Project Management & Analysis Chapter 7 - Defining the Project Budget and Risk Plans

0.0(0)
studied byStudied by 13 people
0.0(0)
full-widthCall Kai
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/56

flashcard set

Earn XP

Description and Tags

For CSN - CNA PPD

Study Analytics
Name
Mastery
Learn
Test
Matching
Spaced

No study sessions yet.

57 Terms

1
New cards

Analogous Estimating

An estimating technique that uses a similar past project as the approximate cost estimate. It is also known as top-down estimating or order-of-magnitude estimating.

2
New cards

Parametric Estimating

An estimating technique that uses math. Quantity of work times the rate.

Dependant on the accuracy of the data.

3
New cards

Bottom-up Estimating

An estimating technique which uses work effort estimates, which is the total time it will take to complete the task if you did nothing else. Must know the rate for each resource.

Starts at the Work Package Level in the WBS

4
New cards

Three-Point Estimates

An estimating technique which is an average of the most likely, optimistic, and pessimistic estimates. 

5
New cards

Three-Point Estimates - Most Likely

Assumes that cost will be as expected

6
New cards

Three-Point Estimates - Optimistic

Assumes that costs will be less than planned.

7
New cards

Three-Point Estimates - Pessimistic

Assumes costs will be more than planned.

8
New cards

Three-Point Estimates formula

(Most Likely + Optimistic + Pessimistic) / 3

9
New cards

Budgeting

Process of aggregating cost estimates and establishing a cost baseline.

10
New cards

Cost Baseline

Total expected cost for the project.

11
New cards

Contingency Reserve

Money set aside to cover costs resulting from possible adverse events or unexpected issues on the project. All projects should have this.

Is under the discretion of the PM.

12
New cards

Management Reserve

An amount set aside by upper management to cover future situations that cannot be predicted. Typically based on a percentage of total project cost.

Is controlled by upper management.

13
New cards

Expenditure Tracking

Measures the project spending to date. Determines Burn Rate, as well as tracks expenditures to the cost baseline.

14
New cards

Expenditure Reporting

How to report on the current state of the budget.
Can be tracked using a project management software or a spreadsheet.

15
New cards

Earned Value Management

Is a performance measurement technique that compares what the project produced against what was spend

Monitors planned value, earned value, and actual costs.

16
New cards

Planned Value

Cost of work budgeted for an activity or time period.

17
New cards

Actual Cost

Actual cost of completing the work in a given time period.

18
New cards

Earned Value

value of the work completed to date as it compares to the PV for that period.

19
New cards

Cost Variance (CV)

Shows whether costs are higher or lower than budgeted

20
New cards

Cost Variance Formula

CV = EV - AC

21
New cards

Cost Variance / Negative Result

This means that costs are higher than budgeted

22
New cards

Cost Variance / Positive Result

This means that costs are lower than budgeted.

23
New cards

Scheduled Variance (SV)

Compares activity’s actual progress to estimated progress to date in terms of cost.

24
New cards

Scheduled Variance Formula

SV = EV - PV

25
New cards

Scheduled Variance / Negative Result

this means that the project is behind schedule

26
New cards

Scheduled Variance / Positive Result

This means that the project is ahead of schedule.

27
New cards

Cost Performance Index (CPI)

Measures the value of the work completed at the measurement date against the actual cost. Most critical of all EVM measures.

28
New cards

CPI Formula

CPI = EV / AC

29
New cards

CPI Result / Greater

Cost performance is better than expected

30
New cards

CPI Result / Less

Cost performance worse than expected.

31
New cards

Schedule Performance Index (SPI)

Measures the progress to date against the progress that was planned.

32
New cards

SPI Formula

SPI = EV / PV

33
New cards

SPI Results / Less

Performance Schedule is worse than expected

34
New cards

SPI Results / Greater

Schedule performance is better than expected.

35
New cards

Burn Rate

The amount of money being spent over time.

36
New cards

Estimate to Complete (ETC)

Cost estimate for the remaining project work. Estimates are provided by team members.

37
New cards

Risk

Potential future event that can have either a negative or positive impact on the project.

38
New cards

Risk Planning

Managing areas of uncertainty in your project.

39
New cards

Risk Identification

Process of determining and documenting potential risks.

40
New cards

Potential Risk Areas

  • Budgets or Funding

  • Schedules

  • Scope

  • Requirement Changes

  • Contracts

  • Hardware

  • Political Concerns

  • Management Risks

  • Legal Risks

    • Technical Issues

41
New cards

SWOT

Strengths, Weaknesses, Opportunities, and Threats.

Strengths and Weaknesses are generally related to issues that are internal to the organization.

Opportunities and threats are usually external to the organization.

42
New cards

Risk Register

Is a list of risks

Include:

  • ID Number

  • Risk Name

  • Risk Description

  • Risk Owner

  • Risk Response Plan

43
New cards

Risk Analysis

The process of identifying risks that have the greatest possibility of occurring and the greatest impact if they do occur.

44
New cards

Risk Probability

The likelihood that a risk event will occur.

Measured from 0.0 to 1.0

45
New cards

Risk Impact

Is the consequence or opportunity the risk poses to the project if it occurs.

Measured in High, Medium, and Low

High = 1.0, Med = 0.5, Low = 0.1

46
New cards

Risk Score

The closer it is to 1.0, the more likely it is to occur and have a significant impact on the project.

47
New cards

Risk Response Planning

Process of reviewing the risk analysis and determining what, if any, action should be taken to reduce negative impacts and take advantage of opportunities as a result of a risk event occuring.

48
New cards

Risk Response Strategies – Negative Risks - Avoid

Avoiding the risk altogether or eliminating the cause of the risk event.

49
New cards

Risk Response Strategies – Negative Risks - Transfer

Moving the liability for the risk to a third party by purchasing insurance, performance bonds, and so on

50
New cards

Risk Response Strategies – Negative Risks - Mitigate

Reducing the impact or the probability of the risk.

51
New cards

Risk Response Strategies – Negative & Positive Risks - Accept

Accepting the consequences of the risk.

52
New cards

Risk Response Strategies – Positive Risks - Exploit

Looking for opportunities to take advantage of positive impacts.

53
New cards

Risk Response Strategies – Positive Risks - Share

Assigning the risk to a third party who is best able to bring about the opportunity.

54
New cards

Risk Response Strategies – Positive Risks - Enhance

Monitoring the probability or impact of the risk event to assure benefits are being realized.

55
New cards

Risk Trigger

A sign or precursor signalling that a risk event is about to occur.

56
New cards

How is Burn Rate Typically Calculated?

Using Cost Performance Index (CPI)

57
New cards

Work Effort Estimating

which is the total time it will take for a person to complete the task if they do nothing else from the time they start until the task is complete.