Performance Analysis Report: MEE Units

MEE Units Performance Analysis Report

Background & Report Objective

  • Evaluates and compares the operational performance of MEE-2, MEE-3, and MEE-4 over their respective operating periods.

  • The objective is to analyze performance trends and cleaning effectiveness for long-term operational reliability and optimization potential.

MEE-3 Plant (Revamped with TG-Klaren Self-cleaning Technology)

Plant Details
  • Capacity: 72 KLD

  • Service: Same effluent as MEE-2 (CaSO₄-rich chemical stream)

  • Design: Conventional forced circulation MEE

  • Tubes per Calandria: 62 nos

  • Fouling Tendency: High

Summary of Cleaning Events
  • Hydrojet Cleaning of Cal-1: February 6-8, 2025

  • Nitric cleaning of Effect 2 to 4: February 27 - March 2, 2025

  • Hydrojet Cleaning: March 11-31, 2025

Key Performance Metrics (January 29, 2025 to April 14, 2025 – 48 Operational Days)

PHASE

Operational Days

AVG. FEED RATE (m³/hr)

AVG. TOP RATE (m³/hr)

AVG. STEAM RATE (T/hr)

STEAM ECONOMY

RECOVERY (%)

BEFORE HYDROJET OF CAL-1

08

3.48

2.53

1.16

2.18

72.88

AFTER HYDROJET OF CAL-1 & BEFORE NITRIC CLEANING

18

2.84

1.82

0.92

2.01

63.91

AFTER NITRIC OF EFFECT 2 to 4

08

2.49

1.48

0.78

1.91

59.43

AFTER 2nd HYDROJET (Still counting…)

13

2.74

1.77

0.88

2.02

64.87

OVERALL AVG.

48

2.86

1.87

0.92

2.02

65.37

Insights and Information from Plant Data (29 JAN 2025 TO 13 APR 2025)
  • Before Hydrojet of Cal-1 (29 Jan to 5 Feb 2025)

    • Stable performance with high recovery around 73% and steam economy around 2.18.

    • Cal-1 was relatively clean, and self-cleaning performed effectively.

  • After Hydrojet of Cal-1 & Before Nitric Cleaning (9 Feb to 26 Feb 2025)

    • Low vacuum observed despite VP draining and pump changeover.

    • Frequent choking in bottom tank suction/discharge lines reduced evaporation.

    • Resulted in recovery drop to 64% and moderate steam economy 2.01.

  • After Nitric Cleaning of Effect 2 to 4 (3 Mar to 10 Mar 2025)

    • Stable but lower performance with recovery down to 59%.

    • Steam rate rose from 0.6 to 0.9 T/hr due to fouling in Cal-1, reducing heat transfer efficiency and increasing thermal resistance.

    • More steam was needed to maintain bottom temperatures, indicating resistance in the evaporation zone.

  • Post-Hydrojet Cleaning (1 Apr to 14 Apr 2025)

    • After March 10, vacuum improved to around -500 to -530 mmHg, resulting in a recovery improvement to 76% as of April 13, 2025.

    • Initial operation faced low feed rates due to a high level in the top tank.

    • Particle movement delayed—caused by blockage in the booster suction line, later resolved.

    • From April 5 to April 9, vacuum dropped to -300 to -450 mmHg due to:

      • Dyke area waterlogged

      • Submerged drain valve

      • Resulted in reduced evaporation and system performance.

    • After April 10, vacuum improved to -500 to -530 mmHg, and recovery rose to 76% by April 14.

  • Impact of Bottom setpoint temperature on Fouling:

    • During the phase before 2nd Hydrojet, RCP-1 discharge bottom temperature setpoint was kept at 99°C.

    • This led to high Cal-1 temperatures, accelerating very hard fouling in the tubes.

    • Post-cleaning, the following corrective measures were taken:

      • Bottom setpoint was reduced to 95°C.

      • RCP-1 frequency fixed at 44 Hz.

      • Result: Smoother recirculation, softer scaling, improved cleaning cycle lifespan, and more stable particle motion.

  • Vacuum Issues from Graph analysis:

    • Inability to drain vacuum pump collection pot due to submerged drain valve (dyke flooding).

    • Persistent leakages in the vacuum system.

    • All these led to fluctuating and low vacuum performance until addressed post-10th Apr.

  • System Stabilization & Overall Performance:

    • MEE-3 operated for 47 days with the Klaren system functional throughout.

    • Delivered an average recovery of 65% and steam economy of 2.02 over 1.5 months.

    • Best Performance aligned with:

      • Clean Cal-1 conditions.

      • Bottom temp set at 95°C.

      • Particle flow normalization.

      • Improved vacuum and drainage.

  • Graphical Reference: Refer Fig 1 in Annexure

MEE-2 Plant

Plant Details
  • Capacity: 72 KLD

  • Service: Handles chemical effluent containing calcium sulphate

  • Design: Conventional forced circulation MEE

  • Tubes per Calandria: 162 nos (As mentioned by Aarti)

  • Fouling Tendency: High

Summary of Cleaning Events
  • Nitric Acid Cleaning: Conducted twice — around March 4-5, 2025 and March 13-16, 2025

  • Hydrojet Cleaning: Conducted from March 19 to April 9.

Key Performance Metrics (January 29, 2025 to April 10, 2025 – 45 Operational Days)

PHASE

Operational Days

AVG. FEED RATE (m³/hr)

AVG. TOP RATE (m³/hr)

AVG. STEAM RATE (T/hr)

STEAM ECONOMY

RECOVERY (%)

BEFORE NITRIC

06

1.95

0.91

0.73

1.45

46.71

AFTER 1st & 2nd NITRIC CLEANING

07

1.93

1.10

0.88

1.23

57.46

AFTER HYDROJET

32

2.76

2.09

1.26

1.66

75.5

OVERALL AVG.

45

2.49

1.73

1.12

1.55

69.74

Insights and Information from Plant Data (29 JAN 2025 TO 10 APR 2025)
  • Pre-Nitric Cleaning (29 Feb to 3 Mar 2025)

    • Plant operation showed flat performance with low vapor generation.

    • Steam economy at avg. 1.45 and avg. recovery at 46.71%, pointing to scaling/fouling buildup.

  • Post-Nitric Cleaning (6 Mar to 12 Mar 2025)

    • Top rate and recovery improved, but feed rate slightly dipped.

    • Steam economy declined to 1.23, possibly due to process realignment or increased vapor escape.

    • Cleaning effect was temporary, and benefits started declining within days.

  • Post-Hydrojet Cleaning (19 Mar to 9 Apr 2025)

    • Major performance boost:

      • Feed rate ↑ to 47%

      • Recovery ↑ to 75.5%

      • Steam economy peaked at 1.66

    • Indicates restored heat transfer significantly reducing resistance.

  • Recovery Spikes Based on Graph Analysis

    • During the "Post-Hydrojet" phase, recovery saw short-term spikes on 4 occasions each following:

      • Vacuum pump collection tank draining

      • Tank changeovers

    • These operational interventions temporarily reduced backpressure and improved vapor draw, enabling better evaporation and recovery.

  • System Stabilization

    • Overall, MEE-2 ran more efficiently after Hydrojet cleaning, averaging 68% recovery over the recorded period of Feb–Mar 2025.

    • Suggests the importance of both mechanical cleaning and support system maintenance (e.g., vacuum efficiency).

  • Graphical Reference: Refer Fig 2 in Annexure

MEE-4 Plant

Plant Details
  • Capacity: 72 KLD

  • Service: RO reject mixed with NT (nitration) stream

  • Design: Tube layout and shell diameter same as MEE-3

  • Tubes per Calandria: 62 nos

  • Fouling Tendency: High

Summary of Cleaning Events
  • 1st Nitric Cleaning: January 31 - February 1, 2025

  • Vacuum Pump (VP) Maintenance work: February 11-12, 2025

  • RCP-1 Maintenance work: From February 17-19, 2025

  • Vacuum Pump (VP) Maintenance work: February 27-28, 2025

  • Hydrojet Cleaning: Conducted from March 4-10, 2025

  • 2nd Nitric Cleaning: From April 3 onwards

Key Performance Metrics (January 29, 2025 to April 2, 2025 – 50 Operational Days)

PHASE

Operational Days

AVG. FEED RATE (m³/hr)

AVG. TOP RATE (m³/hr)

AVG. STEAM RATE (T/hr)

STEAM ECONOMY

RECOVERY (%)

Before 1st Nitric

02

1.73

0.88

0.31

2.83

50.79

Before Hydrojet

25

2.07

1.36

0.69

1.99

65.84

After Hydrojet and Before 2nd Nitric

23

2.89

2.07

1.23

1.68

71.29

Overall Avg.

50

2.45

1.68

0.93

1.88

68.51

Insights and Information from Plant Data (29TH JAN 2025 TO 02nd APR 2025)
  • Before 1st Nitric Cleaning (29–30 Jan 2025):

    • Very short period but with good steam economy 2.83, possibly due to cleaner initial conditions.

    • Recovery was low 51% as plant was just stabilizing.

  • Before Hydrojet Cleaning (2 Feb to 3 Mar 2025)

    • Reasonable feed rate of 2.07 m³/hr with moderate steam rate of 0.69 T/hr.

    • Recovery improved to 65.84%.

    • Drop in steam economy 1.99 indicates early signs of fouling impacting heat transfer.

  • After Hydrojet Cleaning & Before 2nd Nitric (11 Mar to 2 Apr 2025)

    • Best phase in terms of recovery 71.29% and top rate 2.07 m³/hr.

    • However, steam economy further dropped to 1.68, and steam rate increased to 1.23 T/hr.

    • The drop in steam economy along with increased steam usage suggests fouling possibly remained in the tube side or partially removed.

  • Overall Observation (29 Feb to 2 Apr 2025)

    • MEE-4 maintained stable operations over 50 days, with good recovery avg. 67.82%

    • Gradual increase in feed and top rate post hydrojet cleaning.

    • Increasing steam consumption trend with decreasing steam economy indicates need for improved fouling management.

  • Graphical Reference: Refer Fig 3 in Annexure

Overall Comparative Summary – MEE-2, MEE-3 & MEE-4

To assess relative performance across the three MEE plants, key operational metrics from each system were compared over similar operational windows. The table below provides a consolidated view:

PARAMETER

MEE-2 PLANT

MEE-3 PLANT

MEE-4 PLANT

Operational Days

45

47

50

Avg. Feed rate; m3/hr

2.49

2.86

2.45

Avg. Top rate; m3/hr

1.73

1.87

1.68

Avg. Steam rate; m3/hr

1.12

0.92

0.93

Avg. Steam Economy

1.55

2.02

1.80

Avg. Recovery; %

69.74

65.37

68.51

Note: Bold values highlight best-performing parameters among the three

Key Observations and Performance Insights:
  • MEE-3, equipped with the Klaren self-cleaning system, outperformed the other units in terms of steam economy (2.02) and throughput (2.86 m³/hr). The TG- Klaren self-cleaning system effectively minimized tube fouling, maintaining consistent heat transfer and reducing cleaning-related downtime.

  • While MEE-2 recorded the highest recovery (69.74%), it also showed the highest steam consumption (1.12 T/hr) and lowest steam economy (1.55). This suggests that despite higher water removal, the plant faced reduced thermal efficiency—likely due to fouling and suboptimal vacuum levels.

  • MEE-4 demonstrated balanced performance, with steam economy (1.80) and recovery (68.51%) close to MEE-3 and MEE-2, respectively. This indicates that improved vacuum stability and better process control post-cleaning contributed significantly, even in the absence of self-cleaning technology.

  • The steam economy advantage of MEE-3 validates the integration of self-cleaning as a long-term fouling mitigation strategy, supporting consistent performance across varying feed quality and operational disturbances.

  • Vacuum conditions, bottom setpoint control, and cleaning schedules were identified as common influencing factors across all MEEs, impacting evaporation efficiency and recovery. Fine-tuning these parameters, along with real-time monitoring, is essential for sustained plant performance.