Module 2 Notes: Scope Management and WBS (PMBOK 6th Edition)
Module Overview
- Focus: understanding project scope, scope management, and the scope baseline (scope statement, WBS, and WBS dictionary) within the PMBOK framework.
- Context: Part of MGMT 6205 Project Cost Management (Fanshawe) taught by Lawrence Kinlin.
- Structure covered in this module:
- Review from the previous module
- Project management process groups
- Scope management
- Scope baseline components: scope statement, WBS, and WBS dictionary
- Homework and evaluations
- Emphasis on how scope interacts with cost management and overall project planning.
PMBOK 6th Edition – 10 Knowledge Areas (summary)
- Integration: Includes processes/activities to identify, define, combine, unify, and coordinate the various project management processes.
- Schedule: Processes to manage timely completion of the project.
- Quality: Processes for planning, managing, and controlling quality requirements to meet stakeholders’ expectations.
- Communication: Processes for effective information exchange among stakeholders.
- Scope: Processes to ensure the project includes all the work required, and only the work required, to complete the project successfully.
- Cost: Processes involved in planning, estimating, budgeting, financing, funding, managing, and controlling costs to complete the project within the approved budget.
- Resource: Processes to identify, acquire, and manage the resources needed for successful completion.
- Risk: Processes of risk management planning, identification, analysis, response planning, response implementation, and monitoring risk on a project.
- Stakeholder: Identify stakeholders, analyze their expectations and impact, and develop engagement strategies.
- Note: These knowledge areas map to the project life cycle and are interrelated with the process groups.
PMBOK Process Groups and Project Life Cycle
- Process groups define the phases of work that occur across the project life cycle.
- Key groups:
- Defining
- Planning
- Executing
- Closing
- Overlapping/interactive nature:
- Planning processes extend nearly to the end of the project.
- Monitoring and Controlling processes run throughout the project duration.
Knowledge Area 5 – Scope Management
- Definition: Scope management includes the processes required to ensure the project includes all the work required, and only the work required, to complete the project successfully.
- Primary focus: Defining and controlling what is and is not included in the project.
- Important ordering note: Scope should be defined before estimating costs and developing the budget in Cost Management.
Relation to Cost Management
- Project scope is a key input into Cost Management.
- The Project Management Plan is an input to all cost processes and includes all knowledge area plans, but most importantly, the Scope Baseline.
- The Scope Baseline, Schedule Baseline, and Cost Baseline are part of the Project Management Plan.
- Change control procedures govern changes to the scope baseline.
Components of the Project Management Plan
- Scope Management Plan
- Requirements Management Plan
- Schedule Management Plan
- Cost Management Plan
- Quality Management Plan
- Resource Management Plan
- Communications Management Plan
- Risk Management Plan
- Procurement Management Plan
- Stakeholder Engagement Plan
- Baselines and outputs:
- Scope Baseline
- Schedule Baseline
- Cost Baseline
- Other components:
- Change Management Plan
- Configuration Management Plan
- Performance Measurement Baseline
- Project Life Cycle Description
- Development Approach
SCOPE BASELINE
- Definition: The approved version of a scope statement, WBS, and its associated WBS dictionary that can be changed only through formal change control procedures and is used as a basis for comparison to actual results.
- Components (three):
1) Scope Statement
2) Work Breakdown Structure (WBS)
3) WBS Dictionary - Purpose: Provides the baseline against which project performance is measured.
1) Scope Statement (Scope of Work)
- Contents typically include:
- Key objectives of the project
- Expected outcomes of the project
- An abbreviated description of the scope (the work to be completed)
- Introduction and background of the project
- An introductory technical description
- A high-level timeline or estimated duration
- Major milestones
- Purpose: Communicate what is in and out of scope at a high level.
2) Work Breakdown Structure (WBS)
- Definition: A hierarchical outline (map) identifying products and work elements involved in a project.
- Purpose: Defines the relationship of the final deliverable (the project) to its sub-deliverables and to work packages.
- Best suited for: Projects with tangible deliverables rather than purely process-oriented projects.
- Levels:
- Level 1: Project Level
- Level 2: Major Deliverable Level
- Level 3: Sub Deliverable Level
- Level 4: Lowest Sub Deliverable Level – Work Packages
- Key concepts:
- WBS is a decomposition of the project scope into manageable components.
- Work Packages (WP) are the lowest-level deliverables represented in the WBS.
2) WBS – Details About Work Packages
- The lowest level deliverable in the WBS is a work package (WP).
- Characteristics:
- It is the lowest level in every WBS path and represents a deliverable result.
- Each WP has one owner and acts as a miniature project.
- WP includes milestones and is trackable.
- WP describes the 'what' (deliverables), not the 'how' (methods).
- Activities within a WP describe the 'how' (resources, duration, cost).
- Note: Activities are usually not shown as boxes in a WBS diagram.
2) WBS – Naming and Structure Rules
- WBS elements should be written as NOUNS (e.g., "Design UI" would be a WP if treated as a deliverable; however, specific guidance: WP are nouns; activities are verbs).
- Activities inside a WP must be written as VERBS and describe how the WP will be accomplished.
- 100% Rule: The sum of the child elements at a given level equals the parent element’s value.
- Example: 5,000+2,000+2,000=9,000
- In cost terms, the total of child costs equals the parent cost: C{ ext{parent}} = rac{}{}
ext{or more generally } C{ ext{parent}} = ig( ext{sum of } C_{ ext{child}}ig).
- WBS Codes:
- Project code: 1.0 for the overall project
- Major deliverables: 1.2,1.3,1.4
- Sub-deliverables (blue): supporting deliverables (e.g., folders within folders)
- Lowest level deliverables (green): work packages
3) WBS Dictionary
- Purpose: Provides detailed descriptions for each WBS element.
- Format: Typically shown as a table with fields for each element.
- Example fields:
- Work Package ID
- Work Package Name
- Responsible Organization/Individual
- Work Package Description / Statement of Work
- Acceptance Criteria
- Deliverables
- Duration
- Cost
- Due Date
- Dependencies
- Approvers
- Resources Assigned
- Assumptions
- Sample entry (illustrative):
- Project Name: Customer Help Desk
- Work Package ID: 1.4.1.1
- Work Package Name: Designed User Screen
- Assigned To: Dave Litten
- Date Assigned: 7/30/09
- Estimated Cost: 3,800.00
- Description: Using the customer’s User Screen Specification, a new top-level layout design is to be created. A non-functioning layout demonstrator will be prepared to collect feedback. A fully functional prototype will be created for client review/approval.
- Acceptance Criteria: Sign-off from key stakeholders and responsible departments
- Due Date: 15/9/09
- Resources: IT Systems, System Analysts, Engineering
- Dependencies, Approvers, Group/Dept, Account Code, etc.
- More in the example includes: System Requirements Document, Business Requirements Document, and associated roles and timelines.
WBS in MS Project – Practical Creation
- How to build hierarchical WBS in MS Project (.mpp):
- Enter WBS elements in the Task Name column.
- Use Indentation to create the hierarchy.
- Do NOT enter WBS codes manually; MS Project will generate codes based on order/indentation.
- Visuals:
- Summary tasks are shown with bold titles; detailed tasks appear as bars only if given durations.
- A WP is a summary task at the lowest level with its own set of activities underneath.
- Important rule: Activities reside ONLY within a Work Package.
Common WBS Practices and Pitfalls
- Common error: Activities placed outside of a WP (i.e., directly under a sub-deliverable rather than inside a WP).
WBS Dictionary – Example Format and Content
- The dictionary provides per-element descriptions; shown in table format on the slides.
- It elaborates each element’s scope, criteria, and attributes to avoid ambiguity.
Additional Notes on WBS and Baselines
- The WBS, scope statement, and WBS dictionary together define the Scope Baseline.
- The Scope Baseline is used to measure performance and control scope changes through formal change control.
Homework and Evaluations (Module 2)
- Readings for Module 3 as listed in Course Overview.
- Complete Module 2 learning activities in FOL (including Module 2 Tutorial).
- Quiz 1 details in FOL.
- Individual presentation: must be presented before the week of Module 14.
- In-person class: sign up to present during an upcoming class.
- Online class: use Virtual Classroom/Bongo.
References
- Kerzner, Harold (2017). Project Management, Twelfth Edition.
- Larson, Eric W., Gray, Clifford F. (2018). Project Management, The Managerial Process (Seventh Edition).
- Project Management Institute (2017). A Guide to the Project Management Body of Knowledge (Sixth Edition).
- Project Management Institute (2021). A Guide to the Project Management Body of Knowledge (Seventh Edition).