Barrage across Tungabhadra River – Project Significance & Preliminary Designs
Project Significance
- Local representatives requested a diversion structure across the Tungabhadra River near Valaballary to guarantee reliable drawl for three Lift-Irrigation Schemes (LIS):
- Channabashaveshwara LIS (Existing – "E")
- Thimmapur LIS (Under Construction – "U/C")
- Siddalingeshwara LIS (Proposed – "P")
- Without a storage/diversion structure, cumulative abstraction for these schemes would exceed the river’s free-flow availability at lean stages.
- Two technical alternatives were examined:
- Option 1 – Barrage (gated, low-level storage)
- Option 2 – Weir (ungated, fixed-crest).
Comparative studies favoured the gated barrage for precise regulation and larger live storage.
Geographical Location
- Site: Up-stream of Timmapur-LIS drawl point, downstream reach of Tungabhadra River at Valaballary village, Sindhanur Taluk, Raichur District, Karnataka.
- Coordinates: Latitude 15∘46′2.30′′ N; Longitude 76∘57′14.04′′ E.
- Survey of India Topo-sheets: 57 A/14 & 57 A/15 (Map scale 1:50000).
Accessibility
- Roads
- State Highway 128 links Sindhanur with Bengaluru, Hubballi, Belagavi, Vijayapura (Bijapur), Kalaburagi (Gulbarga), Hospet, and Raichur.
- Barrage approach road length: 1020 m (to be freshly constructed, revenue land).
- Rail
- Nearest junction: Kupgal (KGL) on South-Central Railway, ≈32 km from Sindhanur; barrage is ≈25 km from Sindhanur.
- Airports
- Hubballi ≈220 km; Dharwad ≈219 km.
- SOI topo-sheets mosaicked to produce a composite planning map at 1:50000.
- Figure 2-2 marks service-area sheets 57 A/14 (D43E14) & 57 A/15 (D43E15).
Scheme Components (Common to Either Option)
- Diversion structure itself (Barrage/Weir).
- Fabrication, supply and commissioning of: gates, stop-logs, hoisting arrangements.
- Two Nos. monorail lifting hoists (5-ton each).
- Store rooms (2 Nos.).
- Approach road ((1020\,\text{m})).
- O&M for five years.
Option 1 – Barrage (Selected)
Hydrologic & Hydraulic Parameters
- Type: Low-level gated barrage with vertical lift radial/sliding gates.
- Number of vents: 98 (each 5m×3m).
- Sill (Crest) Level: 337.000 m.
- Full Reservoir Level (FRL): 340.000 m.
- Height of gate: 3.0 m (sill to FRL).
- Design discharge: 1470m3s−1 (through vents at FRL).
- Observed High-Flood Level (HFL): 350.163 m (later refined to 350.198 m).
- Total length (between abutments): 587 m.
- Stop-log units: 5m×0.5m; quantity 588.
Structural Components
- Abutments: Left & Right Bank mass-concrete blocks tied with cut-off walls.
- Cut-off walls: Up-stream (U/S) & Down-stream (D/S) on both banks, protecting against piping.
- Aprons: U/S & D/S to absorb scour energy.
- Wing & Return walls: Channel transition and anti-erosion.
- Piers: Reinforced-concrete pier noses support gates & provide roadway/cat-walk.
- Cat-walk: Operable deck for inspection, gate operation & hoist beam.
- Approach Embankments: Earth bunds to integrate structure with natural ground.
- All calculations follow latest BIS Codes (IS 4410, IS 7365, IS 4997, etc.) with allowable‐stress method and flood-frequency checks.
Cost Estimate (Option 1)
- Civil, mechanical & electrical works aggregated cost: Rs.451.50 lakh (≈ Rs.4.515 crore).
- Detailed head-wise breakup enclosed in Annexure 1 (not provided in transcript).
Lifting Hoist System
- Configuration: Single-girder monorail crane traversing along the barrage deck; limited to longitudinal (forward/back) motion + vertical lift.
- Mechanisms:
- Hoist with wire-rope, hook, pulley block.
- Trolley travelling mechanism along I-beam top flange.
- Crane end-carriage integrated with cat-walk steel framework.
- Advantages: Compact, light-weight, minimal lateral load, economical for linear gate arrays.
- Provision: 2 units, each 5ton SWL (Safe Working Load).
- Power: Sourced from existing KPTCL sub-station at Timmapur LIS.
- Budget: Rs.9.76 lakh (supply, installation, testing, commissioning).
Operation & Maintenance
- Five-year O&M lump-sum: Rs.0.52 lakh (covers routine inspection, gate greasing, hoist upkeep, minor civil repairs).
Land Acquisition
- Total land required: 1.10 ha (revenue dry land encompassing barrage footprint, two store rooms & 1.02-km approach road).
- Compensation rate: Rs.30.00 lakh per ha (per state norms).
- Allocation: Rs.33.00 lakh (rounded, Annexure 4).
Option 2 – Weir (Only Reconnaissance Level Mentioned)
- Ungated fixed crest; would not guarantee regulated head for simultaneous operation of three LIS, therefore set aside at concept stage.
Inter-linkages & Wider Relevance
- Supports irrigation modernisation in Tungabhadra left-bank command, enhancing reliability for approx. Sindhanur–Gangavathi paddy belt.
- Reduces energy cost for individual LIS by allowing lower static head due to raised FRL.
- Aligns with state objective of conjunctive use & equitable distribution across Taluks.
- GIS & topo inputs form baseline for future sedimentation, flood routing & environmental studies.
Ethical / Practical Notes
- Acquisition confined to dry revenue land to minimise displacement; no habitation submergence reported.
- Environmental clearance will still require assessment of aquatic ecology due to raised FRL.
- Design must ensure fish-pass or ecological sluice (not discussed in transcript – flagged for future study).