted.
    • Status: Closed.
  • G1.3 – First-Principles & Sub-contract Quotations

    • SWC needs granular data to build SWC Bill-of-Quantities (BoQ).
    • CW supplied “Basis of Estimate” with sub-contractor comparison.
    • Example given during 06 Apr 25 meeting: Discrepancy between DGB20 back-fill quantities in quotes vs CW baseline.
    • Status: Closed after submission.

Indirect Cost Clarifications (I-Series)

  • I1.1 – PM & Supervision Breakdown

    • Deliverable: Resource-loaded WBS to Level 7 matching Group 8 template (shows PM labour, margin, Workers-Welfare, risk, Long-Service-Levy).
    • CW initially non-compliant; later provided activity schedule; SWC confirmed sufficiency.
    • Status: Closed.
  • I1.2 – Quantum of PM Costs (\$4.28 M)

    • SWC view: High given heavy subcontracting; especially $9.6k\$9.6k daily burn during site investigations.
    • CW justification:
    • Option A contract shifts more contractual/quality risk to head contractor.
    • Contamination management (waste classification) needs dedicated resources.
    • Compared to Jasper Rd CWM (4 yrs ago) costs are actually lower.
    • CW supplied detailed cost file; SWC accepted explanation with minor reservations.
    • Status: Closed.

Direct Cost Clarifications (DC-Series)

  • Procurement Governance Reminder

    • SWC Procurement Guidelines: ≥3 quotes for each supplier package >\$50k, plus tender analysis whenever lowest quote not chosen.
  • DC1.1 – Sub-contract & Supplier Quotes

    • CW initially cited Option A confidentiality; SWC insisted.
    • Quotes delivered; SWC satisfied.
    • Status: Closed.
  • DC1.2 – Civil Sub-contract Selection (RA Smith vs Jonishan)

    • Delta: Jonishan $3M≈\$3 M cheaper.
    • Non-conformances cited by CW:
    1. No traffic-management provision.
    2. No haulage / tipping of spoil.
    3. Temporary restoration limited to 50 m.
    4. One crew only → longer duration ⇒ higher indirect cost.
    • Revised procurement strategy & tender evaluation matrix submitted; SWC closed.
  • DC1.3 – MSCL Pipe Supply (Pipe Lining & Coating vs Steel Mains)

    • PLC quote $4.75M\$4.75 M vs Steel Mains $3.74M\$3.74 M.
    • Only 2 suppliers on SWC SP panel for this pipe calibre; 3rd quote impossible.
    • CW rationale for higher-priced supplier: “conservative approach”; willingness to revisit at NTP.
    • Documentation provided; Closed.
  • DC1.4 – Installation Rate $7000/Lm\$7000/Lm

    • SWC flagged as excessive (sub-contract lump sum $12.39M\$12.39 M vs CW install price $16.77M\$16.77 M).
    • CW detailed production-rate model:
    • Typical productivity: 3 × 6 m lengths/crew/day ⇒ 18m/day18\,\text{m/day} market rate.
    • Prospect Reserve constrained:
      • CW allowed 10m/day/crew10\,\text{m/day/crew} (two crews) = 20m/day20\,\text{m/day} overall.
      • Concrete-encased sections (>2.5 m deep) drop to 1 length ≈6 m/day.
    • Option A risk premium & contingency added.
    • SWC to evaluate in final estimator’s report.
    • Status: Pending SWC final cost assessment.
  • DC1.5 – Overall Rate $14,116/Lm\$14,116/Lm for 2.4 km

    • SWC couldn’t reconcile with past projects.
    • CW delivered full first-principles workbook (Direct + Indirect + Provisional).
    • SWC to comment in final report.
    • Status: Pending SWC final report.

Environmental & Heritage (DE-Series)

  • DE1.1 – REF & s60 Controls
    • REF = Review of Environmental Factors; s60 = Heritage Act approval.
    • CW confirmed proposal must change due to:
    1. Experienced archaeologist to monitor all excavations.
    2. Soil-amendment works around pine trees on William Lawson Dr, 6 months pre-construction.
    3. Full-time arborist monitoring those excavations.
    • Implication: Additional time & cost risk to be loaded into programme and risk register.
    • Status: Closed after acknowledgement.

Risk Register Clarifications (R-Series)

  • R1.1 – Time & Cost-Loaded R&O Register
    • Spec §3.5.2 requires:
    • Clear distinction between inherent vs contingent risks.
    • Quantified P50P50 and P90P90 cost/float provisions.
    • Transparent basis of estimate (BoE) per risk scenario.
    • CW provided Group-8-style register; still needs:
    • SWC risk overlays.
    • Re-calibrated Groundwater-Sensitive Waste (GSW) & rock excavation allowances.
    • Status: Open – awaiting resubmission.

Key Technical & Contractual Concepts Explained

  • Option A (NEC-ECC)

    • Lump-sum with activity schedule; payment upon completion of listed activities. Shifts quantity risk to Contractor but still requires transparent cost build-up for SWC funding governance.
  • CESMM4 Coding & WBS Level 7

    • Ensures estimates are measurable, comparable, and traceable; Level 7 captures specific resources (labour, plant, material) enabling Earned ValueEarned\ Value & cost-control reporting.
  • Productivity Assumptions

    • Market norm: 3 × 6 m = 18 m/day/crew.
    • CW conservative: 10 m/day/crew due to environmental constraints.
    • Concrete-encased (>2.5 m depth) sections: 6 m/day/crew.
  • Risk Quantification Metrics

    • P50P50: Probability distribution median ⇒ expected cost/time.
    • P90P90: High-confidence allowance; only 10 % chance of exceedance.
    • Registers record ΔCost\Delta\text{Cost} & ΔTime\Delta\text{Time} in daysdays per risk.
  • Scheduling Milestones

    • DABC Approval: 29/08/2529/08/25
    • NOA: Immediately after DABC.
    • NTP: 10/10/2510/10/25 (6 week administrative lead time).

Practical & Governance Implications

  • Accurate alignment between Programme, Activity Schedule and Pricing Schedule is vital for:

    • Monthly payment certification (Option A).
    • Cash-flow forecasting for both SWC and Contractor.
    • SWC DABC funding release.
  • Non-conforming sub-contract bids can’t be chosen merely on price; missing scope items can inflate SWC’s risk if later added by variation. Ethical procurement demands transparent tender evaluation.

  • Environmental & heritage obligations (archaeologist, arborist, soil amendment) not only add cost but can trigger schedule float consumption; must be mirrored in risk & programme to avoid latent claims.

  • High PM cost scrutiny reflects public-sector accountability; Contractor must demonstrate value-for-money while acknowledging increased Option A risk profile.

Numerical / Statistical References & Formulae

  • Pipe-installation cost flagged: Cinstall=16.77M$2396m7000$/mC_{install} = \frac{16.77\,\text{M\$}}{2396\,\text{m}} \approx 7000\,\$/\text{m}.
  • Overall project rate questioned: Ctotal=33.4M$2396m14,116$/mC_{total} = \frac{33.4\,\text{M\$}}{2396\,\text{m}} \approx 14,116\,\$/\text{m}.
  • Productivity allowances:
    • Normal: 18m/day/crew18\,\text{m/day/crew}
    • Allowed: 10m/day/crew10\,\text{m/day/crew}
    • Concrete-encased: 6m/day/crew6\,\text{m/day/crew}.
  • Administrative lag: LagNTP=6weeks=42days\text{Lag}_{NTP} = 6\,\text{weeks} = 42\,\text{days} post-DABC.

Outstanding Actions Summary

  • CW to update Risk Register (SW risks, GSW & rock).
  • SWC to issue final estimator’s report covering DC1.4 & DC1.5 cost reasonableness.
  • CW to upload revised escalation figures (noted in G1.2.3).
  • Confirmation that amended P6 file (with all G-series fixes) is accepted by SWC planning.