Guideline Engineering Support: Electrical Systems
Document Structure
Title: Engineering Support Electrical Systems
Author: Linda Aspeljung Ronnerstam
Company: Siemens Energy AB
Revision Date: February 25, 2025
Table of Contents
Navigation and Introduction
Purchase Process
SAP Guidelines and Transactions
Stock Balance and Management
Purchase Requisition Process
Material Requests
Creating and Managing Parts
Workflows and Approvals
Explanation of Contents
1. Way of Working / Introduction
The Engineering Support team is responsible for SAP support and some basic PLM tasks.
Key responsibilities include:
Tracking TB (Technical Block) statuses, faults, and time registration per project.
Administration of SharePoint and guideline creation.
Terminology Dictionary:
Part: also referred to as Article or Material.
TB: encompasses Part TB (del-TB) and Complete TB (komplett TB).
2. Purchase Process from an Engineering Angle
Comos: Used for arranging parts and drawings.
PLM: Responsible for the finalization of parts/documents.
Material Registration: Requires an email to be sent post Part status approval (status 30).
TB Processing: Handled by MLP department for purchase requests.
3. SAP Interface Guidelines
Plant Codes: E.g., 1100 for Gas Turbines, 2800 for Service.
Essential SAP Guidelines:
Process ordering materials (E1B100847658).
Fault reporting and administration guidelines.
4. Key Transactions in SAP
User Display (SU01D): Access user data.
Time Sheet (CAT2): Maintain recorded times.
Purchase Order Transactions:
ME2M: For purchasing data, checks on quantities, suppliers, and more.
Stock and Material Management:
MD04: Display stock and requirements.
5. TB Placement Guidelines
To place a TB in SAP:
Ensure filled details include specific networks and activities.
Make sure not to place a TB if the latest finish date is overdue.
Confirmation of workflow acceptance is mandatory.
6. Purchase Requisition (PR) Procedures
PR is necessary after TB placement and requires approval before processing to the purchasing department.
Email notification to manager needed for PR releases.
7. Creating/Housing Parts in PLM
Parts must be created, updated, and linked to respective projects in PLM following company protocols.
Hierarchy of HG (Head Group) structure must be maintained and correctly associated within PLM documents.
8. Workflow Management and Document Review
Workflow processes for reviews require correct assignment of reviewers and approvers.
Uses roles and ensures to maintain proper areas and tasks for efficient processing.
9. General Classifications and Document Structures in PLM
Benefits from organizing documents efficiently helps in retrieval and ensuring updates remain linked to projects.
Workflow tracking helps verify document status and approver actions within the system.
10. Support and Training Resources
Online guidance available for PLM functionality, transactions, and general support within Siemens.
Recommend utilizing SharePoint for updated abbreviations and document resources.