Comprehensive Study Notes on Sanitary Engineering, Sewage Treatment, and Environmental Management
Fundamentals of Sanitary Engineering and Terminology
Sanitary engineering involves the collection, treatment, and disposal of liquid and solid wastes from communities to safeguard public health and protect the environment.
Definitions of Common Terms
- Sewage: All kinds of liquid waste or wastewater produced from the community. It includes sullage, discharge from toilets, urinals, industrial wastewater, groundwater, surface water, and storm water admitted into sewers.
- Domestic Sewage: Sewage derived from residential buildings, commercial establishments, institutions, and public buildings (offices, schools, cinemas, hotels).
- Industrial Sewage: Wastewater obtained from industrial production and manufacturing processes.
- Sanitary Sewage: Sewage produced during dry weather that excludes storm water.
- Storm Water: Runoff rainwater originating from a locality following precipitation.
- Sullage: Wastewater originating from bathrooms, kitchen sinks, wash basins, etc., excluding human excreta and urine. It is generally less harmful and does not emit severe foul odors.
- Sewer: An underground conduit or drain designed to convey sewage. It is typically closed and operates normally under open-channel flow (not flowing full).
- Sewerage: The overall process and infrastructure system of collecting, conveying, treating, and disposing of sewage via a water carriage system through sewers.
- Refuse: Rejected or worthless solid or semi-solid waste material. Refuse is categorized into seven types:
- Garbage
- Rubbish
- Sullage
- Sewage
- Subsoil water
- Storm water
- Night soil
- Dry Refuse: The dry combination of garbage and rubbish.
- Garbage: Putrescible organic wastes obtained from residential, commercial, and institutional kitchens, including waste food, vegetable and fruit peelings (food waste), animal dung, grass, tree leaves, and bird excreta.
- Rubbish: Non-putrescible, inorganic, combustible and non-combustible solid wastes excluding food waste. Examples include paper, plastic, bottles, textiles, rubber, and wood.
Classification of Sewers
- Separate Sewer: A sewer that carries only domestic and industrial sewage while excluding storm water.
- Storm Water Sewer: A sewer designed exclusively to carry storm water runoff.
- Combined Sewer: A single sewer designed to carry domestic sewage, industrial sewage, and storm water together.
- Main Sewer (Trunk Sewer): A major sewer line that receives discharge from multiple branch or sub-main sewers, serving as the primary outlet for a large drainage area.
- Branch Sewer (Sub-Main Sewer): A sewer that receives sewage from several lateral sewers and delivers it into a main or trunk sewer.
- Lateral Sewer: A sewer that collects sewage directly from house sewers and discharges it into a branch or sub-main sewer. It represents the primary collection stage.
- House Sewer: A pipe conveying sewage from a building to a lateral sewer.
- Outfall Sewer: A sewer that receives sewage from the entire collecting network and conveys it to a wastewater treatment plant or final point of disposal. It spans between the lowest branch sewer connection and the disposal point.
Sanitation Systems and Sewerage Classification
Public administrative authorities (such as municipal offices) manage the collection and disposal of waste products using two main administrative and technological systems.
Conservancy System
An ancient system where waste types are collected and disposed of separately. It is obsolete in major cities but remains in use in small towns, villages, and undeveloped areas.
- Operation: Dry refuse (garbage/rubbish) is collected in roadside dustbins and transported by trucks or carts daily or twice daily. Non-combustible waste is dumped in low-lying pits; combustible waste (paper, leaves) is burned; vegetable peelings are dried, burned, and dumped. Night soil (human excreta) is manually collected by human agencies, transported in closed carts/trailers, and buried in underground trenches. Over approximately 2 years, buried night soil converts into agricultural manure. Sullage and storm water flow through open or closed street drains into natural streams, rivers, or seas, or are used for land farming.
- Merits:
- Low initial capital cost due to inexpensive open drains and dry latrines.
- Quantity of sewage reaching treatment plants is minimal.
- Storm water travels in open drains; underground sewer sections remain small and run full for most of the year, reducing silting.
- Pumping cost at outfalls during high river flood levels is minimal.
- Demerits:
- Requires extensive land area for trenching night soil.
- High risk of storm water entering sanitary drains, overloading plants.
- Liquid refuse can seep into subsoil, polluting groundwater sources.
- Latrines must be detached from main living quarters; indoor placement creates foul odors.
- Manual collection and handling of night soil creates highly unhygienic conditions.
- Aesthetic appearance of the city is poor.
- Highly vulnerable to labor strikes (e.g., sweepers), leading to rapid waste decomposition and epidemic risks.
Water Carriage System
Wastewater and human excreta are collected and conveyed using water as the hydraulic medium through underground closed conduits without manual labor. Excreta from water closets mixes with water to form a semi-solid mixture (approx. 99.9% liquid and 0.1% solid) that flows to treatment plants.
- Merits:
- Hygienic; eliminates manual human handling of excreta.
- Underground closed conveyance eliminates foul odor nuisances and epidemic risks.
- Requires a single sewer line, saving underground space compared to separate dry system channels.
- Allows compact building design with attached water closets equipped with water seals and traps.
- Large flow volumes allow self-cleansing velocities at flatter gradients.
- Independent of manual labor strikes for routine operation.
- Treated sewage effluent can be reused for agricultural irrigation.
- Demerits:
- High initial capital construction cost.
- High maintenance cost.
- Large variations in wastewater volume during monsoon seasons burden treatment plants.
Comparison: Conservancy System vs. Water Carriage System
| Parameter | Conservancy System | Water Carriage System |
|---|---|---|
| Building Design | Compact building layout not possible | Enables compact building layout |
| Hygienic Condition | Unhygienic | Highly hygienic |
| Land Requirement | Large land area required for disposal | Small land area required for disposal |
| Labor Requirement | High labor force required | Very few staff required |
| Epidemic Risk | High risk of epidemic outbreaks | Risk of epidemics is significantly reduced |
| Nuisance | High potential for street nuisance | No street nuisance |
| Water Demand | Requires small quantity of water | Requires large quantity of water |
| Capital Cost | Low initial cost | Very high initial cost |
| Groundwater Safety | High risk of groundwater pollution | Prevents groundwater pollution |
| Maintenance Personnel | No skilled labor required | Requires highly skilled technical staff |
| Suitability | Rural and undeveloped areas | Urban areas |
Sewerage System Types
- Separate Sewerage System: Sanitary sewage and storm water are carried separately in two distinct sets of sewers. Sanitary sewage goes to the Wastewater Treatment Plant (WWTP); storm water discharges directly into natural waterways without treatment.
- Advantages: Reduced volumetric load on WWTP; smaller, more economical sanitary sewers; economical pumping; natural water is not unnecessarily contaminated.
- Disadvantages: Small sanitary sewer diameters are difficult to clean; self-cleansing velocity is harder to achieve during low flow; storm sewers lie idle during dry seasons and accumulate dry refuse; higher overall maintenance cost; sanitary sewers must be laid deeper than storm sewers.
- Partially Separate Sewerage System: Sewage and roof/yard storm water from private property are combined into one set of sewers, while street/roadway runoff is conveyed in open surface drains.
- Advantages: Combines benefits of both systems; prevents silting due to periodic flushing by household storm water; reasonable pipe sizing.
- Disadvantages: Minor drawbacks of combined systems (slight increase in treatment volume during rains).
- Combined Sewerage System: Domestic sewage, industrial wastewater, and all storm water are conveyed together in a single sewer line to the WWTP.
- Advantages: Larger sewer diameters make cleaning easier; lower overall maintenance cost; sewage is diluted by storm water, reducing its strength; lower construction cost compared to laying two underground lines.
- Disadvantages: Sewer overflow during heavy storms poses severe public health risks; heavy silting and foul odors occur during dry weather; high treatment plant load; unnecessary treatment of clean rainwater; uneconomical if pumping is required.
Comparison: Separate System vs. Combined System
| Parameter | Separate System | Combined System |
|---|---|---|
| Sewer Lines | Consists of two sets of sewers; requires wide roads | Consists of one set of sewers; suitable for narrow roads |
| Treatment Cost | Low treatment cost due to lower volume | High treatment cost due to storm water volume |
| Rainfall Suitability | Suitable for areas with high rainfall intensity | Suitable for areas with low rainfall intensity |
| Sanitation Degree | Lower degree of sanitation | High degree of sanitation |
| Pumping Suitability | Highly suitable if pumping is required | Expensive if pumping is required |
| Choking Risk | Higher risk of choking in small pipes | Low choking risk due to high self-cleansing velocity |
| Degree of Treatment | High degree of treatment required | Lower degree of treatment required (due to dilution) |
| Construction Cost | Lower overall construction cost | Higher overall cost (large underground conduits) |
Wastewater Quantity Estimation and Stormwater Hydrology
Sources of Wastewater
- Public Water Supply: Municipal water supplied to residential, commercial, and industrial facilities.
- Private Water Supply: Water drawn independently from wells, tube wells, rivers, or canals by private entities, institutions, malls, or hotels.
- Groundwater Infiltration: Water entering sewer lines through loose joints, cracks, or defective pipe walls when the surrounding groundwater table head exceeds the hydraulic head inside the sewer.
- Unauthorized Connections: Rainwater or illegal plumbing discharges tied directly into sanitary sewers.
Flow Components: DWF and WWF
- Dry Weather Flow (DWF): The quantity of sanitary sewage flowing during dry weather periods without storm water runoff. It comprises domestic and industrial sewage. DWF is the minimum flow available throughout the year. It depends on population, industrial output, rate of water supply, and baseline infiltration/ex-filtration.
- Wet Weather Flow (WWF): The combined volumetric flow of sanitary sewage, industrial wastewater, groundwater infiltration, and storm water runoff during rainy periods.
Factors Affecting Sanitary Sewage Quantity
- Population Growth: Wastewater volume scales directly with population. Population forecasting uses methods such as:
- Arithmetic Increase Method
- Geometric Increase Method
- Incremental Increase Method
- Graphical Method
Design Periods for Sewerage Components:
- Sewer Network:
- Pumping Stations:
- Sewage Treatment Plants:
- Efficient Disposal and Utilization Works:
- Rate of Water Supply: Wastewater generation ranges from to of the total public water supply rate.
- Groundwater Infiltration and Ex-filtration: Infiltration increases sewage volume, while ex-filtration (leakage of sewage out into the soil) decreases volume.
- Unauthorized Connections: Direct input of unmetered storm water or illegal drains.
- Type of Area Served: Zoning characteristics (residential density, commercial commercial hubs, heavy industrial zones).
Factors Affecting Storm Sewage Quantity
- Catchment Area Size and Shape: Runoff is higher for large, fan-shaped catchments than for small, fern-shaped catchments.
- Topography: Steep ground slopes yield higher runoff velocity and volume.
- Surface Characteristics: Impervious, rocky, or clay soils produce higher runoff; loose sandy soils yield lower runoff.
- Storm Direction: Storms moving in the direction of streamflow produce higher peak runoff.
- Precipitation Type: Rainfall produces immediate runoff; snow melting produces delayed runoff.
- Rainfall Distribution: Spatial coverage of the storm across the basin.
- Rainfall Intensity and Duration: High intensity increases runoff rates; longer duration prolongs peak flows.
- Soil Moisture Deficiency: Dry soil absorbs substantial initial rainfall (low runoff); saturated soil yields maximum runoff.
- Climatic Conditions: High ambient temperatures increase evaporation losses, reducing runoff.
- Geological Conditions: Fissures, subsoil cracks, and high permeability reduce surface runoff.
- Vegetative Cover: Dense vegetative canopy and root systems increase interception and infiltration, reducing runoff.
Estimation of Peak Sanitary Sewage Flow
Sanitary sewage quantity is calculated using the Return Factor () and Peak Factor ():
Peak Factor () Values by Sewer Type:
- Domestic Sewer:
- Lateral Sewer:
- Branch Sewer:
- Sub-Main Sewer:
- Main Sewer:
- Outfall Sewer:
Peak Factor () Values by Population:
- Up to :
- :
- :
- Greater than :
Estimation of Storm Water Quantity
1. Rational Method
Used for small catchments ().
Where:
- = Storm water runoff ()
- = Runoff coefficient (overall dimensionless composite value)
- = Rainfall intensity ()
- = Catchment area (, where )
Alternative units formulation:
- If is in :
- If is in :
Composite Runoff Coefficient ():
Runoff Coefficients () by Area Type:
- Commercial and Industrial Areas: ( impervious)
- Residential Area (High Density): ( impervious)
- Residential Area (Low Density): ( impervious)
- Parks and Underdeveloped Areas: ( impervious)
Rainfall Intensity () Equations:
- British Ministry of Health Formulas ( in , in ):
- For storm durations :
- For storm durations :
- Kuichling's Formulas:
- For 10-year storm frequency:
- For 15-year storm frequency:
Time of Concentration ():
Assumptions and Limitations of the Rational Method:
- Restricted to small catchment areas ().
- Rainfall intensity is uniform over the entire catchment area.
- Storm duration equals the time of concentration ().
- Runoff is dominated by overland sheet flow.
- Catchment surface slope is not explicitly parameterized.
- Selection of runoff coefficients and intensities is tedious for heterogeneous large areas.
- Basin channel storage effects are neglected.
2. Empirical Formulas
- Burkli-Ziegler Formula: Where is in , (average ), in , in , is slope in .
- Mc-Math Formula: Where (developed for St. Louis, USA).
- Metcalf and Eddy Formula:
- Fanning Formula: ( in , in ).
- Talbat Formula: ( in , in ).
- Dickens Formula: ( in , in , maximum ).
- Ryves Formula: ( in , in ).
- Inglis Formula: ( in , in ).
Solved Mathematical Examples
Example 1
Determine design discharge for separate and combined systems for a town of population, area , water supply rate , runoff coefficient , time of concentration , sewer slope , Manning's . Also find combined sewer diameter.
Solution:
- Dry Weather Flow ():
- Wet Weather Flow (): For ():
- Combined System Discharge:
- Diameter Determination (): For pipe flowing full: ,
Example 2
Catchment area . Composition: Forest (, ), Open ground (, ), Parks (, ), Gravel road (, ), Asphalt (, ), Roofs (, ). Entry time , flow time . Calculate storm water flow.
Solution:
- Composite Runoff Coefficient ():
- Time of Concentration (): .
- Rainfall Intensity (): .
- Storm Water Quantity:
Example 3
Population , area , , entry time , travel time , water supply rate , peak factor . Calculate design discharge for combined sewer.
Solution:
- Sanitary Flow ( with PF):
- Time of Concentration: .
- Rainfall Intensity: .
- Storm Discharge:
- Total Design Discharge: .
Example 4
Residential district area (). Surface breakout: roofs/pavements (), lawns/gardens (), ground surface (). Intensity . Calculate and storm sewage flow.
Solution:
- Overall Coefficient ():
- Storm Sewage Discharge:
Example 5
Calculate combined sewage quantity for:
- Area = , Population density = (Total pop = )
- pavement (), open ground ()
- Water supply rate = , Time of concentration = , Peak factor =
Solution:
- Composite Coefficient ():
- Intensity (): For ,
- Storm Discharge ():
- Sanitary Sewage ():
- Total Combined Discharge:
Example 6
Town area = . Breakdown: hard pavements (), roofs (), barren land (), garden/lawns (), forest (). Intensity , Density = , Water supply = , Peak factor = . Find and discharge for (i) Separate, (ii) Combined, and (iii) Partially Combined systems.
Solution:
- Composite Coefficient ():
- Storm Runoff ():
- Sanitary Sewage (): Total Population =
- System Discharges:
- Separate System: Sanitary Sewer ; Storm Drain
- Combined System:
- Partially Combined System: Closed sewer carries ; Open drain carries storm water .
Characteristics, Decomposition, and Examination of Sewage
Wastewater Sampling
Sampling must yield a representative volume that reflects true pollutant concentrations.
- Grab Sample: A single discrete sample collected at a specific spot and specific time. Reflects conditions only at the exact sampling moment. Suitable for consistent water quality sources (e.g., protected groundwater).
- Composite Sample: A combination of multiple grab samples collected at fixed time intervals (typically over ) proportional to flow rate. Used for volatile or variable industrial and municipal wastewater streams.
- Preservation and Storage: Wastewater changes rapidly due to microbial activity. Samples must be analyzed immediately or stored in ice boxes. Chemical preservatives include chloroform, formaldehyde, and concentrated sulphuric acid (). Crucial Rule: Chemical preservatives must never be added to samples designated for Biochemical Oxygen Demand (BOD) testing.
Biochemical Oxygen Demand (BOD)
BOD is the quantity of dissolved oxygen required by microorganisms to biochemically decompose biodegradable organic matter in sewage under aerobic conditions at a specified standard temperature ().
Applications of BOD Test Results:
- Sizing wastewater treatment units.
- Determining oxygen requirements for organic stabilization.
- Evaluating treatment plant efficiency.
- Measuring sewage strength.
- Calculating dilution water requirements for river discharge.
Carbonaceous vs. Nitrogenous Stages of BOD
- First Stage BOD (Carbonaceous Demand): Biological breakdown of carbon compounds into , , and simple amine compounds. Lasts for .
- Second Stage BOD (Nitrogenous Demand): Oxidation of nitrogenous matter (ammonia, organic nitrogen) into nitrites () and nitrates () by nitrifying bacteria. Takes place after and continues over extended periods.
Derivation of First-Stage BOD Equation
De-oxygenation rate is directly proportional to the organic matter remaining at time ():
Integrating from (where ) to time :
Converting to Base-10 log format (where ):
The BOD exerted () at time is the difference between ultimate initial BOD () and remaining BOD ():
Temperature Correction for Rate Constant (): Where is the rate constant at temperature and is the rate constant at .
Chemical Oxygen Demand (COD)
COD is the quantity of oxygen consumed to chemically oxidize both biodegradable and non-biodegradable organic matter using a strong chemical oxidizing agent (potassium dichromate, ) in an acid medium.
- Fast analysis ( compared to for BOD).
- COD values are always higher than BOD values ().
- Used for process operational control, whereas BOD is used for regulatory standards.
Decomposition Processes
- Aerobic Decomposition: Breakdown carried out by aerobic and facultative bacteria in the presence of dissolved oxygen. End products are non-offensive and stable: Nitrates (), Carbon Dioxide (), Sulphate (), Water (), and energy. Occurs in oxidation ponds, trickling filters, aerated lagoons.
- Anaerobic Decomposition (Putrefaction): Breakdown carried out by anaerobic and facultative bacteria in the complete absence of free dissolved oxygen. Oxygen is extracted from organic radical bounds (, ). End products are offensive gases and unstable solids: Hydrogen Sulphide (), Ammonia (), Methane (), Nitrogen (). Occurs in septic tanks, sludge digesters.
Comparison: Aerobic vs. Anaerobic Decomposition
| Parameter | Aerobic Decomposition | Anaerobic Decomposition |
|---|---|---|
| Oxygen Requirement | Requires presence of free dissolved oxygen | Takes place in the absence of free oxygen |
| End Products | , , , | , , , , |
| Effluent Quality | Higher quality, stable effluent | Lower quality effluent |
| Responsible Organisms | Aerobic and facultative bacteria | Anaerobic and facultative bacteria |
| Process Units | Oxidation ponds, trickling filters, ASP | Septic tanks, anaerobic sludge digesters |
Characteristics of Sewage
1. Physical Characteristics
- Color: Fresh sewage is light brown. After of aerobic breakdown, it becomes medium grey. Aged anaerobic sewage becomes dark grey or black.
- Odor: Fresh sewage is practically odorless. Stale sewage emits (rotten egg odor). Causes loss of appetite, nausea, impaired respiration.
- Temperature: Typical wastewater temperatures are slightly higher than domestic water supplies. Biological activity increases up to . High temperatures decrease gas solubility (lower DO) and reduce fluid viscosity.
- Turbidity and Solids: Total solids () are categorized into:
- Colloidal Solids: Finely divided non-settleable particles; removed by coagulation/biological oxidation.
- Suspended Solids: Settleable and non-settleable solids.
- Dissolved Solids: Solutes that pass through filter media.
2. Chemical Characteristics
- pH: Fresh sewage is slightly alkaline (). As organic acids form during decomposition, pH drops (acidic). Extreme pH ( or significantly) indicates heavy industrial waste discharges.
- Solids Composition: Organic solids (carbon, hydrogen, oxygen) volatilize completely at for (Volatile Solids). Inorganic solids (nitrogen, chlorine, salts) remain as ash (Fixed Solids).
- Nitrogen Content: Present as Organic Nitrogen, Free Ammonia (), Ammonium (), Nitrites (), and Nitrates (). High nitrogen accelerates aquatic algae growth.
3. Biological Characteristics
Sewage contains bacteria, protozoa, fungi, algae, and viruses. Bacteria are grouped by oxygen demand into Aerobic, Anaerobic, and Facultative.
Sewage Testing and Examination Methods
- Physical Tests:
- Temperature: Ordinary thermometer ().
- Color: Tintometer.
- Odor: Threshold Odor Number ().
- Turbidity: Turbidity Rod or Jackson's Turbidimeter.
- Solids Laboratory Procedures:
- Total Solids (): Evaporate known sample volume in crucible of initial weight at for . Weigh dry crucible ().
- Total Volatile Solids () and Fixed Solids (): Ignite the dry residue from testing in a muffle furnace at for . Cool and weigh ().
- Total Suspended () and Dissolved Solids (): Filter volume through Whatman No. 44 filter paper. Evaporate filtrate at to determine . Calculate .
- Settleable Solids (): Measured using an Imhoff Cone (1-liter capacity). Allow sample to settle undisturbed for . Settleable volume read directly off cone bottom ().
- Chemical Oxygen Demand () Test: Add known excess standard potassium dichromate () and concentrated sulphuric acid () with silver sulphate catalyst to sample. Boil for . Titrate remaining dichromate against standard ferrous ammonium sulphate ().
- BOD Dilution Test Procedure:
- Measure initial Dissolved Oxygen () of sample/dilution water.
- Dilute wastewater with aerated nutrient-enriched dilution water.
- Incubate diluted sample at in the dark for .
- Measure final Dissolved Oxygen ().
- Calculate depletion:
- Compute BOD:
Design, Hydraulics, and Construction of Sewers
Design Criteria for Sewers
- Specific gravity of sewage is taken as .
- Design Period: .
- Minimum sewer pipe diameter: ; recommended minimum: . Commercially available in increments up to .
- Sewer Gradients: Selected to maintain velocities between self-cleansing (minimum) and non-scouring (maximum). Slopes range from (steep) to (flat).
- Pipe design assumes gravity open-channel flow running full at maximum peak discharge.
Velocity Criteria
1. Self-Cleansing Velocity
The minimum flow velocity required to keep solid particles in suspension and prevent deposition/silting at the sewer invert. Calculated via Camp Shield's Formula:
Where:
- = Particle diameter
- = Acceleration due to gravity ()
- = Specific gravity of solids ( for organic, for inorganic)
- = Darcy-Weisbach friction factor ()
- = Dimensionless particle characteristic constant ()
Minimum Self-Cleansing Velocities for Separate Systems:
- Diameter :
- Diameter :
- Diameter :
- Combined Sewer Minimum:
2. Non-Scouring (Maximum) Velocity
The maximum permissible flow velocity that prevents structural erosion, scouring, and abrasion of the interior sewer lining.
Maximum Non-Scouring Velocities by Material:
- Earthen channels:
- Ordinary brick lining:
- Cement concrete:
- Stoneware:
- Cast iron pipe:
- Vitrified clay and salt glazed:
Hydraulic Formulas
Discharge Equation:
Manning's Formula: Where (Hydraulic radius), = slope, = Manning's rugosity coefficient. Manning's Rugosity Coefficient ():
- Fine soil / Sand:
- Grass lined:
- Brick work:
- Cast iron:
- Cement concrete (good): ; Cement concrete (fair):
- Salt glazed stoneware (good): ; (fair):
- Plastic pipe:
Hazen-Williams Formula: Coefficient Values: Vitrified clay = ; Brick = ; Cast iron (old) = ; Cast iron (new) = ; Concrete/Plastic/AC = 120\text{ to }150$.\n\n- **Chezy's Formula**: \n V = C \sqrt{R S}\n Using Manning relation C = \frac{1}{n} R^{1/6}.\n - *Kutter's Formula for C*:\n C = \frac{23 + \frac{0.00155}{S} + \frac{1}{n}}{1 + \left(23 + \frac{0.00155}{S}\right) \frac{n}{\sqrt{R}}}\n - *Bazin's Formula for C*:\n C = \frac{157.6}{1 + \frac{m}{\sqrt{R}}}\n Where m = 0.11m = 0.21m = 0.83m = 1.54m = 2.36 (ordinary earth channel).\n\n### Partial Flow Hydraulics in Circular Sewers\n\nLet Dd\phi = Angle subtended by flow surface at center (degrees).\n\n- **Depth ratio**: \n \frac{d}{D} = \frac{1}{2} \left(1 - \cos\left(\frac{\phi}{2}\right)\right)\n- **Proportional Area (\frac{a}{A})**:\n \frac{a}{A} = \frac{\phi}{360} - \frac{\sin\phi}{2\pi}\n- **Proportional Wetted Perimeter (\frac{p}{P})**:\n \frac{p}{P} = \frac{\phi}{360}\n- **Proportional Hydraulic Radius (\frac{r}{R})**:\n \frac{r}{R} = 1 - \frac{360 \sin\phi}{2\pi \phi}\n- **Proportional Velocity (\frac{v}{V})**:\n \frac{v}{V} = \frac{n}{n_d} \left(\frac{r}{R}\right)^{2/3}\n- **Proportional Discharge (\frac{q}{Q})**:\n \frac{q}{Q} = \frac{a}{A} \frac{v}{V} = \left(\frac{a}{A}\right) \left(\frac{n}{n_d}\right) \left(\frac{r}{R}\right)^{2/3}\n\n*Equal Self-Cleansing Tractive Force Condition*:\nTo provide equal self-cleansing at partial depth, tractive shear forces must be equal (\tau_s = \tau \implies \gamma r S_s = \gamma R S):\n\n\frac{S_s}{S} = \frac{R}{r}\nv_s = \frac{1}{n_d} r^{2/3} S_s^{1/2} = V \left(\frac{n}{n_d}\right) \left(\frac{r}{R}\right)^{1/6}\n\n### Sewer Shapes\n\n1. **Circular Sewers**: Most widely used. Maximum hydraulic efficiency (least perimeter for given area); uniform stress distribution; easy to manufacture. Max diameter up to 1.5\text{ m}. Unsuitable for combined sewers with large flow variations because self-cleansing velocity drops at low DWF.\n2. **Egg-Shaped Sewers**: Depth is 1.5 \times \text{width}. Smaller bottom radius and larger top arch. Maintains high velocity during low DWF. Highly efficient for combined sewers. Demerits: Tedious construction, lower structural stability than circular sewers, expensive.\n3. **Non-Circular Sewers**: Used for soft foundation soils or constrained headroom.\n - *Semi-Elliptical*: Excellent load distribution for large sewers (> 2\text{ m}).\n - *Parabolic (Delta)*: Large capacity, lower normal flow level.\n - *Horse-Shoe*: Heavy top arch load support; wide flat invert.\n - *Rectangular (Box)*: Simple formwork, used in restricted headroom, RCC construction.\n - *U-Shaped*: Good hydraulic properties, easy maintenance for conduits > 1\text{ m} wide.\n\n### Sewer Pipe Materials\n\n1. **Salt Glazed Stoneware**: Manufactured from vitrified clay/shale at 1200^\circ\text{C}80\text{ to }1000\text{ mm}600\text{ to }900\text{ mm}. Socket and spigot joints. Highly resistant to abrasion and acid corrosion. Weak in tension, heavy, brittle.\n2. **Cement Concrete (PCC / RCC)**: Widely used for medium/large sewers. PCC used for diameter \le 60\text{ cm}< 15\text{ m} head); RCC used for large diameters/pressures.\n - *Crown Corrosion Phenomenon*: Bacterial reduction of sulphate compounds under anaerobic invert deposits generates \text{H}2\text{S} gas:\n \text{SO}_4^{2-} + \text{Organic matter} \xrightarrow{\text{Bacteria}} \text{S}^{2-} + \text{H}_2\text{O} + \text{CO}_2\n \text{S}^{2-} + 2\text{H}^+ \rightarrow \text{H}_2\text{S}\n \text{H}_2\text{S}\text{H}_2\text{SO}_4):\n \text{H}_2\text{S} + 2 \text{O}_2 \xrightarrow{\text{Thiobacillus}} \text{H}_2\text{SO}_4\n \text{H}_2\text{SO}_4\text{CaCO}_3), causing crown structural disintegration.\n3. **Cast Iron (CI)**: High structural, tensile, and flexural strength. Used for high internal/external pressure, wet soil, traffic vibrations, river crossings, and inverted siphons.\n\n### Solved Engineering Problems\n\n#### Example 1\nPopulation = 80,000145\text{ lpcd}0.8n_d = 0.0131:40030.75\frac{d}{D} = 0.75).\n\n*Solution*:\n1. **Design Discharge (q)**:\n q = \frac{80000 \times 145 \times 0.8 \times 3}{24 \times 3600 \times 1000} = 0.334\text{ m}^3/\text{sec}\n2. **Hydraulic Geometry at d/D = 0.75**:\n \cos\left(\frac{\phi}{2}\right) = 1 - 2\left(\frac{d}{D}\right) = 1 - 2(0.75) = -0.5 \implies \frac{\phi}{2} = 120^\circ \implies \phi = 240^\circ\n \sin\phi = \sin(240^\circ) = -0.866\n a = \frac{\pi D^2}{4} \left(\frac{240}{360} - \frac{-0.866}{2\pi}\right) = 0.63 D^2\n p = \pi D \left(\frac{240}{360}\right) = 2.094 D\n r = \frac{a}{p} = \frac{0.63 D^2}{2.094 D} = 0.301 D\n3. **Discharge Equation**:\n q = \frac{1}{n_d} a r^{2/3} S^{1/2}\n 0.334 = \frac{1}{0.013} (0.63 D^2) (0.301 D)^{2/3} \left(\frac{1}{400}\right)^{1/2}\n 0.334 = 76.923 \times 0.63 D^2 \times 0.4492 D^{2/3} \times 0.05\n 0.334 = 1.088 D^{8/3} \implies D^{8/3} = 0.3069 \implies D = 0.64\text{ m}\n\n#### Example 2\nDesign circular combined sewer: Area = 60\text{ ha}3.2\text{ m/s}18\text{ min}5\text{ min}C = 0.5565,000235\text{ lpcd}.\n\n*Solution*:\n1. **Storm Flow**:\n t = 18 + 5 = 23\text{ min}\n I = \frac{1020}{23 + 20} = 23.72\text{ mm/hr}\n Q{\text{storm}} = \frac{0.55 \times 23.72 \times 60}{360} = 2.174\text{ m}^3/\text{sec}\n2. **Sanitary Flow**:\n Q_{\text{sewage}} = \frac{65000 \times 235 \times 0.8}{24 \times 3600 \times 1000} = 0.1414\text{ m}^3/\text{sec}\n Taking peak factor 1.25\implies Q = 0.1767\text{ m}^3/\text{sec}\n3. **Combined Flow**: Q = 2.174 + 0.1767 = 2.350\text{ m}^3/\text{sec}\n4. **Sewer Dimensions**:\n Using Q = \frac{1}{n} A R^{2/3} S^{1/2} = 2.350\n For \frac{1}{S} = 600n = 0.012\n Solving gives D = 1.35\text{ m}1.424\text{ m}^21.649\text{ m/s}.\n\n#### Example 3\nFind full diameter of sanitary sewer: Population = 90,000180\text{ lpcd}n = 0.0251:500R.F. = 0.8.\n\n*Solution*:\n1. **Average Sanitary Discharge**:\n Q = \frac{90000 \times 180 \times 0.8}{24 \times 3600 \times 1000} = 0.15\text{ m}^3/\text{sec}\n2. **Velocity**: V = \frac{1}{0.025} \left(\frac{D}{4}\right)^{2/3} \left(\frac{1}{500}\right)^{1/2} = 0.713 D^{2/3}\n3. **Discharge Equation**:\n Q = A V \implies 0.15 = \left(\frac{\pi D^2}{4}\right) (0.713 D^{2/3}) = 0.560 D^{8/3}\n D^{8/3} = 0.2679 \implies D = 0.611\text{ m}\n\n#### Example 4\nCalculate size of circular sewer to carry Q = 0.6\text{ m}^3/\text{sec}d = D/21:1000n = 0.013$.
Solution: For half-full flow: , , . (Note: If solved with under high-roughness parameter).
Example 5
Circular sewer , slope = , . Find velocity and half-full discharge.
Solution: For half-full: ,
Sewer Construction Procedure
- Setting out Centerline: Centerline pegs are driven at , , or intervals starting from downstream (tail end).
- Method 1 (Offset Line): Parallel line offset from centerline to clear traffic.
- Method 2 (Sight Rails): Vertical posts driven on both sides of trench supporting horizontal cross-rails.
- Alignment and Gradient Control: Maintained using Boning Rods (Travelers) and sight rails. A cord stretched between consecutive sight rails represents an imaginary line parallel to the invert slope.
- Excavation and Timbering: Trench excavated to minimum depth above sewer, width . For depths , vertical or horizontal timber sheeting and struts prevent side cave-ins.
- Laying and Jointing: Pipe bedded on concrete or firm soil, aligned with plumb bobs, and jointed (cement mortar, bitumen, rubber rings).
- Sewer Testing:
- Straightness & Obstruction Test: A smooth wooden ball (diameter less than pipe internal diameter) is rolled down the invert, or light from a lamp at one end is viewed via a mirror at the opposite end.
- Water Test (Exfiltration Test): Low end plugged, high end fitted with funnel/air vent. Filled with water under head. Loss after must not exceed .
- Air Test: Used for large pipes. Test section pressurized to water column. Pressure drop must remain within water column over test interval.
- Backfilling: Excavated earth free of stones is backfilled and compacted in layers after test approval.
Primary, Secondary, and Biological Sewage Treatment Processes
Wastewater treatment converts harmful organic and inorganic impurities into stable solids, yielding safe effluent.
Process Classification
- Preliminary Processes: Screening (removes large floating solids), Grit Removal (removes heavy inorganic discrete solids), Skimming (removes fats, oils, grease).
- Primary Treatment: Plain Sedimentation and Chemical Precipitation. Removes settleable organic solids ( TSS removal, BOD removal).
- Secondary (Biological) Treatment: Microbial decomposition of dissolved and colloidal volatile organic matter under aerobic or anaerobic conditions.
- Suspended Growth Processes: Microorganisms suspended in liquid mix via aeration/agitation. (e.g., Activated Sludge Process, Aerated Lagoons, Anaerobic Digesters).
- Attached Growth (Fixed-Film) Processes: Microorganisms attached to inert media (rock, slag, plastic). (e.g., Trickling Filters, Rotating Biological Contactors).
- Combined Processes: Hybrid systems (e.g., Trickling filter with activated sludge).
- Tertiary (Advanced) Treatment: Removal of specific recalcitrant compounds, nutrients (N, P), heavy metals, pathogens.
Primary Treatment Units
1. Racks and Screens
Traps coarse floating debris (plastics, rags, leaves, dead animals).
- Coarse Screens (Racks): Clear opening between bars (typically ). Collects material per million sewage.
- Medium Screens: Bar spacing . Collects per million sewage.
- Fine Screens: Perforated plates or wire mesh with openings (). Removes up to TSS.
2. Grit Chamber
Long narrow channels designed to settle out inorganic discrete grit (sand, gravel, ash, eggshells; diameter , specific gravity ) while keeping lighter organic particles in suspension.
Settling Velocity () (Transition Zone formula for ): Where is in , in , in .
Surface Overflow Rate ( or ): . Efficiency .
Design Parameters:
- Detention Time: .
- Horizontal Flow Velocity (): .
- Critical Scouring Velocity (): For inorganic grit (, , ): . For organic matter (, ): (prevents organic deposition).
3. Skimming Tank
Removes light floating substances (oil, grease, soap, vegetable debris).
- Compressed air diffusers at bottom () coagulate grease and float scum into side troughs.
- Surface Area Equation: , where (minimum rising velocity).
- Detention Time: .
4. Primary Sedimentation Tank (PST)
Settleable organic solids removal under gravity.
- Settling Regimes:
- Type 1 (Discrete Settling): Unhindered settling of non-flocculating particles (Grit chambers).
- Type 2 (Flocculent Settling): Particles coalesce during settling, increasing mass and velocity (PST).
- Type 3 (Hindered / Zone Settling): High solids concentration; particles settle as a contiguous mass matrix (Secondary Settling Tanks).
- Type 4 (Compression Settling): Mechanical compaction of lower sludge matrix (Bottom of SST / Thickeners).
- PST Design Criteria:
- Detention Period: (plain sedimentation); (coagulated).
- Flow Velocity: .
- Tank Dimensions: Rectangular (, ); Circular Diameter .
- Effective Liquid Depth: .
- Surface Overflow Rate (): Plain (); Flocculated
- Freeboard: .
Solved Mathematical Examples for Primary Units
Example 1 (Grit Chamber Design)
Flow = (), , , particle diameter , , . Design grit chamber.
Solution:
- Detention time .
- Volume .
- Settling Velocity ():
- Depth .
- Total Plan Area . Provide 2 units of area each. For width , Length . Total depth = .
- Critical Velocity Checks: Check: . (Design OK).
Example 2 (Circular PST Design)
Population = , water supply rate = , return factor = , Peak factor = , detention time = , .
Solution:
- Average Sewage = .
- Peak Flow .
- Tank Volume .
- Plan Area .
- Liquid Depth . Total Depth = .
Secondary Biological Treatment Units
1. Trickling Filters
Attached growth aerobic units. Sewage is sprayed over packed coarse aggregate media ( diameter, depth ). Microorganisms form a slimy biological film (biofilm). Aerobic conversion occurs at the surface; inner layers become anaerobic, leading to sloughing of the biomass.
Recirculation Ratio (): ( = Recirculated flow, = Raw inflow).
Recirculation Factor ():
National Research Council (NRC) Efficiency Formulas:
- Single-Stage / First-Stage High-Rate Trickling Filter (HRTF): Where is fraction efficiency, is influent BOD (), is effluent BOD (), is applied BOD load (), is filter volume (), is recirculation factor.
- Second-Stage HRTF: Where .
- Standard Rate Trickling Filter (SRTF): No recirculation ().
Comparison: Standard Rate vs. High Rate Trickling Filters:
| Attribute | Standard Rate (SRTF) | High Rate (HRTF) |
|---|---|---|
| Hydraulic Loading () | ||
| Organic Loading () | ||
| Filter Depth () | ||
| Recirculation Ratio () |
2. Activated Sludge Process (ASP)
Suspended growth aerobic process. Wastewater from PST is mixed with returned active biological sludge (containing high concentrations of active microorganisms) in an aeration tank. Air is supplied via diffusers or mechanical aerators.
Flow Streams: PST effluent () + Return Activated Sludge () forms Mixed Liquor. Solids in aeration tank are termed Mixed Liquor Suspended Solids (MLSS, ).
Sludge Volume Index (SVI): Volume in occupied by of settled MLSS after settling in an Imhoff cone:
- : Excellent settleability.
- : Satisfactory normal operational target.
- : Poor settling (sludge bulking).
Sludge Density Index (SDI): .
Return Sludge Ratio ():
Food to Microorganism Ratio (): Target range: .
Hydraulic Retention Time (HRT / ): .
Volumetric BOD Loading: .
Air Requirements: applied.
Example (ASP Design)
, Influent BOD , Effluent target , MLSS , , . Find (i) Reactor volume, (ii) Detention time, (iii) Recycle ratio.
Solution:
- Volume ():
- Detention Time ():
- Recycle Ratio ():
3. Waste Stabilization Ponds (Oxidation Ponds)
Shallow earthen basins relying on bacterial-algae symbiosis. Aerobic bacteria utilize free oxygen released by algae during photosynthesis to oxidize organic matter into , , and . Algae consume the and nutrients released by bacteria in the presence of sunlight.
- Zonal Layers:
- Top Aerobic Zone (algae photosynthesize, dissolved oxygen present).
- Middle Facultative Zone.
- Bottom Anaerobic Zone (settled sludge stabilization).
- Design Criteria:
- Detention period: .
- Operational Depth: .
- Length to Width Ratio: .
- Organic BOD Loading: (cold climates) to (tropical regions).
- Freeboard: .
Example (Oxidation Pond Design)
Population = , water supply = , return factor = , Influent BOD = , depth = , Organic loading = , . Find dimensions and detention time.
Solution:
- Sewage Flow (): .
- Daily BOD Load: .
- Surface Area (): , .
- Volume ():
- Detention Time (): .
Sewage Disposal Methods and River Self-Purification
Sewage disposal is necessary to prevent stagnant odors, public health hazards, vector breeding, and environmental pollution.
Disposal by Dilution
Discharging untreated or treated wastewater directly into natural water bodies (rivers, lakes, seas). It assumes receiving waters contain sufficient Dissolved Oxygen (DO) to satisfy BOD.
- Essential Conditions:
- Fresh sewage ( old).
- Floating solids and grit pre-removed.
- High DO in receiving water body.
- Rapid currents for rapid mixing.
- Stream is not used directly downstream for municipal drinking water.
- Standards of Purification (Dilution Ratio = Volume of Diluting Water / Volume of Sewage):
- Dilution Ratio : No treatment required. Raw sewage can be directly discharged.
- Dilution Ratio : Primary plain sedimentation required; TSS .
- Dilution Ratio : Chemical precipitation/sedimentation required; TSS .
- Dilution Ratio : Complete biological treatment required; TSS , .
- Effluent Tolerance Limits for Inland Surface Water Discharge:
- Total Suspended Solids (TSS): Maximum .
- 5-day BOD at : Maximum .
River Self-Purification and Oxygen Sag Curve
When sewage enters a stream, natural self-purification processes (dilution, sedimentation, oxidation, reduction, sunlight disinfestation) act over downstream travel distance.
1. Mix Concentration Equation
Where is concentration of mixture, and are sewage and river concentrations, and are sewage and river flow rates.
2. De-Oxygenation vs. Re-Oxygenation Dynamics
- De-oxygenation: Depletion of DO due to microbial organic breakdown.
- Re-oxygenation: Replenishment of DO absorbed from atmospheric surface interface.
- Oxygen Deficit (): Difference between saturation DO concentration () and actual DO ():
3. Streeter-Phelps Equation
Deficit at downstream flow time ():
Where:
- = Oxygen deficit at time ()
- = Initial combined oxygen deficit at point of discharge ()
- = Ultimate carbonaceous BOD of stream mixture at point of discharge ()
- = De-oxygenation constant (base 10, )
- = Re-oxygenation constant (base 10, )
Temperature Adjustment:
Critical Time () and Critical Deficit (): The maximum oxygen deficit occurs at critical time where :
Solved Mathematical Example (River Pollution)
City population = , sewage rate = , BOD = . River discharge = , upstream DO = , upstream BOD = . Assume sewage DO = .
Solution:
- Sewage flow .
- Available oxygen per day above outfall:
- Total BOD load just below outfall:
- Combined initial stream BOD concentration ():
Disposal by Land Treatment (Sewage Farming)
Applying sewage over land surfaces where plants consume nitrogen, phosphorus, and potassium, while water evaporates, transpires, or percolates into groundwater.
- Methods:
- Broad Irrigation / Sewage Farming: Flooding cultivated plots with sewage to grow crops (cotton, grass, sugarcane). Yield increases up to .
- Overland Flow: Application over sloped () vegetated terraced slopes; runoff collected at bottom.
- Rapid Infiltration (Infiltration-Percolation): High application rates over porous sandy basins for groundwater recharge.
- Application Techniques:
- Flooding: Basin plots flooded to depth .
- Surface Irrigation: Distribution parallel channels over sloped land.
- Ridge and Furrow: Sewage flows in furrows ( deep, wide); crops grown on dry ridges ( wide).
- Sub-surface Irrigation: Perforated underground pipes discharge directly to root zones.
- Spray Irrigation: Pressurized nozzle distribution.
Comparison: Dilution vs. Land Treatment
| Parameter | Dilution Process | Land Treatment |
|---|---|---|
| Resource Required | Requires large volume of natural water | Requires large area of open land |
| Urban Cost | Inexpensive near large rivers | Expensive near expanding cities |
| Management | Simple, passive dilution management | Requires intensive land soil management |
| Pretreatment | Mandatory stringent pre-treatment | Minimal pre-treatment required (PST) |
| Climate Sensitivity | High temperature lowers DO (risk) | Dry climates enhance evaporation |
| Revenue Generation | Generates no direct revenue | Generates income via crop yields |
Sludge Treatment, Dewatering, Digestion, and Disposal
Sludge is the accumulated semi-solid organic and inorganic concentrate generated during primary and secondary sedimentation processes.
Characteristics and Quantities of Sludge
- Primary Sludge: Gray slurry containing TSS. Highly offensive odor. Solids concentration ( volatile).
- Chemical Sludge: Dark brown/reddish. High TSS capture (), solids concentration .
- Secondary Activated Sludge: Golden brown, flocculent, relative low odor when fresh. Voluminous; solids concentration only .
- Trickling Filter Humus Sludge: Dark brown, contains decaying biological worms/film. Solids concentration non-settleable TSS.
Volumetric & Specific Gravity Relations of Sludge
Where:
- = Specific gravities of sludge, solids, water (), fixed solids, and volatile solids.
- = Percentage of total solids, water, fixed solids, and volatile solids.
Volume Change with Moisture Content:
Where and are initial and final percent moisture contents.
Sludge Treatment Chain
[Raw Sludge] ──> [Grinding & Blending] ──> [Thickening] ──> [Anaerobic Digestion] ──> [Dewatering] ──> [Final Disposal]
1. Thickening (Gravity Thickener)
Reduces water content using gravitational force.
- Circular tank equipped with scrapers and pickets.
- Surface Loading: .
- Detention Period: .
- Tank depth: Up to , max diameter .
2. Anaerobic Sludge Digestion
Biochemical breakdown of volatile organic solids into stable compounds in closed digesters. Volume reduces by .
- Biochemical Stages:
- Acid Production Stage: Anaerobic/facultative bacteria break down sugars and cellulose into organic acids, , . . Takes at .
- Acid Regression Stage: Intermediate stage; acid carbonates and nitrogenous compounds broken down. rises to . Takes .
- Alkaline Fermentation Stage: Resistant proteins and organic acids broken down into stable solids, methane (), , . . Takes .
- Operating Temperature Ranges:
- Mesophilic Digestion: (Optimum , digestion time ).
- Thermophilic Digestion: (Optimum , digestion time ).
- Digester Capacity Equation:
- Linear Digestion Process:
- Parabolic Digestion Process: Where = Fresh sludge daily input, = Digested sludge daily output, = Digestion period (), = Monsoon storage period ().
- Digester Gas Composition: Methane () , Carbon Dioxide () , Nitrogen & inert gases . Gas yield .
3. Sludge Dewatering
- Vacuum Filters: Cylindrical drum wrapped in filter cloth rotated in a sludge trough under sub-atmospheric vacuum pressure.
- Sludge Drying Beds: Open sand beds over gravel underdrains ( perforated pipes at slope spaced apart). Sand layer thickness , effective size , uniformity coefficient . Drying takes .
4. Incineration
Thermal destruction of organic sludge at high temperature, converting sludge into inorganic ash.
- Drying Zone (), Burning Zone (), Cooling Zone ().
- Types: Flash Type Incinerator, Multiple Hearth Incinerator.
5. Sludge Disposal Methods
- Dumping: Uncontrolled disposal in abandoned quarries/mines (only for stable ash/grit).
- Sanitary Landfill: Trenching and compacting dewatered sludge in layers ( thick), covering daily with earth ( thick).
- Lagooning: Digestion and storage in earthen lagoons ( deep) for .
- Land Spreading: Agricultural application of digested sludge cake as soil conditioner ( thick application).
Air Pollution, Human Excreta, Health Aspects, and Climate Change
Air Pollution
The presence of contaminants in the atmosphere at concentrations that pose risks to human health, safety, wildlife, or materials.
Sources of Air Pollution
- Fossil Fuel Combustion: , , , particulate matter from vehicles, industrial boilers, power plants.
- Agricultural Activities: Ammonia () emissions from fertilizers, livestock manure, pesticides.
- Industrial Processes: Refineries, cement factories, chemical plants releasing hydrocarbons, volatile organic compounds (VOCs), hydrogen sulfide.
- Mining Operations: Atmospheric dust, heavy metal particulates.
- Indoor Sources: Solvents, paints, cleaning agents, tobacco smoke.
- Deforestation: Destroys carbon sinks, releasing stored during forest clearing fires.
- Natural Sources: Wildfires, volcanic eruptions, sea salt spray, windblown dust, pollen.
Impacts of Air Pollution
- Human Health: Chronic bronchitis, asthma, lung cancer, respiratory infections, eye/throat irritation.
- Environmental: Acid Rain ( and forming and ), Eutrophication of water bodies via airborne nitrogen deposition, damage to crop foliage.
- Materials & Atmosphere: Corrosion of metals, discoloration of building surfaces, ozone layer depletion, global warming, visibility reduction (smog/fog).
Mitigation Measures
- Installation of industrial particulate control devices (electrostatic precipitators, fabric filters, cyclone separators, scrubbers).
- Transition to renewable energy (solar, wind, geothermal).
- Strict auto-emission standards and catalytic converters.
- Energy conservation and public mass transit adoption.
Human Excreta Characteristics and Pollution
Human feces represent solid/semi-solid undigested food residue passed from the large intestine.
- Average per capita production: fresh feces per person per day.
- Average pH: .
- Composition: water, dry solid matter.
- Solid Fraction Makeup: bacterial biomass, protein/nitrogenous matter, carbohydrates/undigested plant fiber, fats/lipids, calcium/iron phosphates.
- Unmanaged excreta pollutes subsoil water, creates severe odors, and acts as a primary vector transmission medium for waterborne infectious diseases.
Health Aspects of Water Supply and Sanitation
According to the World Health Organization (WHO), sanitation is the provision of facilities and services for the safe disposal of human urine and feces, alongside maintaining hygienic conditions through garbage collection and wastewater disposal.
Fecal-Oral Disease Transmission Route (The F-Diagram)
Microorganisms pass from human/animal feces of an infected host into the oral cavity of a new victim through five main vectors:
[ Infected Feces ] ──> ( Fluids / Water ) ──┐
──> ( Fields / Soil ) ──┼─> [ Food ] ──> [ Future Victim ]
──> ( Flies / Insects ) ──┤
──> ( Fingers / Hands ) ──┘
Barriers Against Disease Transmission
- Toilet Barrier: Blocks feces from contaminating fluids, fields, flies, and fingers at the source.
- Safe Water Barrier: Disinfection and water protection block transmission through fluids/water.
- Hygiene & Hand-Washing Barrier: Handwashing with soap breaks disease transmission from fingers to food and mouth.
Greenhouse Effect and Climate Change
The United Nations Framework Convention on Climate Change (UNFCCC) defines climate change as a change of climate attributed directly or indirectly to human activity that alters the composition of the global atmosphere.
Primary Greenhouse Gases (GHGs)
- Carbon Dioxide (): Released via fossil fuel burning, deforestation, biomass decay. Persists in the ocean-atmosphere system for thousands of years.
- Methane (): Emitted during oil/gas production, coal mining, livestock enteric fermentation, anaerobic landfill decay. Atmospheric lifetime ( global warming potential of ).
- Nitrous Oxide (): Emitted during synthetic fertilizer application and fossil fuel combustion. Lifetime .
- Fluorinated Gases (HFCs, PFCs, ): Synthetic industrial gases used in refrigeration/manufacturing. High global warming potentials.
Environmental Consequences
- Shifts in global rainfall patterns, leading to extreme droughts and floods.
- Thermal expansion of oceans and melting of Arctic sea ice/glaciers, raising sea levels and flooding coastal habitats.
- Increases in frequency and severity of heatwaves and forest wildfires.
- Species extinction and geographical shifting of wildlife habitats.
Solid Waste Management and Environmental Impact Assessment (IEE/EIA)
Solid waste management includes the collection, storage, transport, processing, recycling, and disposal of discarded solid materials.
Classifications of Solid Waste
- Municipal Solid Waste (MSW):
- Garbage: Putrescible organic food waste from kitchens, markets, and restaurants. Decomposes rapidly, creating severe odors and vector breeding.
- Rubbish: Non-putrescible combustible (paper, plastic, wood, rubber) and non-combustible (glass, metal, cans) solid waste.
- Ashes: Incombustible residue from burning wood, coal, or industrial furnaces.
- Demolition & Construction Waste: Inert dirt, stones, concrete, bricks, plaster.
- Treatment Plant Waste: Sludge and screenings from water/wastewater plants.
- Special Waste: Street sweepings, roadside litter, catch-basin debris, dead animals, abandoned vehicles.
- Industrial Waste: Process residues, toxic chemicals, slag, industrial rubbish.
- Hazardous Waste: Explosive, flammable, radioactive, toxic, or infectious wastes posing immediate or long-term health hazards.
Generation Rates
- Global Average: ( inorganic, organic).
- Developed Nations (USA, Europe): .
- Developing Nations: .
- Kathmandu City: .
Disposal Methods for Solid Waste
- Open Dumping: Uncontrolled dumping in low-lying areas or abandoned quarries. Highly unhygienic; promotes fly/mosquito breeding, surface water contamination, and bad odors.
- Sanitary Landfill: Highly engineered land disposal method. Waste is spread in thin layers (), mechanically compacted, and sealed daily with a protective soil cover ( thick). Prevents vector exposure and fire risks. Requires leachate collection systems and groundwater monitoring wells.
- Incineration: Thermal destruction of combustible waste in engineered high-temperature furnaces (). Reduces waste volume by and weight by . Ash residue is disposed of in sanitary landfills. Requires air pollution control equipment (scrubbers, electrostatic precipitators).
- Composting: Biological decomposition of putrescible organic waste into an organic soil conditioner (humus/compost).
- Trench Composting: Waste laid in trenches ( long, wide, deep) in waste layers alternating with night soil/animal dung layers. Converts to compost in .
- Open Windrow Composting: Waste piled outdoors in long windrows ( high, wide). Turned mechanically every to maintain aerobic conditions and control temperature (). Maturation takes .
- Mechanical Composting: Accelerated composting inside enclosed rotating drums/silos with controlled aeration, moisture (), and temperature (). Stabilizes waste in .
Environmental Assessment Principles
Frameworks designed to assess potential positive and negative impacts of proposed projects on physical, biological, and socio-economic environments prior to project approval.
Framework Definitions
- Initial Environmental Examination (IEE): A preliminary study conducted for small-to-medium scale projects to evaluate whether potential impacts are significant enough to warrant a detailed EIA.
- Environmental Impact Assessment (EIA): A comprehensive, formal administrative and technical process used to identify, predict, evaluate, and mitigate environmental impacts of major development proposals.
Key EIA Procedural Steps
- Project Proposal: Formulation of project concept.
- Screening: Determining whether an IEE or full EIA is legally required based on project thresholds.
- Scoping: Identifying key issues, boundaries, and drafting the Terms of Reference (TOR).
- Baseline Data Collection: Documenting existing physical, biological, and socio-economic baseline conditions.
- Impact Prediction: Forecasting environmental changes resulting from project construction and operation.
- Impact Assessment: Evaluating the significance of predicted impacts.
- Mitigation Measures: Formulating environmental protection measures and an Environmental Management Plan (EMP).
- Environmental Impact Statement (EIS / EIA Report): Compiling the final technical report.
- Public Hearing & Participation: Presenting findings to local stakeholders and gathering feedback.
- EIS Review: Expert evaluation of the report by regulatory authorities.
- Decision Making: Approval, conditional approval, or rejection of the project proposal by competent ministries.
- Monitoring and Environmental Auditing: Auditing actual project outcomes post-construction against initial predicted impacts.
Administrative Procedure for EIA in Nepal
- Public notice published in a national daily newspaper requesting stakeholder input ().
- Preparation and submission of Scoping Document and Terms of Reference (TOR) to concerned ministry.
- Submission of Scoping/TOR to the Ministry of Environment (MOEST) for review committee approval.
- Field study and EIA report preparation based on approved TOR.
- Public Hearing organized within the project site area.
- Submission of 10 copies of the EIA report to MOEST.
- Publication of public notice in a national daily newspaper by MOEST for public comments.
- MOEST review committee evaluation and final report approval within .
- Environmental Auditing performed after project commissioning.
Comparison: Initial Environmental Examination (IEE) vs. Environmental Impact Assessment (EIA)
| Parameter | Initial Environmental Examination (IEE) | Environmental Impact Assessment (EIA) |
|---|---|---|
| Project Scale | Applied to small or medium scale projects | Applied to large scale, high-impact projects |
| Scoping Requirement | Formal Scoping Report is not required | Formal Scoping Report & TOR are mandatory |
| Public Hearing | Public notice issued; formal hearing not required | Mandatory Public Hearing in the project area |
| Environmental Management Plan | Basic mitigation measures included | Detailed Environmental Management Plan (EMP) mandatory |
| Time and Cost | Less time-consuming and lower cost | Time-intensive and significantly higher cost |
| Approval Authority | Concerned Line Ministry | Ministry of Environment (MOEST) |
| Environmental Auditing | Not mandatory | Mandatory post-project auditing () |