Meeting Notes: Plan Check, Coordination, and Submittal Strategy

Meeting Notes: Plan Check, Coordination, and Submittal Strategy

  • Purpose and scope
    • Coordination meeting focused on plan check responses, progress sets, and coordination across disciplines for Buildings A, B, C, D, and related sites (Fitness/Cottage references), plus utilities, permits, and site logistics.
    • Key themes: plan check comments, submittal schedules, utility relocations/easements, power and low-voltage coordination, and site constraints (parking, Green Book compliance).

Attendees and roles (highlights)

  • Participants include representatives coordinating plan checks, electrical, mechanical, plumbing, fire protection, civil, fire alarm, lighting, and external utility coordination (Easements/UNR/AE/Planning).
  • Notable absences or mentions: Rory was not on the call; other team members carried forward items for discussion.

Plan Check and Submittals

  • Fitness and Cottage plan check responses
    • Richard reported outstanding items for plan check responses on Fitness or Cottage.
    • Still waiting on a couple of consultants; network access was down, so he could not open documents to verify missing items.
    • Mechanical and Plumbing for Fitness response potentially missing; Richard will double-check and send a list once network access is restored.
    • Action: Richard to circulate the missing items list after the meeting.
  • Auditorium submittal
    • Auditorium has been submitted and is in review.
    • Billing comments expected this week.
  • Coordination with CRD and progress sets
    • Goal: obtain progress sets from all consultants; Electrical is the only one not yet providing a progress set.
    • If all progress sets are received, the team can perform a cursory review to identify items needing cleanup or coordination.
    • Richard to receive the combined progress set after the meeting.
  • Building C and D progress sets and reviews
    • General statement: progress sets have been collected from all teams except Electrical; once received, a review will be performed for consistency and coordination.
    • Building A: internal plan review completed; mechanical comments from Sandra were reviewed and no major issues observed; awaiting final follow-up if needed.
    • Building B and C coordination items highlighted by multiple members; aim to finalize approvals and circulate comments.
  • Lighting, Fire Alarm, and Low Voltage coordination
    • Joe and Huaji discussed lighting details needing clarification (three-foot clearance and under-ground routing). Mechanical progress sets to inform the lighting plan.
    • Fire alarm coordination: need fire alarm plan from Jim to align with power and building systems; plan to push for a PDF update with changes moved to the south ramp area.
    • Low voltage coordination: undergrounding considerations and potential downtime for Building D; discuss implications for site energization and sequencing. If downtime is required, plan must minimize disruption and maintain essential power where possible.
  • Power requirements and coordination for Buildings C and D
    • discussion with Anthony about how to energize and reconfigure power during undergrounding of low voltage.
    • Considerations include keeping the site energized during the process and the potential need to loop power around the site; assess feasibility with AE and Planning.
  • Action items by discipline (summary)
    • Electrical: provide progress set for Buildings B and C; review for coordination once received.
    • Mechanical: supply progress sets and confirm pumping and HVAC coordination for Buildings C and D.
    • Fire Alarm: obtain and share the fire alarm plan from Jim; align with electrical and low-voltage work.
    • Lighting: confirm location and routing; share PDF updates showing changes to the south ramp and fitness area.
    • Civil/Drainage: verify plumbing and civil latest plan alignment; avoid last-minute changes; ensure site-wide consistency.
    • Fire Sprinklers: Dawn to confirm coordination status; no open items noted at this time.

Site, Permitting, and Utilities Coordination

  • Planned submittals and schedule
    • Buildings C and D to be delivered for the 18th, with a 19th submittal date. For Building A, plan check comments expected by the end of this week or early next week.
    • Overall plan check comments to be distributed as they are received.
  • Easements, utilities, and third-party coordination
    • Ongoing discussion on utility relocations and easements for Fellowship Plaza; potential long lead times requiring early engagement.
    • Mark (UNR) involved in easement discussions; engineering teams pushing to advance with the joint trench drawings and determine if new easements are required.
    • Don and others noting that the ease of moving utilities through Fellowship Plaza could take months; aim to push for early action and avoid delays in project timelines.
  • Sewer coordination and invert considerations
    • Coordination to locate sewer lines with a utility locator; results to be shared when available.
    • In Building C, there is an emphasis on ensuring an acceptable invert to avoid installing a sewage lift station; Building D invert considerations seem less urgent due to location.
  • Site development permits and critical path notes
    • Full site development permit set targeted for early August; ensure all disciplines are aligned so there are no conflicting changes that delay distribution.
  • Fitness and fire water routing updates
    • Changes to the fighters’ water riser and routing discussed; PDF updates to be circulated; the team will review the updated set showing the south ramp and relocated water lines.
  • Relocation of domestic and fire lines in Building C
    • Domestic and fire lines moved to the south ramp in Building C; for Building D, new routing is via Odd Fellows Drive; these updates have been circulated and are under review.
  • Utility relocation timing and coordination with Fellowship Plaza
    • Potential requirement to move utilities outside existing easement at Fellowship Plaza; the team will pursue an initial set to gauge review timelines; if needed, new easements must be prepared for review by the managing entity (LA corporate office mentioned as a potential bottleneck).
  • Action items
    • Provide locator results for sewer lines when available and share with the team.
    • Prepare and circulate updated utility drawings showing current routing for Building C and D.
    • Initiate discussions with AE and Planning on the parking and tree removal trade-offs related to Building C parking layout.

Parking, Site Layout, and Planning Considerations

  • Building C parking and landscape constraints
    • The team is evaluating the need to remove two parking spaces and a tree; a line behind (dash line) could potentially be used to free up space in the front, but this requires design adjustments and planning approvals.
    • There was confusion over whether only one parking stall could be removed; the current conclusion is that two spaces would need to be sacrificed plus a tree removal, which is challenging and requires alternative strategies.
    • Next steps: internal discussions to develop feasible alternatives; possibly revert to the line behind (dashed line) if acceptable; plan to discuss further in upcoming meetings.

Schedule, Deliverables, and Next Steps

  • Upcoming meetings and deliverables
    • Resident meeting scheduled for the 25th in the afternoon around 2:00 PM; a PowerPoint presentation will be prepared with slides in a consistent format; Team members to supply a few slides for preparation.
    • Plan check comments for Building A to be distributed as soon as they are received; C and D submittals targeted for about 22 weeks from now.
  • Documentation and coordination expectations
    • Ensure plumbing and civil latest plan alignment; if any mismatch is found, notify immediately to avoid last-minute changes.
    • The site development permit set for early AugustAugust should be distributed to all by the deadlines; if it wasn’t, coordinate with the team to circulate.
    • Sharing of updated fitness drawings showing the fire riser relocation to the south ramp; Timely PDF updates to be distributed to all members.

Notable Issues, Risks, and Decisions

  • Green Book compliance and termination plan for Building C transformer layout
    • The termination plan transformer layout for Building C is planned for the 2929 (specific month/year details to be confirmed). Emphasis on ensuring PG compliance to avoid site shutdowns once plan is approved and on-site.
    • Layout constraints include providing two parking spaces and a peninsula while keeping minimum clearances of 8extft8 ext{ ft} in front of certain elements, and aligning with back-of-house placements for site efficiency.
    • If two spaces must be sacrificed, options include moving the ramp alignment and possibly using shown dashed lines; a final determination requires AE and Planning input and cost/space impact analysis.
  • Power continuity during undergrounding
    • The team discussed keeping the site energized during undergrounding and stated that a one-day downtime is typical for switching; however, there is interest in looping around the site to minimize disruption for the five boxes on the opposite side.
    • Action: Anthony to coordinate with AE and Planning to assess feasibility of a looped power configuration and communicate any implications to the broader team.
  • Infrastructure coordination with external stakeholders
    • Ongoing challenges with easement approvals and utility relocations outside Fellowship Plaza; potential months-long process; plan to push for earlier action and provide regular updates to the team.

Quick Reference: Key Dates and Numbers (LaTeX format)

  • Expected submittal for Buildings C and D: 1818 (delivery date) and 1919 (submittal date)
  • Plan check comments for Building A: expected by the end of weekweek or early nextnext week
  • Parking and setbacks: minimum clearance of 88 feet (in relevant locations)
  • Two parking spaces to be sacrificed for Building C layout; potential tree removal; explore alternatives using the dashed line option
  • Transformer layout planning date: 2929 (for Building C transformer-related activity)
  • Early August: target for site development permit set distribution
  • Resident meeting: 2525th (afternoon) at approximately 2:002:00 PM

Quick actions for follow-up (owner assigns)

  • Richard: Compile and circulate the missing plan-check items for Fitness/Cottage once network access is restored; confirm Mechanical and Plumbing items.
  • Electrical lead: Provide progress set for Buildings B and C as soon as available; participate in cursory coordination review.
  • Jim: Share the fire alarm plan; coordinate with electrical and low-voltage teams; provide updates in PDF.
  • Joe/Huaji: Finalize lighting clarifications; share updated PDFs reflecting changes to the south ramp and fitness area.
  • Ferduland and team: Confirm mechanical pumping process details; share mechanical progress sets for Building D; coordinate with civil and plumbing.
  • Dawn: Confirm fire sprinkler coordination status; provide any updates.
  • Don: Prepare the resident meeting slides; ensure a uniform PowerPoint format; circulate to the team.
  • AE/Planning: Review parking/layout changes for Building C; evaluate the feasibility of the dash-line solution and parking-tree trade-offs.
  • UNR/Mark: Advance easement discussions and provide status updates; coordinate the joint trench drawings if relocation outside current easement is needed.
  • Anthony: Lead discussions on undergrounding and looping power for Building D; provide a more detailed plan on possible downtime and site energization strategy.

Note: If you’d like, I can convert these notes into a more concise study handout or create a discipline-by-discipline checklist to help you study for the exam. Would you prefer that format as well?