Module 2 Notes: Scope Management and WBS

Module Agenda

  • From previous module
  • Project management process groups
  • Scope management
  • Scope baseline: scope statement, work breakdown structure (WBS) and WBS dictionary
  • Homework and evaluations

PMBOK Knowledge Areas (10)

  • Integration: Includes the processes and activities to identify, define, combine, unify, and coordinate the various project management processes.
  • Scope: Includes the processes required to ensure the project includes all the work required, and only the work required, to complete the project successfully.
  • Schedule: Includes the processes required to manage the timely completion of the project.
  • Cost: Includes the processes involved in planning, estimating, budgeting, financing, funding, managing, and controlling costs to complete the project within the approved budget.
  • Quality: Includes the processes for incorporating the org. quality policy regarding planning, managing, & controlling project and product quality requirements, to meet stakeholders' expectations.
  • Resource: Includes the processes to identify, acquire, and manage the resources needed for the successful completion of the project.
  • Communications: Includes the processes required to ensure timely and appropriate generation, collection, distribution, storage, and ultimate disposition of project information.
  • Risk: Includes the processes of conducting risk management planning, identification, analysis, response planning, response implementation, and monitoring risk on a project.
  • Procurement: Includes the processes to purchase or acquire products, services, or results needed from outside the project team.
  • Stakeholder: Identify stakeholders, analyze their expectations, their impact on the project and develop effective engagement strategies.

PMBOK Process Groups and Project Lifecycle

  • The project management process groups relate to the project life cycle and the knowledge areas.
  • Level of overlap between groups; the lifecycle informs how processes are applied.

Overlapping Project Management Process Groups

  • Planning processes are performed to nearly the end of the project.
  • Monitoring and Controlling processes are performed throughout the entire project duration.

Scope Management (Knowledge Area 5)

  • Definition: Scope management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.
  • Focus: Managing project scope is primarily concerned with defining and controlling what is and is not included in the project.
  • IMPORTANT: We generally need to define scope before we can estimate costs and develop a budget in cost management.

Cost Management and the Role of Scope Baseline

  • PMBOK 6 - PROJECT COST MANAGEMENT: Project scope is a key input into cost management.
  • The project management plan, which is an input to all the cost processes, includes all the other knowledge area plans, but most importantly, the scope baseline.
  • The project management plan is an important overarching document for cost processes.

Components of the Project Management Plan

  • Scope Management Plan
  • Requirements Management Plan
  • Schedule Management Plan
  • Cost Management Plan
  • Quality Management Plan
  • Resource Management Plan
  • Communications Management Plan
  • Risk Management Plan
  • Procurement Management Plan
  • Stakeholder Engagement Plan
  • Scope Baseline
  • Schedule Baseline
  • Cost Baseline
  • Change Management Plan
  • Configuration Management Plan
  • Performance Measurement Baseline
  • Project Life Cycle Description
  • Development Approach

Scope Baseline

  • Definition: The approved version of a (1) scope statement, (2) work breakdown structure (WBS), and (3) its associated WBS dictionary, that can be changed using formal change control procedures and is used as a basis for comparison to actual results.
  • Components: Scope Statement, WBS, WBS Dictionary
  • These three components form the baseline used to compare planned vs. actual project performance.

Scope Baseline – 1. Scope Statement (SOW)

  • Provides an overview of the project and generally includes:
    • Key objectives of the project
    • Expected outcomes of the project
    • An abbreviated description of the scope (the work to be completed) in the project
    • An introduction
    • Background of the project
    • An introductory technical description of the project
    • A high-level timeline (an estimated duration)
  • Major milestones

Scope Baseline – 2. Work Breakdown Structure (WBS)

  • WBS is a hierarchical outline (map) that identifies the products and work elements involved in a project.
  • Defines the relationship of the final deliverable (the project) to its sub-deliverables, and in turn, their relationships to work packages.
  • Best suited for projects that have tangible outcomes rather than process-oriented projects.

WBS Levels and Structure

  • Project Level (Level 1)
  • Major Deliverable Level (Level 2)
  • Sub Deliverable Level (Level 3)
  • Lowest Sub Deliverable Level / Work Packages (Level 4)
  • Work Packages (WP): lowest level deliverable; trackable; one owner; a miniature project; includes milestones; describe the "what" (deliverable) while Activities describe the "how".

WBS vs Activities

  • Work packages describe the deliverables and are written as NOUNS.
  • Activities describe the work to produce the deliverables and are written as VERBS.
  • WP must contain activities; activities reside inside a WP.
  • Activities describe the resources, duration, and cost required to complete the work.
  • Activities are not typically shown as boxes in a WBS diagram; they are detailed underneath the WP if shown.

The 100% Rule

  • The combination of the boxes on each level represents 100% of the parent package.
  • Example: 5,000+2,000+2,000=9,0005{,}000 + 2{,}000 + 2{,}000 = 9{,}000
  • Another example: 25,000+61,000=86,00025{,}000 + 61{,}000 = 86{,}000
  • These illustrate how child components sum to the parent budget/level total.

WBS Codes

  • The project deliverable has the WBS code 1.01.0 for the overall project.
  • Major deliverables: 1.2,1.3,1.41.2, 1.3, 1.4
  • Sub-deliverables (blue) are supporting deliverables (like a folder within a folder).
  • We are only finished decomposing major deliverable 1.21.2 of this WBS; the lowest level deliverables (green) are called work packages.
  • Figure: A partial WBS without project names to focus on WBS codes.

Hierarchical vs Non-Hierarchical WBS

  • Hierarchical WBS is easier to visualize.
  • A non-hierarchical WBS is generally more difficult to visualize.

Creating a Hierarchical WBS in MS Project

  • Enter the WBS elements into the Task Name column in a new .mpp file.
  • Use indents to emulate a hierarchy.
  • Do NOT enter the WBS codes; MS Project will create the codes based on order and indentation of items.

Sample WBS in MS Project (MS Project Notes)

  • Control the levels of the WBS by using the indent and outdent buttons.
  • Summary tasks are shown in bold; Detailed tasks show as a bar only if they have a duration.
  • They represent an activity.
  • We enter durations for detailed tasks; summary task durations are calculated automatically.
  • Typically, there are multiple activities in a WP.
  • Activities (detailed tasks) are placed below a WP (summary task) and are indented.
  • A WP is a special deliverable; it is the lowest level deliverable in any branch of the WBS.

Common WBS Error

  • Activities were placed outside of a work package (i.e., directly under a sub-deliverable).
  • Important: Activities can reside ONLY within a work package.

WBS Dictionary

  • The WBS dictionary provides detailed descriptions for each element within a project WBS.
  • Shown here in table format.

WBS Dictionary – Example (Entries)

  • Work Package ID: 1.4.1.1

  • Work Package Name: Designed User Screen

  • Work Package Description/Statement of Work: Using the customer's User Screen Specification, a new top-level layout design is to be created. A non-functioning layout demonstrator will be prepared to collect feedback; a fully functional prototype will be created for client review and approval.

  • Acceptance Criteria

  • Deliverables

  • Duration

  • Cost

  • Due Date

  • Dependencies

  • Approvers

  • Assigned To: Dave Litten

  • Date Assigned: 7/30/09

  • Estimated Cost: 3,800.003{,}800.00

  • Group/Dept: IT Systems

  • Date Due: 15/9/09

  • Account Code: CHD/1/4/33

  • Resources Assigned

  • Assumptions

  • Example: 1.1.2 System Requirements Document – System Analyst, Tier 1 Engineering Team; System requirements document will detail project requirements from a technical perspective; Signoff from key stakeholders and responsible departments; SR Doc; Duration: 4extweeks4 ext{ weeks}; 2 FTP; Due: 6/29

Homework and Evaluations

  • Readings for Module 3 as listed in Course Overview
  • Complete the learning activities in Module 2 in FOL (including Module 2 Tutorial).
  • Quiz 1 – see details in FOL
  • Individual presentation – must be presented before week of Module 14
    • In-person class: sign up to present during an upcoming class
    • Online class: get familiar with the use of Virtual Classroom/Bongo

References

  • Kerzner, Harold (2017). Project Management, Twelfth Edition.
  • Larson, Eric W., Gray, Clifford F. (2018). Project Management, The Managerial Process (Seventh Edition).
  • Project Management Institute (2017). A Guide to the Project Management Body of Knowledge (Sixth Edition).
  • Project Management Institute (2021). A Guide to the Project Management Body of Knowledge (Seventh Edition).