Notes: Pre-Contract Administration & Tendering in Landscape Architecture
Pre-Contract Administration: Introduction and Stage Overview
Prepare for Test: Date ; Time ; Venue: ; Official (Closed), Non-Sensitive
Stages of Landscape Project
Stage : Design Process
Sub-Stages: Concept Design; Design Development; Detail Design
Stage : Project Contract Administration
Sub-Stages: Tender – Softscape & Hardscape (Pre-Contract Administration); Contract Admin / Project implementation; Defects liability Period
Awarding of Contract intersection with design stages
Concept Design, Design Development, Design Details, Tender – Softscape & Hardscape (Pre-Contract Administration), Contract Admin / Project implementation, Defects liability Period
Contract Administration: two main teams engaged in a Landscape Contract
main Teams: 1) Design Team 2) Contractor Team
Pre-Contract Administration: Tender
The two types of tender called in Singapore are: Open Tender and Pre-qualified Tender
Tendering process: overview of tendering concepts and process flows
Objectives of tendering: competitive pricing, qualification of bidders, and avoidance of malpractice
Key terms: tender, contract, and their relationship
Stages of Landscape Project: Design Process and Tendering Context
Stage : Design Process
Concept Design (early ideas and spatial organization)
Design Development (refinement of schemes, layouts, and integration with site constraints)
Detail Design (construction details, materials, and finishes)
Stage : Project Contract Administration
Tender (Pre-Contract Administration): invitation to bid, reception of bids, initial evaluation
Contract Administration / Project implementation: post-award management, site supervision, progress, quality control
Defects liability Period: warranty/planned remediation after project completion
Awarding of Contract reflects progression through Concept Design, Design Development, and Tender Details toward formal contract execution
Tendering: Types, Pros/Cons, and Documentation
Tender types in Singapore
Open Tender
Pre-qualified (Selective/Close Tender)
Open Tender: advantages and disadvantages
Advantages: , ,
Disadvantages: , , ; difficult to anticipate bidder numbers (0 to many)
Close/Selective Tender: advantages and disadvantages
Advantages: ,
Disadvantages: ,
Tender Documentation: Parts and Interrelationship
Parts of Tender Document
Form of Tender
Conditions of Contract
Tender Drawings
Specifications
Specifications are written documents detailing what/how the work is to be done
Bill of Quantities
The 3 main documents that form a Tender Document
a) Tender Drawings (Illustrative)
b) Specifications (Qualitative)
c) Bills of Quantities (Quantitative)
Interrelationship between Specs & Drawings
Specifications are verbal/written; drawings are graphic; they must reinforce one another
Working drawings (contract drawings) are the quantitative, graphic representations showing extent of work
Working drawings contain symbols, numbers, dimensions, and notes identifying products/systems; finish/opening/schedules are often part of drawings
The information in working drawings must tally with the specifications; they should complement, not repeat
Do not describe in words what is drawn; avoid inaccuracies and inconsistencies
Grey areas can occur; conflicts resolved case-by-case between landscape architect and contractor
Quality and Specifications
Quality is defined as conformance to requirements; in landscape practice, quality ensures work aligns with intended design intent
Specifications must be properly vetted and unambiguous; lack of comprehensive specs leads to design, cost, quality, and legal issues
Specifications: Types, Vetting, and Plant Specifications
4 TYPES OF SPECIFICATIONS
1. Performance specification (Design & Build): end result specified; method left to contractor
2. Reference specification: standard for material/execution/testing; e.g., PSB (materials), AVA (plants/soil)
3. Proprietary specification: specifies a particular product/item to be installed
4. Descriptive specification: thorough, logical description of materials and workmanship standards
Plant specifications (Trees)
Correct names: botanical names (common names optional)
Plant size: overall height; trunk girth/calliper; canopy spread
Additional descriptions: number of branches, sculptural form, size classification (Instant, Standard/Heavy, Standard/Extra-Heavy), trunk type (single/multi), trunk alignment, root-ball size, transplant method, delivery condition
Palms specifications
Correct names: botanical names; common names optional
Plant size: overall height; clear trunk height for single-trunk palms
Descriptions by species: spread of leaves/crown, number of leaves/fronds, multi-trunk minimum number, trunk straightness, root-ball size, transplant method, delivery condition
Shrubs specifications
Correct names: botanical names; common names optional
Plant size: overall height; spread of leaves/branches
Species-specific descriptors: bushy condition/shape, pot size, established stocks, minimum stems/leaves, minimum numbers, transport requirements
Cost Estimation and Bill of Quantities
Factors governing cost estimates for Landscape Works
Pre-growing
Ground Preparation
Planting (Softscape)
Construction & Installation (Hardscape)
Maintenance & Defects Liability Period
Other works
Bill of Quantities (BOQ) overview
Example/template provided for softscape works (illustrative)
Typical BOQ structure includes: description, plant size, spacing, unit, unit quantity, price, total amount
Softscape Works BOQ (illustrative)
Sections: TREES, PALMS, SHRUBS & GROUND-COVERS, TURF, SOIL MIX
Data columns: HT (height), Girth (circumference/diameter), Overall Height, Spacing, Unit, Qty, Price, Total
Tendering Process: Stages, Deadlines, and Evaluation
Two main stages in Tendering
Pre-tender preparation & notification
Final checking/vetting of tender documents; notification to relevant parties (date of calling, closing, opening)
Determine categories of landscape contractors to invite/comply
Tendering Stage 1: Calling of Tender
Consultants’ programme/schedule
Main Contract construction schedule
Client/consultant request; site conditions requirements
Ensure three main sections of tender/contract documents are completed: Contract Drawings (Illustrative), Specifications (Qualitative), Bills of Quantities (Quantitative)
Tendering Stage 1: Tender period and site activities
Site briefing; corrigendum issues; enquiries; tender questionnaires; closing of tender is strict
Tendering Stage 2: Opening and evaluation
Opening of tenders; independent party witnesses submissions
Compilation of contract documents; signing and distribution
Important timing notes
Closing time for tender return is fixed; late submissions are rejected
If submitting online via Gebiz, closing time is at 12:00 am; hardcopy is usually 12:00 pm noon
Tender evaluation and disqualification reasons
Incomplete tender; amended specifications; false information on BCA standings
Refusal to clarify; prior track records; evidence of malpractice
Tender vs Contract: Key Differences and Purposes
Definitions
Tender: Formal notification of procurement needs and invitation of bids; request for quotations to obtain competitive bids
Contract: Legal document binding the two parties after tender; outlines terms, timelines, payment terms, etc., for a defined work/project/goods
Purposes
Tender: To obtain competitive quotations from multiple suppliers/contractors
Contract: To formalize the agreed terms and conditions under which the work will be performed
Relationship
Tender leads to the selection of a bidder; contract is executed based on the tender outcome
Contract Administration: From Award to Documentation
Contract Administration responsibilities
Award of Landscape Works Contract to Landscape Contractor
Landscape Contractor to implement landscape works as per contract; variations and additional works governed
Landscape Architect / Landscape Designer / Project Manager to administer/manage the project from inception to completion
Key Contract Document Components
Form of Tender
Conditions of Contract
Contract Drawings
Specifications
Bill of Quantities
Example contract structure highlights
Parties: Landscape Contractor and Customer; defined addresses and premises
4. Changes in the Services: written changes; potential additional charges; schedule modifications
3. Term and Schedule: start date, substantial completion, full completion; subject to weather and client changes
2. Changes in the Services; 1. Landscaping Services; 5. Entire Agreement; 6. Obligations; 7. Insurance; 8. Liability Waiver; 9. Representations; 10. Termination; 11. Dispute Resolution; 12. Legal and Binding; 13. Governing Law/Compliance; 14. Severability
Generally, post-award administration requires documentation, change control, and adherence to statutory requirements
Contract Documents: the hierarchical relationship
The contract is built on (and cross-references) Form of Tender, Conditions, Drawings, Specifications, and BOQ; these documents collectively define scope, quality, and pricing
Main and Sub-Contract Arrangements in Landscape Projects
Main Contract types (in Singapore practice)
types of Main Contract generally adopted:
a. Lump Sum Contract / Fixed Price
b. Lump Sum Contract with Bills of Quantities and schedule of rates
Sub-Contract types
types of Sub-Contract generally adopted:
a. Nominated Subcontracts
b. Domestic Subcontracts
Lump Sum Contract with Bills of Quantities: advantages
Advantages: Tenderers can state total costs; Pricing based on consistent quantities; Easy comparison across tenders
Bills of Quantities: why they matter
Acts as a link between design and implementation
Enables tenders to be submitted on the same basis
Helps contractor assess material, labour, plant requirements
Aids tender evaluation and valuation of alterations
Provides a basis for interim valuations
Variations and Obligations in Contract Administration
Work Variation Claims
a) Addition, omission, demolition, or substitution of work, materials, or goods
b) Changes in type, standard, or quality of work, materials, or goods
c) Changes in plans, elevations, layouts, or dimensions
d) Ordered changes to contractor’s temporary works or methods of working
e) Ordered changes, additions, or omissions involving designated or nominated sub-contractors or suppliers
f) Postponement of any part of the Works
Contract Administration Obligations (Project Manager role)
Overall planning, coordination, and control of the project from inception to completion
Acts on behalf of the client; provides independent cost-effective service
Manages multiple disciplines; ensures alignment with project brief
Ensures project meets time, budget, and quality objectives from inception to completion
Landscape Architects vs Landscape Designers
Scope and role descriptions
Landscape architects / designers plan, design, and manage open spaces; work across outdoor and indoor environments; integrate landscape with art, environment, architecture, horticulture, engineering, sociology, and placemaking
They develop frameworks and policies for place-making that enable government and citizens to create better places
Key distinction
Landscape Architects typically engage in broader planning, policy, and design leadership beyond individual projects; landscape designers may focus more on implementation and design details under the architect/landscape architect framework
Exam Context: Quiz and Test Rules
Quiz format
Multiple Choice Questions; Enumeration questions requiring short answers; Answer 5/7 questions
CLOSED BOOK test
Test rules (as stated)
No communication between students during the test; no use of handphones or external devices
Bring your own stationery; use pen/ink; no pencils
Test details
Test duration: ; Date: ; Day: Thursday; Venue: ; Be on time