Sitewide Phase 3 Infrastructure Works – Contract CGP01V050: Comprehensive Notes

Parties & Contract Overview

  • Employer (First Party): Capital Group Properties for Real Estate Development S.A.E.

    • Registered office: Cairo Festival City, Taha Hussein St., Fifth Settlement, New Cairo, Plot 14B-1, Bldg A, 4th Floor

    • Signatories: H.E. Saeed Al Ghafli (Chairperson), Mr. Ahmed Aref (CEO)

  • Contractor (Second Party): Global Energy S.A.E.

    • Registered office: Unit 664 El Geish Rd intersecting Rd 45, Al Muntazah, Alexandria

    • Commercial Reg. No.: 72111

    • Signatory: Mr. Alsafy Gomaa Fathy Abdelmoaty (CEO)

  • Project: “Alburouj Project” – Sitewide Phase 3 Infrastructure Works Construction Package

    • Location: Km 42 South Cairo-Ismailia Road

    • Contract Ref.: CGP01V050

  • Contract Price: EGP 445,382,045EGP\ 445{,}382{,}045 (incl. VAT & all taxes) on a re-measured basis

  • Time for Completion: 480 calendar days480\ \text{calendar days} from Commencement Date

  • Defects Notification Period (DNP): 365 days365\ \text{days}

  • Performance Security: 10%10\% of Contract Price (bank guarantee)

  • Advance Payment: 10%10\% of Accepted Contract Amount (repaid at 10%10\% of each IPC)

  • Delay Penalties: EGP 600,000/dayEGP\ 600{,}000\,/\text{day} per Section, capped at 10%10\% of Contract Price

Contract Documents & Priority (Clause 1.5)

  1. Contract Agreement

  2. Letter of Acceptance (if any)

  3. Appendix to Tender

  4. Particular Conditions of Contract

  5. General Conditions (FIDIC Red Book 1999)

  6. Technical Clarifications / Addenda

  7. Specifications & General Requirements

  8. Drawings

  9. Pricing Preambles

  10. BOQ & Method of Measurement

  11. Annexes A1–A3 (Scope, Schedule & Milestones, Masterplan) and B1–B5 (Guarantee forms, OCIP, etc.)

  • Documents are mutually explanatory; conflicts referred to Engineer; Contractor must notify ambiguities within 14 days or lose entitlement.

Scope Highlights (Annex A1 & Employer Nomination Rights)

  • Employer may direct-procure / nominate specified suppliers for:

    • Buildings: lighting fixtures, A/C units, sanitary ware, elevators, flooring, etc.

    • Infrastructure: interlock, cables, fiber optics, transformers, security, etc.

    • Landscape: lighting, play equipment, furniture, signage, security

    • Fences & Gates: precast concrete fence

  • Contractor’s price includes all coordination & potential resequencing with other contractors.

Contractor Key Obligations (Particular Conditions)

  • Design (where specified), execute, complete, test, commission & remedy defects strictly per Contract, Laws of Egypt, best international practice.

  • Provide new, lien-free materials; no deleterious substances.

  • Provide Arabic translation of Contract & BOQ within 28 days of signing; failure ⇒ 5 % withholding from 1st IPC.

  • Full site security for own materials until hand-over.

  • Performance Security to be issued within 14 days; must be unconditional, irrevocable, Egyptian bank.

  • Maintain insurances per Clause 18; OCIP supplied by Employer, deductibles on Contractor.

  • Programme: detailed baseline within 14 days; bi-weekly updates; daily & weekly look-ahead reports; float is for project, not solely Contractor; Time Impact Analysis (SCL 2017) required for EOT claims.

  • Quality: QA/QC plan, commissioning team, mock-ups, samples, shop-drawings; Engineer replies within 10 working days (RFIs 10 days, IRs 2 days).

  • HSE: safety plan 7 days pre-Commencement; dedicated safety officer; compliance with Egyptian Law 4/1994; fines & suspension for breaches.

  • Social insurance compliance; up to 10 % withholding if certificates not provided.

  • Subcontracting: prior written consent; pre-qualification ≥5 yrs experience; collateral warranty (Annex B4) within 10 days of appointment; max 15 % nomination fee.

  • Confidentiality: no disclosure, photos, or publicity without Employer consent.

  • Prohibited: assignment without Employer approval; use of deleterious materials; removal of Plant/Materials without consent.

Employer Rights & Powers

  • May assign/novate Contract to affiliate without Contractor objection.

  • Engineer requires Employer approval before key determinations (payments, variations, EOTs, suspension, termination, etc.).

  • May withhold payments for: missing documents, safety issues, insurance lapses, slow progress.

  • Can de-scope works (Clause 40) or procure materials (Clause 41); Contractor bears cost & no loss-of-profit.

  • Step-in rights under Sub-contractor Collateral Warranty; can take over Subcontract upon Contractor default.

Variations & Adjustments (Clause 13)

  • Written instruction mandatory; Contractor to proceed even if price unresolved.

  • Omitted work ≠ entitlement to loss of profit.

  • Overhead & profit on new-rate variations capped at 20%20\% of direct cost.

  • Value Engineering sharing: Contractor receives 30%30\% of documented savings.

  • Price adjustment limited:

    • Diesel escalation formula: V<em>2=V</em>1×0.01×(New Rate101)×(1AP%)V<em>2=V</em>1\times0.01\times\big(\tfrac{\text{New Rate}}{10}-1\big)\times(1-\text{AP\%})

    • Steel rebar & cement fluctuation mechanisms detailed.

    • Foreign currency clause: adjustment triggered if USD/EGP moves outside 424842–48 range, using: V<em>2=V</em>1×0.15×(USD New30.951)V<em>2=V</em>1\times0.15\times\big(\tfrac{\text{USD New}}{30.95}-1\big)

Payment Provisions (Clause 14)

  • Currency: Egyptian Pound only.

  • IPC frequency: monthly; Engineer may certify only if ≥35 % of forecast; cap at 115 % of cash-flow forecast.

  • Retention: 5%5\%, released 50 % at Taking-Over, 50 % at Final Certificate.

  • Financing charges for late payment: Corridor Rate of CBE, payable after 28 days from notice; no EOT or suspension due to late payment.

  • Plant/Materials on site: up to 40 % of BOQ rate (65 % for specified big-ticket items) after delivery & approval.

Delays & EOT (Clauses 8 & 20)

  • EOT causes limited; notice within 7 days; fully detailed claim within 28 days; fail ⇒ forfeiture.

  • Float first consumed; no EOT unless delay pushes critical path below zero.

  • Delay penalties accrue daily; reaching 10 % cap allows Employer to terminate.

Suspension & Termination (Clauses 8.8, 15, 16)

  • Employer may suspend for Contractor default, HSE, etc.; Contractor bears cost if attributable.

  • Employer automatic termination triggers: insolvency, failure to provide guarantees/insurance, delay penalties maxed, breach of law, etc.

  • Contractor has no right to terminate; Clause 16 declared “Not Used”.

Risk, Liability & Insurance (Clauses 17 & 18)

  • Contractor 10-year decennial liability per Egyptian Civil Code.

  • Employer’s risks narrowed (war, radioactivity, etc. limited to Egypt).

  • Total Contractor liability capped at Accepted Contract Amount, except for fraud/gross negligence.

  • OCIP in force; Contractor pays deductibles; must comply with policy notifications.

Dispute Resolution (Clause 20)

  • Disputes → Engineer decision within 56 days.

  • If dissatisfied: 56 days amicable settlement → CRCICA arbitration, Cairo, Egyptian Law; three arbitrators (Employer, Contractor, and chair by CRCICA if no agreement).

Appendix to Tender Key Data

  • Working hours: per Egyptian Labour Law; extended hours require approval & supervision costs.

  • Retention limit: 5%5\% of Contract Price.

  • Insurance deductibles: To Be Determined; Contractor’s equipment insured at 150 % of value.

  • Electronic communication: email permitted only in emergency; hard copy follow-up within 2 working days.

Forms & Annexes

  • B1 Performance Security Form (unconditional, payable on first demand; expires 60 days post Performance Certificate).

  • B2 Advance Payment Security Form (reduces as repayments made).

  • B3 Discharge & Release of Lien.

  • B4 Sub-contractor Collateral Warranty (step-in, IP rights, assignment).

  • B5 OCIP details.

Additional Particular Conditions (Clauses 21-42)

  • Change of Contractor constitution requires Employer approval.

  • Mandatory liaison with authorities; Contractor absorbs regulatory changes unless due to Employer.

  • Extensive Site facilities: temporary storage, fencing, first aid, fire prevention, welfare, etc.

  • Proof of payment to suppliers & subcontractors required with each IPC.

  • Duty to mitigate delays & costs; evidence within 14 days of Employer request.


These bullet-point notes capture the full structure, obligations, risk allocation, financial terms, and procedural requirements of the “Sitewide Phase 3 Infrastructure Works Construction Package” Contract (CGP01V050) between Capital Group Properties and Global Energy, incorporating all Particular Conditions and Appendix data.