Capacity Planning and Heat Map UI for Pharmaceutical Equipment Manufacturing

Pharmaceutical Equipment Manufacturing Overview

  • The manufacturing focus is on specialized equipment for the pharmaceutical industry, specifically stainless steel containers used in medicine production.

  • Production timelines for individual units of equipment generally range from 22 to 33 weeks.

  • Orders must be managed and scheduled to determine the specific week of shipment to a client.

  • The manufacturing process involves significant fabrication activities similar to general steel construction (such as making a steel door). These activities include:

    • Cutting

    • Welding

    • Bending

    • Buffing

    • Fitting

  • The primary scheduling objective is to allow users to select an order and assign it to a specific production week to determine shipment feasibility.

Capacity Load and Planning

  • The capacity planning system evaluates the load placed on manufacturing resources when an order is scheduled.

  • There are three fundamental manufacturing processes monitored for capacity load:

    • Welding

    • Buffing

    • Fitting

  • Scheduling is managed via an internal "Capacity BOM" (Bill of Materials). This internal mechanism calculates the necessary resources required for a finished good based on the selected manufacturing week.

  • When a user selects a target completion date (e.g., the last week of August), the system automatically calculates the impact on the capacity for welding, buffing, and fitting for that period.

  • Initial planned capacity is based on available manpower. Example weekly capacity thresholds include:

    • Welding: 35 hours35\,\text{hours}

    • Buffing: 30 hours30\,\text{hours}

    • Fitting: 90 hours90\,\text{hours}

Capacity Heat Map and Visual Indicators

  • The system utilizes a heat map UI to provide immediate visual feedback on resource utilization when an order is assigned to a week.

  • The heat map acts as a tool to identify potential bottlenecks in the manufacturing schedule.

  • Utilization is categorized using a color-coded framework based on the percentage of planned capacity consumed:

    • Green: Load is less than 50%50\% of total capacity (Load<50%\text{Load} < 50\%).

    • Yellow: Load is between 50%50\% and 75%75\% of total capacity (50%≤Load≤75%50\% \le \text{Load} \le 75\%).

    • Red: Load exceeds 75%75\% of total capacity (Load>75%\text{Load} > 75\%).

  • Updating the schedule triggers an immediate update to the heat map, revealing how new orders impact specific weeks and resource types.

System Mechanics and UI Development

  • The internal mechanics of the system link the orders to the capacity BOM to generate the required data for the UI.

  • While the user interface displays the heat map and order lists, the underlying internal logic (crude internal mechanics) handles the calculations of load versus capacity.

  • UI development requires understanding how order selection translates into resource consumption across the three primary fabrication categories.