Electricity Overview

  • Topic encompasses the fundamental aspects of electricity transmission and distribution.

Electricity Transmission and Distribution

  • Hierarchical Structure of Voltage Levels:

    • 400 kV

    • 275 kV

    • 132 kV

    • 33 kV

    • 11 kV

    • 415 volts

    • 230 volts

  • Transmission involves high-voltage lines that carry electricity over long distances, while Distribution refers to the lower-voltage lines that deliver electricity to homes and businesses.

Historical Context of the UK’s Electricity Transmission Network

  • The UK National Grid dates back to 1925 with the formation of the Central Electricity Board (CEB).

  • Objective: To create a “national gridiron” to efficiently supply electricity across Britain.

  • 1935: Seven key locations were selected to form the backbone of this interconnected network; control rooms established at each site.

  • 1937: Successful testing linking all seven grid locations, marking the operational launch of the National Grid.

Post-War Developments

  • By the late 1940s, electricity demand surged beyond expectations, leading to inadequacies in the existing 132 kV lines.

  • The electricity supply sector was mainly dominated by 569 small companies, predominantly local authority-run, accounting for two-thirds of electricity sales.

  • The Electricity Act 1947, effective from April 1, 1948, nationalised the electricity supply in Great Britain:

    • Established the British Electricity Authority (BEA) to manage the electricity grid.

    • BEA controlled generation and transmission, while Area Boards managed distribution and sales.

  • Plans were initiated for a new high-voltage grid operating at 275 kV, with future potential to upgrade to 400 kV.

Evolution of the Supergrid

  • Original Supergrid designed around conventional coal-fired power stations in the Midlands, facilitating North-South power flows to urban areas.

  • Current trends indicate an evolution toward accommodating renewable energy sources, particularly from offshore wind farms in the North Sea.

  • The National Grid is progressing towards a next-generation Supergrid to support the UK’s Net Zero targets.

Nuclear Power Development

  • August 27, 1957: Sellafield in Cumbria began operations as the first full-scale nuclear power station in the UK (and the Western world), contributing to the national grid for nearly 50 years before its closure in 2003.

Future Challenges and Upgrades

  • The existing electricity grid faces capacity challenges due to the anticipated surge in offshore renewable energy.

  • The UK is urged to enhance its electricity grid systems urgently, in preparation for an increase in demand and the shift towards decarbonisation, decentralisation, and digitalisation.

    • An estimated four times more transmission infrastructure must be constructed in the next seven years than the amount installed since 1990.

Current Generation and Transmission Grid

  • Visual representation (Flow Diagram) inclusive of key voltage lines, offshore wind projects, and existing circuits.

Capital Projects and Investments

  • National Grid is set to expedite up to 20 GW of grid connections, equivalent in capacity to six Hinkley Point C nuclear reactors.

  • Hinkley Point is recognized as Europe's largest construction site with ongoing development of two new nuclear reactors.

Distribution vs. Transmission

  • Transmission Lines: High-voltage electricity over long distances.

  • Distribution Lines: Lower-voltage electricity over shorter distances to consumers.

Legislation and Regulatory Framework

The Electricity Act 1989

  • Provides licensing for electricity generation and supply in England and Wales.

  • Section 10, Schedule 3 grants powers to license holders:

    • Acquire land and rights over land for distributing electricity (not for any other purpose).

Wayleave vs. Easement

  • Some landowners prefer a capital sum for an easement over annual wayleave payments, giving up rights to terminate.

  • Certain companies like National Grid now offer only easements.

Acquisition by Agreement

  • Schedule 3 Part 1 establishes protocols for acquiring land or rights via agreement, involving standard documents that outline terms and conditions for installation.

Compulsory Acquisition

  • If mutual agreement is unattainable:

    • A formal notice is served requiring a wayleave within 21 days.

    • If not granted, an application for compulsory purchase order is submitted to the Secretary of State, typically for land related to substations.

Construction Under Pylons

  • Historical context on high-voltage overhead line placement in relation to urban developments.

  • Developers often seek to relocate overhead lines, but National Grid expresses preference to retain lines due to environmental and cost considerations.

Health and Safety Considerations

Electric and Magnetic Fields (EMFs)

  • Current international scientific evidence does not support any causal relationship between EMFs from high voltage power lines and health issues such as cancer.

  • No special government precautions regarding home development near power lines are recommended based on EMF evidence.

Undergrounding Options

Low Voltage Undergrounding

  • Methods include ploughing and directional drilling for the installation of low voltage lines.

Technologies for Connection

400kV AC Overhead Lines

  • Typical spacing is 365m.

  • Various pylon designs discussed:

    • Conventional lattice: Height typically 40m-50m.

    • Low-height lattice: Height typically 38m-41m.

    • T-pylon: Height typically 35m-38m.

Underground 400 kV AC Cable Specifications

  • Conductor made of copper or aluminum.

  • Insulation: Cross-linked polyethylene (XLPE).

Tunneling Considerations

  • Tunnel dimensions and construction methods are outlined for underground cable installations, including necessary ventilation and emergency access points.

Development Consent Orders (DCOs)

  • Established by the Planning Act 2008 for projects categorized as Nationally Significant Infrastructure (NSIP).

    • DCOs govern construction and maintenance permissions for energy, transportation, and water projects.

    • Planning Inspectorate manages applications, examining public opinions and evidentiary support before presenting recommendations to the Secretary of State for decision making.

Application Process Steps for DCOs

  1. Pre-Application: Public consultations are conducted.

  2. Acceptance: Application is received and verified by the Planning Inspectorate.

  3. Examination: Detailed evidence review over six months.

  4. Recommendation and Decision: Report issued to Secretary of State for approval or rejection.

  5. Post Decision: Period for judicial reviews is allowed for six weeks post-decision.