Folsom Project Meeting Notes (June 6, 2024)
Project Updates and Discussions
Outstanding Items and Assistance
- Lighting Package: Finalizing is a priority; currently behind schedule.
- Submittals:
- Issue for permit drawings: fire alarm, IRCs, and two-way radio.
- Submittal status: MSB one and MSB two.
- PV (Photovoltaic) System:
- Issues with SMUD (Sacramento Municipal Utility District) approval.
- SMUD's pilot program may not be a pilot program.
- The vendor is non-responsive; struggling to answer questions.
- Concern about potential cost impact due to delays.
PV System and SMUD Approval
- Follow up with the PV vendor to get a response to SMUD.
- Potential cost increases for MSBs (Main Switch Boards) due to delays should be avoided.
Lighting Fixture Changes
- Design team resistant to changes; significant cost difference in fixtures.
- Need to convince the owner to approve the change, as VE (Value Engineering) wasn't done with the owner.
Project Schedule and Delays
- An updated master schedule has been created to account for rain delays.
- The start of secondaries is planned for mid-August.
- Multi-family project delays are impacting manpower projections.
- The foreman, Joe, will be shifted to this project after wrapping up a 200-unit multifamily project in Sacramento.
Weather Considerations and Drying In
- Plan is to dry in the whole building at once.
- Consider phasing the dry-in process to allow MEPs (Mechanical, Electrical, and Plumbing) to start work in phases.
- Roof framing duration: 10 days.
- Roof installation duration: 15 days.
- Electrical inspectors typically require all windows and window flashing to be in place before allowing wire pulling.
- Flexibility to start on one end of the building and work from southwest to northeast.
- Roof framing completion: November 12, 2025.
- Estimated dry-in completion: early December.
Project Duration and Acceleration
- The project is on a 22-month schedule, with delays tacked onto the end.
- No official request for acceleration.
- Buffer built into the schedule, aiming for completion by October 14, 2026, before the 22-month mark.
Change Orders
- RFI (Request for Information) 22: Heat pump upsize (likely in the owner's hands).
- SMUD primary work handled by the joint trench contractor.
- AT&T and Comcast work also with the joint trench contractor.
- Secondary and primary conduit deduct: joint trench will handle everything; electricians just pull wire.
- Temp power: handled.
- Fire alarm: to be resolved after building permit issuance.
- MSBook d one PV: pending SMUD approval; may revert to the original plan.
- PV raceways: electrical team to handle raceways from the electrical room to the arrays.
- Fireplace deduct: fireplace has been ordered.
- Price increase due to tariffs: avoided.
- Trash compactor wiring: RFI out.
- Joint trench credit: 33 reduction if joint trench handles primaries.
- Building permit issuance dependent on grading and fire road completion.
- Last communication with FAAHJ (Authority Having Jurisdiction) in April; awaiting a definitive answer from Tammy (coordinator) and Allison (building official).
- Aiming to get pad certification and building permit issued before the end of the year to maintain the 2019 code cycle.
- Allison (chief building official) indicated the building pad should be ready in time.
- The 90k amount tied to FAAHJ comments is related to low-frequency devices and may be avoided if the 2019 code cycle is maintained.
Outstanding Items and Coordination
- Need a response from SMUD and resolution on lighting fixtures.
- Potential delays due to lack of response from the PV contractor is a concern.
- Meeting to be scheduled towards the end of the month for further updates.