Construction Coordination Meeting Notes: Phase 1 and Phase 2 Status Updates
Venison Cottage and Fitness Center Project Status
Venison and Cottage are currently at the same construction stage, primarily awaiting the completion of fire sprinkler installations.
Interior work updates for Venison and Cottage:
CES is beginning the interior roping process today.
Workers are roping the Romex wiring in both buildings.
The installation sequence begins in the Cottage and then moves to the Fitness building.
Roping is estimated to be completed by the middle of next week.
Electrical boxes have already been installed, which is expected to expedite the roping process.
Operational sequence following fire sprinkler installation:
Completion of fire sprinkler installation.
Formal fire inspection.
Closing up the walls.
Installation of insulation.
Installation of drop ceilings.
Final adjustment of fire sprinkler heads.
Exterior work updates for Venison and Cottage:
The buildings are currently wrapped.
Windows in the Cottage are scheduled for completion either today or by tomorrow.
Exterior progression is currently on hold pending the setting of exterior door frames.
Lathing will commence once the door frames are set and the exterior wrap-up is finished.
Phase 1 Materials, RFIs, and Submittals
The current status of the shower-and-tub change out is as follows:
The change has been submitted as a Change Order (CO).
Approval is pending from Morgan, who has been delayed due to other business.
All necessary components, including the valve and the tub itself, are confirmed to be readily available.
Significant pending submittals for Phase 1 include:
Concrete roof tiles.
Plaster.
Technical verification for membrane installation:
A resubmited design is currently with the design team.
Confirmation is required regarding whether the specified membrane is acceptable for use on OSB (Oriented Strand Board).
Joey is coordinating with the manufacturer to provide an official letter of confirmation.
The manufacturer is located in India.
RFI and door status for Phase 1:
There is an ongoing wait for doors from Pinnacle, who were not present for the status update.
Phase 2 Schedule, Sequence, and Operations
Infrastructure and heavy civil updates for Building A:
Shoring operations are moving forward.
Steel beam delivery and fabrication are scheduled for next week.
Pile driving (piles) is scheduled to begin the week of the 31st.
Utility and sequencing plans:
Coordination for underground utilities will begin once the site reaches subgrade.
The established building sequence remains unchanged: Building A, followed by the Auditorium, then Building B, and finally Building C.
Phase 2 RFIs and documentation:
RFIs from Betty are being processed and entered into ProPort.
One specific RFI involves a potholing requirement.
Building C Structural Infrastructure and MEP Coordination
Building C is designated as a load-bearing structure utilizing light-gauge metal framing.
Critical coordination requirements for Building C:
MEP (Mechanical, Electrical, and Plumbing) coordination must be highly detailed and finalized early.
Structural trusses must sit precisely on top of the walls, meaning the physical location of walls cannot be shifted once established.
There is extensive blocking required within the walls and the truss bases.
Operational warnings regarding blocking interference:
On previous projects, plumbers and other trades have cut or removed structural blocking while attempting to strap their work into place.
Any cutting or removal of blocking must be strictly avoided to maintain structural integrity.
There are specific minimum distances and limitations regarding where blocking can be moved if a conflict arises.
Structural and truss drawings are currently being finalized for submittal so all trades can review them and coordinate their paths.
Because most MEP systems on the project are design-build, there should be sufficient flexibility to maneuver around structural requirements if coordinated in advance.
Safety Protocols and Compliance
As Phase 2 moves into a normal pace of instruction for Building A, safety meetings will be formally incorporated into the weekly schedule.
Safety meeting details:
These sessions will add approximately five minutes to the existing meeting time.
A system for signing off on these safety meetings is currently being developed.
Ongoing compliance requirements:
All teams are required to conduct weekly tailgate meetings while on-site.
Written records of these tailgate meetings must be maintained and submitted for project documentation.
Questions & Discussion
Attendee Question: What is the status of the shower tub change out?
Response: It has been submitted as a Change Order. The team is waiting for Morgan to approve it. The materials (valve and tub) are available.
Attendee Question: Are there any RFIs or submittals we need to worry about?
Response: Concrete roof tiles and plaster are the big submittals. Regarding the membrane on OSB, a letter is being worked on with the manufacturer in India. For Phase 1, the team is still waiting on doors from Pinnacle. For Phase 2, Betty's RFIs are being put into ProPort, including one for potholing.
Kevin (AGCO Metal Framing and Drywall) Comment: He emphasized the need for MEP coordination in Building C because the load-bearing walls and trusses cannot move. He warned other trades not to cut the blocking, as this has been an issue on past projects.
Response: The project lead acknowledged the importance of this and noted that since the MEPs are design-build, they should be able to maneuver around the framing requirements.
Personnel Attendance Note: Josiah (Project Manager) and Steven (Superintendent) from Bunhill were present. Yolanda was also noted as being in attendance.