SCM 2160 Final Review
Aggregate Planning (S&OP)
What are the different forms of aggregation that takes place during the S&OP?
What are some ways that operations management can use to satisfy demand in an S&OP?
What are the two types of planning strategies discussed in this course? What are their costs and benefits?
What are some constraints you may face in workforce scheduling?
What are three rules you can use to determine the order processing sequence? How do you compare the impact of different rules? (Calculations)
Resource Planning
What is an ERP system? What is IS?
What is dependent demand?
What are the 3 inputs used to develop an MRP? What are the functions of the 3 inputs and the results of the MRP?
What are the 3 lot-sizing rules we discussed, and what are their benefits?
Quality Management
What are the two major components of quality?
What are the two "costs of quality?"
What are the two types of measures that can be used in statistical process control? What charts are used for each?
What does it mean to say your process is in control or out of control?
How do you know which control chart to use?
How do you calculate the UCL, LCL, and CL for each of the SPC charts?
Why do we need to use x-bar chart and R chart together?
Lean Operations
What is the primary goal of the lean philosophy? An operations system that maximizes value by eliminating waste and unnecessary activities.
What are some of the types of waste removed through lean practices? Overproduction, waiting, transportation, overprocessing, inventory, motion, and defects
What are the two key elements of lean supply chains? Why are they important? 1. Closer supplier ties and small batch sizes
What is one of the lean practices or tools we discussed and how does it contribute to waste reduction? Poka-yoke, jidoka and andon
What are some differences between cellular flows and line flows? Cellular flow groups machines by product for flexibility, while line flow arranges them sequentially for high-volume efficiency.
Project Management
What is the project scope and what is scope creep? An interrelated set of activities with a definite start and end that produces a unique outcome using specific resources + The boundaries of the project that define what is included and excluded
What are some of the visualization tools project managers use, and what are their functions? PERT + CPM
What is the "critical path"? The longest path through a project (determines total duration).
What is slack? The amount of time an activity can be delayed without delaying the project.
What are some of the tradeoffs you need to consider when scheduling for projects? Open issues and risks, schedule status