Meeting Notes: Plan Check, Coordination, and Submittal Strategy
Meeting Notes: Plan Check, Coordination, and Submittal Strategy
- Purpose and scope
- Coordination meeting focused on plan check responses, progress sets, and coordination across disciplines for Buildings A, B, C, D, and related sites (Fitness/Cottage references), plus utilities, permits, and site logistics.
- Key themes: plan check comments, submittal schedules, utility relocations/easements, power and low-voltage coordination, and site constraints (parking, Green Book compliance).
Attendees and roles (highlights)
- Participants include representatives coordinating plan checks, electrical, mechanical, plumbing, fire protection, civil, fire alarm, lighting, and external utility coordination (Easements/UNR/AE/Planning).
- Notable absences or mentions: Rory was not on the call; other team members carried forward items for discussion.
Plan Check and Submittals
- Fitness and Cottage plan check responses
- Richard reported outstanding items for plan check responses on Fitness or Cottage.
- Still waiting on a couple of consultants; network access was down, so he could not open documents to verify missing items.
- Mechanical and Plumbing for Fitness response potentially missing; Richard will double-check and send a list once network access is restored.
- Action: Richard to circulate the missing items list after the meeting.
- Auditorium submittal
- Auditorium has been submitted and is in review.
- Billing comments expected this week.
- Coordination with CRD and progress sets
- Goal: obtain progress sets from all consultants; Electrical is the only one not yet providing a progress set.
- If all progress sets are received, the team can perform a cursory review to identify items needing cleanup or coordination.
- Richard to receive the combined progress set after the meeting.
- Building C and D progress sets and reviews
- General statement: progress sets have been collected from all teams except Electrical; once received, a review will be performed for consistency and coordination.
- Building A: internal plan review completed; mechanical comments from Sandra were reviewed and no major issues observed; awaiting final follow-up if needed.
- Building B and C coordination items highlighted by multiple members; aim to finalize approvals and circulate comments.
- Lighting, Fire Alarm, and Low Voltage coordination
- Joe and Huaji discussed lighting details needing clarification (three-foot clearance and under-ground routing). Mechanical progress sets to inform the lighting plan.
- Fire alarm coordination: need fire alarm plan from Jim to align with power and building systems; plan to push for a PDF update with changes moved to the south ramp area.
- Low voltage coordination: undergrounding considerations and potential downtime for Building D; discuss implications for site energization and sequencing. If downtime is required, plan must minimize disruption and maintain essential power where possible.
- Power requirements and coordination for Buildings C and D
- discussion with Anthony about how to energize and reconfigure power during undergrounding of low voltage.
- Considerations include keeping the site energized during the process and the potential need to loop power around the site; assess feasibility with AE and Planning.
- Action items by discipline (summary)
- Electrical: provide progress set for Buildings B and C; review for coordination once received.
- Mechanical: supply progress sets and confirm pumping and HVAC coordination for Buildings C and D.
- Fire Alarm: obtain and share the fire alarm plan from Jim; align with electrical and low-voltage work.
- Lighting: confirm location and routing; share PDF updates showing changes to the south ramp and fitness area.
- Civil/Drainage: verify plumbing and civil latest plan alignment; avoid last-minute changes; ensure site-wide consistency.
- Fire Sprinklers: Dawn to confirm coordination status; no open items noted at this time.
Site, Permitting, and Utilities Coordination
- Planned submittals and schedule
- Buildings C and D to be delivered for the 18th, with a 19th submittal date. For Building A, plan check comments expected by the end of this week or early next week.
- Overall plan check comments to be distributed as they are received.
- Easements, utilities, and third-party coordination
- Ongoing discussion on utility relocations and easements for Fellowship Plaza; potential long lead times requiring early engagement.
- Mark (UNR) involved in easement discussions; engineering teams pushing to advance with the joint trench drawings and determine if new easements are required.
- Don and others noting that the ease of moving utilities through Fellowship Plaza could take months; aim to push for early action and avoid delays in project timelines.
- Sewer coordination and invert considerations
- Coordination to locate sewer lines with a utility locator; results to be shared when available.
- In Building C, there is an emphasis on ensuring an acceptable invert to avoid installing a sewage lift station; Building D invert considerations seem less urgent due to location.
- Site development permits and critical path notes
- Full site development permit set targeted for early August; ensure all disciplines are aligned so there are no conflicting changes that delay distribution.
- Fitness and fire water routing updates
- Changes to the fighters’ water riser and routing discussed; PDF updates to be circulated; the team will review the updated set showing the south ramp and relocated water lines.
- Relocation of domestic and fire lines in Building C
- Domestic and fire lines moved to the south ramp in Building C; for Building D, new routing is via Odd Fellows Drive; these updates have been circulated and are under review.
- Utility relocation timing and coordination with Fellowship Plaza
- Potential requirement to move utilities outside existing easement at Fellowship Plaza; the team will pursue an initial set to gauge review timelines; if needed, new easements must be prepared for review by the managing entity (LA corporate office mentioned as a potential bottleneck).
- Action items
- Provide locator results for sewer lines when available and share with the team.
- Prepare and circulate updated utility drawings showing current routing for Building C and D.
- Initiate discussions with AE and Planning on the parking and tree removal trade-offs related to Building C parking layout.
Parking, Site Layout, and Planning Considerations
- Building C parking and landscape constraints
- The team is evaluating the need to remove two parking spaces and a tree; a line behind (dash line) could potentially be used to free up space in the front, but this requires design adjustments and planning approvals.
- There was confusion over whether only one parking stall could be removed; the current conclusion is that two spaces would need to be sacrificed plus a tree removal, which is challenging and requires alternative strategies.
- Next steps: internal discussions to develop feasible alternatives; possibly revert to the line behind (dashed line) if acceptable; plan to discuss further in upcoming meetings.
Schedule, Deliverables, and Next Steps
- Upcoming meetings and deliverables
- Resident meeting scheduled for the 25th in the afternoon around 2:00 PM; a PowerPoint presentation will be prepared with slides in a consistent format; Team members to supply a few slides for preparation.
- Plan check comments for Building A to be distributed as soon as they are received; C and D submittals targeted for about weeks from now.
- Documentation and coordination expectations
- Ensure plumbing and civil latest plan alignment; if any mismatch is found, notify immediately to avoid last-minute changes.
- The site development permit set for early should be distributed to all by the deadlines; if it wasn’t, coordinate with the team to circulate.
- Sharing of updated fitness drawings showing the fire riser relocation to the south ramp; Timely PDF updates to be distributed to all members.
Notable Issues, Risks, and Decisions
- Green Book compliance and termination plan for Building C transformer layout
- The termination plan transformer layout for Building C is planned for the (specific month/year details to be confirmed). Emphasis on ensuring PG compliance to avoid site shutdowns once plan is approved and on-site.
- Layout constraints include providing two parking spaces and a peninsula while keeping minimum clearances of in front of certain elements, and aligning with back-of-house placements for site efficiency.
- If two spaces must be sacrificed, options include moving the ramp alignment and possibly using shown dashed lines; a final determination requires AE and Planning input and cost/space impact analysis.
- Power continuity during undergrounding
- The team discussed keeping the site energized during undergrounding and stated that a one-day downtime is typical for switching; however, there is interest in looping around the site to minimize disruption for the five boxes on the opposite side.
- Action: Anthony to coordinate with AE and Planning to assess feasibility of a looped power configuration and communicate any implications to the broader team.
- Infrastructure coordination with external stakeholders
- Ongoing challenges with easement approvals and utility relocations outside Fellowship Plaza; potential months-long process; plan to push for earlier action and provide regular updates to the team.
Quick Reference: Key Dates and Numbers (LaTeX format)
- Expected submittal for Buildings C and D: (delivery date) and (submittal date)
- Plan check comments for Building A: expected by the end of or early week
- Parking and setbacks: minimum clearance of feet (in relevant locations)
- Two parking spaces to be sacrificed for Building C layout; potential tree removal; explore alternatives using the dashed line option
- Transformer layout planning date: (for Building C transformer-related activity)
- Early August: target for site development permit set distribution
- Resident meeting: th (afternoon) at approximately PM
Quick actions for follow-up (owner assigns)
- Richard: Compile and circulate the missing plan-check items for Fitness/Cottage once network access is restored; confirm Mechanical and Plumbing items.
- Electrical lead: Provide progress set for Buildings B and C as soon as available; participate in cursory coordination review.
- Jim: Share the fire alarm plan; coordinate with electrical and low-voltage teams; provide updates in PDF.
- Joe/Huaji: Finalize lighting clarifications; share updated PDFs reflecting changes to the south ramp and fitness area.
- Ferduland and team: Confirm mechanical pumping process details; share mechanical progress sets for Building D; coordinate with civil and plumbing.
- Dawn: Confirm fire sprinkler coordination status; provide any updates.
- Don: Prepare the resident meeting slides; ensure a uniform PowerPoint format; circulate to the team.
- AE/Planning: Review parking/layout changes for Building C; evaluate the feasibility of the dash-line solution and parking-tree trade-offs.
- UNR/Mark: Advance easement discussions and provide status updates; coordinate the joint trench drawings if relocation outside current easement is needed.
- Anthony: Lead discussions on undergrounding and looping power for Building D; provide a more detailed plan on possible downtime and site energization strategy.
Note: If you’d like, I can convert these notes into a more concise study handout or create a discipline-by-discipline checklist to help you study for the exam. Would you prefer that format as well?