1/56
For CSN - CNA PPD
Name | Mastery | Learn | Test | Matching | Spaced |
|---|
No study sessions yet.
Analogous Estimating
An estimating technique that uses a similar past project as the approximate cost estimate. It is also known as top-down estimating or order-of-magnitude estimating.
Parametric Estimating
An estimating technique that uses math. Quantity of work times the rate.
Dependant on the accuracy of the data.
Bottom-up Estimating
An estimating technique which uses work effort estimates, which is the total time it will take to complete the task if you did nothing else. Must know the rate for each resource.
Starts at the Work Package Level in the WBS
Three-Point Estimates
An estimating technique which is an average of the most likely, optimistic, and pessimistic estimates.
Three-Point Estimates - Most Likely
Assumes that cost will be as expected
Three-Point Estimates - Optimistic
Assumes that costs will be less than planned.
Three-Point Estimates - Pessimistic
Assumes costs will be more than planned.
Three-Point Estimates formula
(Most Likely + Optimistic + Pessimistic) / 3
Budgeting
Process of aggregating cost estimates and establishing a cost baseline.
Cost Baseline
Total expected cost for the project.
Contingency Reserve
Money set aside to cover costs resulting from possible adverse events or unexpected issues on the project. All projects should have this.
Is under the discretion of the PM.
Management Reserve
An amount set aside by upper management to cover future situations that cannot be predicted. Typically based on a percentage of total project cost.
Is controlled by upper management.
Expenditure Tracking
Measures the project spending to date. Determines Burn Rate, as well as tracks expenditures to the cost baseline.
Expenditure Reporting
How to report on the current state of the budget.
Can be tracked using a project management software or a spreadsheet.
Earned Value Management
Is a performance measurement technique that compares what the project produced against what was spend
Monitors planned value, earned value, and actual costs.
Planned Value
Cost of work budgeted for an activity or time period.
Actual Cost
Actual cost of completing the work in a given time period.
Earned Value
value of the work completed to date as it compares to the PV for that period.
Cost Variance (CV)
Shows whether costs are higher or lower than budgeted
Cost Variance Formula
CV = EV - AC
Cost Variance / Negative Result
This means that costs are higher than budgeted
Cost Variance / Positive Result
This means that costs are lower than budgeted.
Scheduled Variance (SV)
Compares activity’s actual progress to estimated progress to date in terms of cost.
Scheduled Variance Formula
SV = EV - PV
Scheduled Variance / Negative Result
this means that the project is behind schedule
Scheduled Variance / Positive Result
This means that the project is ahead of schedule.
Cost Performance Index (CPI)
Measures the value of the work completed at the measurement date against the actual cost. Most critical of all EVM measures.
CPI Formula
CPI = EV / AC
CPI Result / Greater
Cost performance is better than expected
CPI Result / Less
Cost performance worse than expected.
Schedule Performance Index (SPI)
Measures the progress to date against the progress that was planned.
SPI Formula
SPI = EV / PV
SPI Results / Less
Performance Schedule is worse than expected
SPI Results / Greater
Schedule performance is better than expected.
Burn Rate
The amount of money being spent over time.
Estimate to Complete (ETC)
Cost estimate for the remaining project work. Estimates are provided by team members.
Risk
Potential future event that can have either a negative or positive impact on the project.
Risk Planning
Managing areas of uncertainty in your project.
Risk Identification
Process of determining and documenting potential risks.
Potential Risk Areas
Budgets or Funding
Schedules
Scope
Requirement Changes
Contracts
Hardware
Political Concerns
Management Risks
Legal Risks
Technical Issues
SWOT
Strengths, Weaknesses, Opportunities, and Threats.
Strengths and Weaknesses are generally related to issues that are internal to the organization.
Opportunities and threats are usually external to the organization.
Risk Register
Is a list of risks
Include:
ID Number
Risk Name
Risk Description
Risk Owner
Risk Response Plan
Risk Analysis
The process of identifying risks that have the greatest possibility of occurring and the greatest impact if they do occur.
Risk Probability
The likelihood that a risk event will occur.
Measured from 0.0 to 1.0
Risk Impact
Is the consequence or opportunity the risk poses to the project if it occurs.
Measured in High, Medium, and Low
High = 1.0, Med = 0.5, Low = 0.1
Risk Score
The closer it is to 1.0, the more likely it is to occur and have a significant impact on the project.
Risk Response Planning
Process of reviewing the risk analysis and determining what, if any, action should be taken to reduce negative impacts and take advantage of opportunities as a result of a risk event occuring.
Risk Response Strategies – Negative Risks - Avoid
Avoiding the risk altogether or eliminating the cause of the risk event.
Risk Response Strategies – Negative Risks - Transfer
Moving the liability for the risk to a third party by purchasing insurance, performance bonds, and so on
Risk Response Strategies – Negative Risks - Mitigate
Reducing the impact or the probability of the risk.
Risk Response Strategies – Negative & Positive Risks - Accept
Accepting the consequences of the risk.
Risk Response Strategies – Positive Risks - Exploit
Looking for opportunities to take advantage of positive impacts.
Risk Response Strategies – Positive Risks - Share
Assigning the risk to a third party who is best able to bring about the opportunity.
Risk Response Strategies – Positive Risks - Enhance
Monitoring the probability or impact of the risk event to assure benefits are being realized.
Risk Trigger
A sign or precursor signalling that a risk event is about to occur.
How is Burn Rate Typically Calculated?
Using Cost Performance Index (CPI)
Work Effort Estimating
which is the total time it will take for a person to complete the task if they do nothing else from the time they start until the task is complete.