DAMAGES
under common law, claim is available “as of right”
financial form of compensation
where there is a BREACH OF CONDITION C can also repudiate - this means to terminante the contract so that any future contractual obligations cease
C doesn’t have to repudiate - can continue by AFFIRMING
if they affirm C loses their right to repudiate but can still claim damages
where there is a breach of warranty, C has no right to repudiate and can claim damages only
LIMITS ON DAMAGES
CAUSATION
(but for, remoteness of damage tests)
where c is suing for damages, c may not be compensated for all of their losses which flow from D’s acts
court applies 2 tests
BUT FOR test
But for D’s breach of contract, would C have suffered the loss?
If no , then C can be compensated
if yes, then C will not be compensated
REMOTENESS OF DAMAGE : HADLEY V BAXENDALE
Loss must NOT BE TOO REMOTE- if it is then it is not recoverable. Damages are recoverable from:
i. Loss arising naturally from the breach
ii. Loss which was in contemplation of the parties at the time they made the contract
C’s owned a crankshaft ,it broke and needed to be replaced otherwise the mill would not work and orders would not get fulfilled. The claimants gave the crankshaft to a carrier and said “please take this to Greenwich” so a replacement could be made. Ok said the carriers, but they delayed. The delay meant that the will was idle, did not work and could not fulfil orders. C’s lost money because of this.
There are lots of reasons for a miller to send a crank shaft to a courier. D had no way of knowing that their breach would cause a longer shutdown of the mill , resulting in lost profits. Not liable
VICTORIA LAUNDRY V NEWMAN IND
HADLEY CASE RULE MEANS C’S CANNOT ALWAYS RECOVER ALL THE LOSS THEY HAVE SUFFERED
Vitoria laundry sued
D’s failed to deliver a boiler on time- the boiler was delivered 5 months late. Victoria Laundry was awarded : normal loss of profits but not additional BECAUSE the boiler company never knew about any special contracts that Victoria Laundry had with others
THE HERON II
contract to transport a cargo of sugar
cargo was delayed by 9 days
price of sugar dropped
c sought to recover the difference from D
D argued “damages are too remote”- just as likely market price could go up
since D must have known that market prices fluctuate, any loss would have been in his contemplation
PARSONS V UTTLEY INGHAM
D’s installed a pig nut hopper
ventilation hatch had been sealed during transport
nuts went mouldy
nuts were fed to pigs
pigs got sick and some died
c’s sued d’s
CoA (denning) allowed claim
WELLESLEY PARTNERS V WITHERS
Look at what is in reasonable contemplation rather than what was reasonably foreseeable?
EXPEINCE HENDIRX CASE