Procurement Process, Negotiation, and Strategic Purchasing
Course Overview & Business Process Lifecycle
Primary Course Sections:
Procurement Process for Awarded Projects
Negotiation 101
Strategic Procurement 101
Business Process Lifecycle Phases:
Business Development (Winning Phase):
Steps: Projects Prospecting Qualification Bidding
Major Actions:
Conduct site visits and thoroughly understand site conditions
Expand the supplier base geographically
Issue Requests for Estimate (RFE)
Identify alternative materials or new products
Project Organization and Contracting (Winning/Executing Transition):
Steps: Handover Project Start-up
Major Actions:
Update the Risk Register
Develop the Procurement Strategy (ProcStrat)
Identify and resource manpower requirements
Engage suppliers
Review and understand the Client Contract
Project Execution and Accountability (Executing Phase):
Steps: Construction Project Turn-Over
Major Actions:
Develop Procurement Programme Monitoring Report (PPMR)
Execute Purchase Request (PR) Purchase Order (PO) Delivery Receipt flow
Manage supply and subcontractor continuity
Oversee inventory and warehouse management
Perform PO closures and financial settlements
Manage excess material transfers and disposals
Project Completion / Celebration

Procurement Process Stage 1: Planning

Procurement Strategy (ProcStrat):
Definition & Purpose: Identifies procurement strategies, line items, subcontractor packages, potential vendors, lead times, risks, and opportunities prior to execution.
Process Owner: Quantity Surveyor (QS) / Planner.
Approved By: Project Manager (PM) & Department Head.
Core Elements Evaluated:
Project Needs:
Materials: Cement (Type I, Type II), Rebar (Grade 40, Grade 60), Aggregates (G1 Gravel, S1 Sand).
Services: FRC Works (Foundation and Perimeter Walls), Masonry Works (Plastered Interior Walls).
When Is It Needed?: Schedules actual PO issuance, deliveries, and site mobilization.
Who?: Identifies potential vendors and market options.
How Much?: Analyzes market rates and aligns with project budget.
Work Packages (WP):
Derived directly from the Approved Bill of Quantities (BOQ) and Project Schedule to structure package-by-package purchasing.
Procurement Programme Monitoring Report (PPMR):
Definition & Purpose: Systematically monitors line items, subcontractor packages, Material Approval Request (MAR) status, PR status, and PO status across established lead times.
Process Owner: Project Procurement Specialist / Project Procurement Officer.
Approved By: Project Manager.
Tracking Scope: Tracks actual vendors with POs, actual PO financial values against budget, and exact delivery/mobilization schedules.
Procurement Process Stage 2: Requisition
Purchase Request (PR):
Definition & Purpose: Document that officially initiates sourcing in the Procurement Department and triggers the ordering of items listed in the PPMR.
Process Owner: Quantity Surveyor (QS) / Cost Engineer (Project).
Approved By: Project Management Team (PMT), Project Manager (Project), and Admin Head (Head Office).
Key Content Requirements:
Service or Material Item Description
Quantities
Date Needed on Site
Approved Budget
Additional Requisition Documents:
Material Requisition (MR):
Contains detailed technical specifications and required site delivery dates for line items.
Initiates PR for items not initially included in standard Work Packages.
Process Owner: Requestor / QS.
Approved By: Project Manager or Department Head.
Capital Investment Request (CIR):
Mandatory additional request for acquiring fixed assets (e.g., laptops, office furniture) under material requests.
Process Owner: Requestor / QS.
Approved By: Accounting Department Head.
Material Approval Request (MAR):
Required for items requiring client approval prior to purchase.
Process Owner: Quality Assurance / Quality Control (QAQC).
Assisted By: QS.
Approved By: Client.
Requisition Requirements for Subcontractors:
Prospective subcontractors must be made fully aware of scope complexity during requisition, adhering to Main Contract specifications.
13 Standard Subcontract Requisition Documents:
Bill of Quantities (Responsible: QS / Cost Engineer)
Drawings (Responsible: QS)
Work Schedule (Responsible: Planner / Subcontractor)
Responsibility Matrix (Responsible: QS / PM / Subcontractor)
Specifications (Responsible: QS)
Method of Measurement and Payment (Responsible: QS / Cost Engineer)
Subcontractor Quality Requirements Checklist (Responsible: QAQC / Subcontractor)
Guaranteed Maximum Quantity [GMQ] (Responsible: QS / Cost Engineer)
Resources Loading (Responsible: Planner / Subcontractor)
Technical Data Sheet (Responsible: Subcontractor)
Method Statement (Responsible: Operations / QAQC / Subcontractor)
Detailed Programme [Optional] (Responsible: Subcontractor)
Contractor's ESH Management Guidelines [CEMG] (Responsible: Environmental Safety & Health [ESH] / Subcontractor)
Procurement Process Stage 3: Sourcing
Vendor Accreditation:
Vendors are formally evaluated and verified by a third-party service provider.
Required Compliance Documents:
Company profile
SEC and DTI Registration (Certificate of Business Name Registration, Deed of Articles of Partnership, Articles of Incorporation and By-Laws)
Business Permit / Mayor's Permit
BIR Registration
List of Completed / Served Projects
Credit Facilities / Bank References
Copy of Board Resolution for Authorized Signatories / Secretary Certificate
Latest SSS Sample and Official Receipts
Sales Invoice Sample and Official Receipts
Sustainability Compliance Form
Authorization Letter
Vendor Code and Policy
Disclosure Statement
Vendor Information Sheet (VIS)
Key Sourcing Documents & Processes:
Request for Quotation (RFQ):
Formal request sent to prospective vendors for pricing on required materials or services.
Process Owner: Procurement Specialist.
Key Considerations: Granular cost breakdown (materials, equipment, labor, delivery), VAT inclusion, price validity period, lead times/availability, commercial terms & conditions, exact delivery point.
Canvass Sheet / Bid Evaluation Summary Form:
Matrix tabulating all incoming supplier proposals.
Inputs are normalized to ensure equitable ("apple-to-apple") comparison.
Explicitly highlights pros and cons of each supplier offer.
Process Owner: Procurement Specialist.
Award Recommendation:
Required for high-value procurements; provides formal technical and financial justification for vendor selection.
Procurement Process Stage 4: Purchase Orders
Purchase Order (PO) & Subcontract Agreement:
Definition: Legally binding contract between buyer and seller.
Execution Platforms: SAP Purchase Order / ARIBA.
Process Owner: Procurement Specialist / Category Lead.
Approved By: Project Manager (governed by Limits of Authority / LOA levels).
Core PO Components: Vendor name, item descriptions, ordered quantities, unit and total prices, agreed delivery dates, and comprehensive terms & conditions.
Function: Triggers the official delivery and fulfillment process from the vendor.
Procurement Process Stage 5: Delivery & Materials Management
Scope & Management Responsibilities:
Process Owner: Site Quantity Surveyor / Site Procurement Officer.
Approved By: Project Manager & Procurement Head.
Key Operational Tasks: Managing full or staggered PO delivery schedules; maintaining minimum inventory threshold levels (ideally to lead time); receiving and quality checking goods; warehouse storage and issuance; excess material management; PO financial closure.
Delivery & Material Workflow Lifecycle:
Delivery: Site QS/Procurement creates a Goods Receipt (GR) upon delivery.
Inventory: QS/Procurement/Warehousemen store items securely in the site warehouse.
Goods Issuance: Warehousemen release stored items to authorized requestors.
Excess Management: Unused items are formally redirected for resale or transfer to other active project sites.
Inventory & Delivery Documentation:
Delivery Receipt: Physical document recording material backloading and returns to suppliers. (Process Owner: Vendor, QS, Project Procurement; Accepted By: Warehouse Manager).
Goods Receipt and Issuance: Digital ERP (SAP) records reflecting receipt of incoming goods and system issuance of stock. (Process Owner: Warehouse Manager; Overseen By: Vendor, QS, Project Procurement).
Material Delivery Inspection Report: Documents physical and technical verification (quality, quantity, specifications) conducted by QAQC, Discipline Representatives, and MIA against RFQ specs. (Process Owner: QAQC; Overseen By: QS/Procurement; Approved By: PM / QS Manager).
Material Inventory Monitoring: Manually updated inventory ledger tracking material movements across defined reporting periods. (Process Owner: Warehouse Manager; Overseen By: QS/Procurement).
Material / Asset Disposal Routing / Approval Form: Secures management authorization to dispose of scrap materials with residual commercial value. (Process Owner: QS/Procurement; Accepted By: QS / Procurement Head per LOA).
Scrap Management Examples:
Unused Structural Materials: Corroded scaffolding, structural steel offcuts, scrap rebar, discarded wire rolls.
Defective Machinery: Non-functional concrete mixers, damaged wheelbarrows.


Site Warehouse Audits:
Monthly audit ensuring proper warehouse upkeep and safety compliance.
7 Audit Scope Areas: Layout and Space, Inventory Management, Emergency Procedures, ESH and PPE Management, Manual Handling / Ergonomics, Waste Disposal, Client-Supplied Materials.
Case Example (DNL Warehouse Audit - Feb 2020 vs. Mar 2020):
February 2020 Score (79%): Hazards noted included correct but delayed GR/GI processing, disorganized inventory sorting, and poor housekeeping in the Pipe Storage Area.
March 2020 Score (88%): Corrective action verified organized inventory sorting and a tidy, hazard-free Pipe Storage Area.
Procurement Process Stage 6: Vendor Management
Strategic Objectives:
Maintain a reliable and qualified vendor pool.
Build strong collaborative partnerships with top-performing suppliers.
Enforce strict adherence to contractual terms and conditions.
Vendor Performance Report (VPR):
Purpose: Evaluates supplier performance periodically based on delivered scope.
Contributors: PMT, ESH Officers, QAQC Officers.
Overseen By: Vendor and Project Manager / Procurement Officer.
Approved By: Procurement Head.
VPR Evaluation Frameworks:
Subcontractor VPR for Services (Example: Tartaro Construction Inc., Palayan Project, Nov 2021):
Project Management (40% Weight): Business Relations (), Management of Key Personnel (), Schedule (), Cost Control ().
ESH Performance (18% Weight): ESH Incident Record (), Occupational Health (), Safety & Health Compliance (), Environmental Regulations (), Site ESH Requirements (), ESH Participation ().
Quality of Construction (20% Weight): Qualified Workers (), Compliance to Drawings/Specs (), Defect Rate (), Submittals ().
Sample Outcome: Accounted Score = (, rated Marginal/Needs Improvement).
Vendor VPR for Materials (Example: Sorcom Readymix Concrete, Palayan Binary Power Plant, March 2024):
Quality (30% Weight): Adherence to Specs (), Defect Rate ().
ESH Performance (10% Weight): No Recordable Incidents (), No ESH Violations ().
Delivery (40% Weight): Quantity Reliability (), Timeliness of Delivery ().
Responsiveness (20% Weight): Response to Queries (), Complaint Rectification ().
Sample Outcome: Overall Rating = (Very Satisfactory; Passing threshold is ).


Negotiation Strategies for Procurement
Core Negotiator Mindset:
Procurement professionals must maintain full leverage ("hold all the ACES") during supplier discussions.
Anticipate sales tactics to counter inquiries effectively while gathering intelligence.
Sales Questions vs. Best Negotiator Responses:
Lead Time:
Sales Question: "When do you really need this by?"
Optimal Response: "What’s your standard delivery? What are you currently delivering at?"
Competition:
Sales Question: "Who is our competition?"
Optimal Response: "Company policy doesn’t allow me to reveal that - who do you regard as your major competition?"
Quality and Specifications:
Sales Question: "What do you like/dislike about your current supplier? How do we compare with others?"
Optimal Response: "Would you want us talking about your problems with your competitors?"
Price:
Sales Question: "Out of price, quality, delivery, terms and warranty, what’s most important to you? What is your budget?"
Optimal Response: "I’m concerned about the total package – price, terms, quality, delivery, warranty, contract length. They are all important. That’s not the point. The point is, what’s the best you can do?"
Strategic Procurement & Portfolio Analysis
Tactical vs. Strategic Purchasing:
Tactical Purchasing: Reactive, transactional execution of administrative tasks (requesting quotes, issuing POs, expediting orders) without alignment to enterprise goals or long-term value creation.
Strategic Purchasing: Proactive planning, implementing, evaluating, and controlling purchasing decisions to align supply chain capabilities with long-term corporate goals.
Long-Term Contracting Frameworks:
Master Purchasing Agreement (MPA): Overarching agreement establishing pre-approved terms, conditions, and pricing for repetitive material/goods purchases, expediting individual PO releases.
Master Services Agreement (MSA): Establishes baseline legal and commercial terms for recurring service engagements (e.g., equipment calibration, third-party inspection, maintenance), streamlining future scope execution.
Kraljic Portfolio Analysis Matrix:
Leverage Items (Low Supply Risk, High Profit Impact):
Strategic Focus: Volume consolidation, competitive bidding/tendering, vendor selection, umbrella agreements.
Examples: Bored piling works, design-and-build designers, structural rebars, ready-mix concrete.
Strategic Items (High Supply Risk, High Profit Impact):
Strategic Focus: Strategic alliances, long-term partnerships, early supplier involvement (ESI), cost and technology roadmap alignment.
Examples: High-technology automation systems, client-mandated specialized equipment brands.
Non-Critical Items (Low Supply Risk, Low Profit Impact):
Strategic Focus: Product standardization, call-off orders, operational efficiency, delegated purchasing.
Examples: PVC pipes, standard office supplies, consumables, drinking water.
Bottleneck Items (High Supply Risk, Low Profit Impact):
Strategic Focus: Volume insurance contracts, supply security, alternative sourcing identification.
Examples: Aggregates sourced from environmentally sensitive or highly restricted locations.
Supplier Positioning Matrix (Spend vs. Supplier Attractiveness):
Exploitable (High Spend, Low Attractiveness): Vendor seeks to extract margin; procurement must command better terms.
Nuisance (Low Spend, Low Attractiveness): Minimal vendor interest; loss of supplier causes low operational impact.
Core Customer (High Spend, High Attractiveness): Vendor provides full support, best commercial terms, and long-term commitment.
Developmental (Low Spend, High Attractiveness): Opportunities to engage, explore, and expand business relationship.
Fundamental Rule: Know where your organization stands; do not demand concessions without established market leverage.