UNIT 3 PART 1

Pacing
  • Definition: Measuring distances by counting the number of normal steps or paces.

  • Key Relationships:

    • 1 step=1 pace1\text{ step} = 1\text{ pace}

    • 1 stride=2 paces1\text{ stride} = 2\text{ paces}

  • Pacing Formulas:

    • Pace Factor (PF)=Known LengthMean Number of Paces\text{Pace Factor (PF)} = \frac{\text{Known Length}}{\text{Mean Number of Paces}}

    • Paced Distance (PD)=Pace Factor×Mean Number of Paces\text{Paced Distance (PD)} = \text{Pace Factor} \times \text{Mean Number of Paces}

    • Relative Precision (RP)=∣Tape Distance−Pace Distance∣Tape Distance\text{Relative Precision (RP)} = \frac{|\text{Tape Distance} - \text{Pace Distance}|}{\text{Tape Distance}}

  • Factors Affecting Pace Length:

    • Speed of pacing

    • Roughness of ground

    • Weight of clothing and shoes

    • Fatigue of the pacer

    • Slope of terrain (going downhill produces fewer steps)

    • Age and sex of individual

  • Mechanical Counters:

    • Passometer: Automatically registers the number of paces.

    • Pedometer: Automatically calculates distance based on an input pace factor.

Taping
  • Definition: Measuring horizontal distances by stretching a calibrated tape between two points.

  • Composition of Taping Party:

    1. Head Tapeman: Carries the forward end of the tape and holds the zero mark.

    2. Rear Tapeman: Holds the trailing end of the tape at the starting point.

    3. Recorder: Records distance measurements and field notes.

    4. Flagman: Directs alignment and marks measured points.

  • Types of Tapes:

    • Steel Tape: Standard surveying tape; prone to corrosion.

    • Invar Tape: Made of 35%35\% nickel and 65%65\% steel; has a very low coefficient of thermal expansion, but is expensive.

    • Lovar Tape: Properties and cost fall between steel and Invar tapes.

    • Other Tapes: Linen/cloth, non-metallic, fiberglass, wires, builder's, phosphor bronze, and nylon-coated steel tapes.

  • Standard Conditions for Steel Tapes:

    • Temperature: 20 ∘C20\,^\circ\text{C} (68 ∘F68\,^\circ\text{F})

    • Pull/Tension: 50 N50\,\text{N} (10 lbs10\,\text{lbs})

    • Support: Supported throughout its entire length.

Taping Errors & Slope Corrections
  • Sources of Taping Errors: Incorrect tape length, temperature variation, non-standard pull, sag due to weight/wind, poor alignment, tape not horizontal, improper plumbing, faulty marking, and incorrect reading.

  • Slope Taping Formulas:

    • Horizontal distance (dd) from slope distance (ss):
      d=s⋅cos⁡(θ)d = s \cdot \cos(\theta)
      d=s2−h2d = \sqrt{s^2 - h^2}

    • Slope Corrections (ChC_h) (Always subtracted from slope distance):

    • Gentle Slope (θ<11.31∘\theta < 11.31^\circ):
      Ch=h22sC_h = \frac{h^2}{2s}

    • Steep Slope (11.31∘≤θ≤16.7∘11.31^\circ \le \theta \le 16.7^\circ):
      Ch=h22s+h48s3C_h = \frac{h^2}{2s} + \frac{h^4}{8s^3}

    • Very Steep Slope (θ>16.7∘\theta > 16.7^\circ):
      Ch=s(1−cos⁡(θ))C_h = s(1 - \cos(\theta))

Taping Corrections
  • Incorrect Tape Length Correction (ClC_l):

    • Tape Correction: C=True Length−Nominal LengthC = \text{True Length} - \text{Nominal Length}

    • Total Correction: Cl=C×Measured LengthNominal LengthC_l = C \times \frac{\text{Measured Length}}{\text{Nominal Length}}

    • Application Rules:

    • Measuring: If tape is too long, add (++); if too short, subtract (−-).

    • Laying Out: If tape is too long, subtract (−-) ; if too short, add (++).

  • Temperature Correction (C<em>tC<em>t):
    C</em>t=α⋅L⋅(T<em>m−T</em>s)C</em>t = \alpha \cdot L \cdot (T<em>m - T</em>s)

    • α\alpha = Coefficient of thermal expansion (0.0000116 ∘C−10.0000116\,^\circ\text{C}^{-1} for steel)

    • LL = Measured length

    • TmT_m = Measurement temperature

    • TsT_s = Standard temperature (20 ∘C20\,^\circ\text{C})

  • Pull Correction (C<em>pC<em>p):
    C</em>p=(P<em>m−P</em>s)LAEC</em>p = \frac{(P<em>m - P</em>s)L}{AE}

    • PmP_m = Applied pull during measurement

    • PsP_s = Standard pull (50 N50\,\text{N})

    • AA = Cross-sectional area of tape

    • EE = Modulus of elasticity

  • Sag Correction (C<em>sC<em>s) (Always subtracted):
    C</em>s=W2L24P2=w2L324P2C</em>s = \frac{W^2 L}{24 P^2} = \frac{w^2 L^3}{24 P^2}

    • WW = Total unsupported weight of tape

    • ww = Weight per unit length (W=w⋅LW = w \cdot L)

    • PP = Applied tension/pull

  • Normal Tension (PnP_n):

    • The tension required to equate pull elongation with sag shortening (C<em>p=C</em>sC<em>p = C</em>s), eliminating the combined error of sag and pull.