Capacity Planning and Heat Map UI for Pharmaceutical Equipment Manufacturing
Pharmaceutical Equipment Manufacturing Overview
The manufacturing focus is on specialized equipment for the pharmaceutical industry, specifically stainless steel containers used in medicine production.
Production timelines for individual units of equipment generally range from to weeks.
Orders must be managed and scheduled to determine the specific week of shipment to a client.
The manufacturing process involves significant fabrication activities similar to general steel construction (such as making a steel door). These activities include:
Cutting
Welding
Bending
Buffing
Fitting
The primary scheduling objective is to allow users to select an order and assign it to a specific production week to determine shipment feasibility.
Capacity Load and Planning
The capacity planning system evaluates the load placed on manufacturing resources when an order is scheduled.
There are three fundamental manufacturing processes monitored for capacity load:
Welding
Buffing
Fitting
Scheduling is managed via an internal "Capacity BOM" (Bill of Materials). This internal mechanism calculates the necessary resources required for a finished good based on the selected manufacturing week.
When a user selects a target completion date (e.g., the last week of August), the system automatically calculates the impact on the capacity for welding, buffing, and fitting for that period.
Initial planned capacity is based on available manpower. Example weekly capacity thresholds include:
Welding:
Buffing:
Fitting:
Capacity Heat Map and Visual Indicators
The system utilizes a heat map UI to provide immediate visual feedback on resource utilization when an order is assigned to a week.
The heat map acts as a tool to identify potential bottlenecks in the manufacturing schedule.
Utilization is categorized using a color-coded framework based on the percentage of planned capacity consumed:
Green: Load is less than of total capacity ().
Yellow: Load is between and of total capacity ().
Red: Load exceeds of total capacity ().
Updating the schedule triggers an immediate update to the heat map, revealing how new orders impact specific weeks and resource types.
System Mechanics and UI Development
The internal mechanics of the system link the orders to the capacity BOM to generate the required data for the UI.
While the user interface displays the heat map and order lists, the underlying internal logic (crude internal mechanics) handles the calculations of load versus capacity.
UI development requires understanding how order selection translates into resource consumption across the three primary fabrication categories.