In-Depth PMBOK® Study Notes
PMBOK® Overview
- PMBOK® (Project Management Body of Knowledge) defines essential project management processes and practices and serves as a guide for project managers.
Introduction to PMBOK®
- Purpose: A summary for preparation for the PMP® exam, not an introductory guide.
- Content Summary: 47 processes summarized; gaps exist in projects, programs, organization, and ethics sections.
- Use: Intended as a study aid alongside the original PMBOK® and other resources. Available under the Creative Commons license.
Project Management Concepts
- Project: Temporary endeavor to create a unique product, service, or result.
- Emphasizes defined beginning and end.
- Outputs may last beyond project duration.
- Program: A group of related projects managed collectively.
- Portfolio: A collection of projects and programs to achieve strategic business goals.
- Organizational Project Management (OPM): Framework for executing strategic objectives.
- Project Management Office (PMO): Standardizes project governance (Supportive, Controlling, Directive).
Project Integration Management
- Develop Project Charter: Authorizes project and PM's authority; formalizes project initiation.
- Inputs: Project SOW, business case, agreements, organizational process assets.
- Outputs: Project charter.
Project Stakeholder Management
- Identify Stakeholders: Engaging everyone impacted by the project.
- Tools: Stakeholder analysis.
- Outputs: Stakeholder register detailing roles, expectations, influence, etc.
Planning Process Group
Develop Project Management Plan: Integrates all subsidiary plans for project execution and control.
- Inputs: Project charter, outputs from other processes.
- Outputs: Project Management Plan (PMP).
Plan Scope Management: Defines how scope will be managed, validated, and controlled.
- Outputs: Scope management plan, requirements management plan.
Collect Requirements: Gathering detailed stakeholders’ needs.
- Outputs: Requirements documentation, traceability matrix.
Define Scope: Detailed description of project deliverables and boundaries.
- Outputs: Project scope statement, project document updates.
Create WBS: Breaks project work into manageable pieces.
- Outputs: Scope baseline, project document updates.
Project Time Management
- Plan Schedule Management: Framework for managing project schedules, including contingency planning.
- Outputs: Schedule management plan.
- Define Activities: Identifying and detailing activities for deliverables.
- Outputs: Activity list, activity attributes, milestone list.
- Sequence Activities: Establishes relationships between activities.
- Outputs: Project schedule network diagram.
- Estimate Activity Resources: Determining required resources for activities.
- Outputs: Activity resource requirements, resource breakdown structure.
- Estimate Activity Durations: Estimating how long activities will take.
- Outputs: Activity duration estimates.
- Develop Schedule: Constructing a schedule model for the project.
- Outputs: Schedule baseline, project schedule.
Project Cost Management
- Plan Cost Management: Procedures for managing costs throughout the project.
- Outputs: Cost management plan.
- Estimate Costs: Estimating costs for project work.
- Outputs: Activity cost estimates and basis for estimates.
- Determine Budget: Aggregating costs to create the cost baseline.
- Outputs: Cost baseline, project funding requirements.
Project Quality Management
- Plan Quality Management: Defining quality standards and how to achieve them.
- Outputs: Quality management plan, quality metrics.
- Perform Quality Assurance: Auditing quality control processes to ensure adherence.
- Outputs: Change requests, project management plan updates.
- Control Quality: Monitoring and controlling project quality processes.
- Outputs: Quality control measurements, validated changes.
Project Human Resource Management
- Plan Human Resource Management: Staffing requirements and acquisition plan.
- Outputs: HR management plan.
- Acquire Project Team: Assembling the project team based on the HR plan.
- Outputs: Project staff assignments, resource calendars.
- Develop Project Team: Enhance team performance through training and development.
- Outputs: Team performance assessments.
- Manage Project Team: Influencing team dynamic, performance appraisal, conflict resolution.
- Outputs: Change requests, project management plan updates.
Project Communications Management
- Plan Communications Management: How to communicate effectively with stakeholders.
- Outputs: Communications management plan.
- Manage Communications: Distribution of information and engagement with stakeholders.
- Outputs: Project communications, updates to project documents.
Project Risk Management
- Plan Risk Management: Developing a risk management strategy tailored to the project.
- Outputs: Risk management plan.
- Identify Risks: Systematic identification of risks impacting the project.
- Outputs: Risk register.
- Perform Qualitative Risk Analysis: Assessing risks based on probability and impact.
- Outputs: Updated project documents.
- Perform Quantitative Risk Analysis: Detailed analysis of risk, utilizing data and models.
- Outputs: Project documents updates.
- Control Risks: Implementing responses and tracking risks throughout the project.
- Outputs: Change requests, project documents updates.
Project Procurement Management
- Plan Procurement Management: Outline how procurement will be managed throughout the project.
- Outputs: Procurement management plan, statement of work.
- Conduct Procurements: Selecting vendors and managing procurement processes.
- Outputs: Selected sellers, agreements.
- Control Procurements: Overseeing seller performance and compliance with agreements.
- Outputs: Work performance information, change requests.
Project Stakeholder Management
- Plan Stakeholder Management: Strategies for engaging stakeholders effectively.
- Outputs: Stakeholder management plan.
- Manage Stakeholder Engagement: Working with stakeholders to build support, resolve issues.
- Outputs: Issue log, change requests.
Closing Process Group
- Close Project or Phase: Formal closure with documentation of lessons learned and release of resources.
- Outputs: Final deliverables, updates to organizational process assets.
- Close Procurements: Finalizing all procurement activities and agreements.
- Outputs: Closed procurements, OPA updates.