The historical time frame covering the constructions of pyramids in Egypt is a time when the distinctions between the design and construction professionals identified the following as builders
Master Builders
During the roman empire, they developed which of the following? 1-concrete, 2-bridges, 3-domes, 4-arches, and 5-trusses
1,3,4
Road construction was created during the industrial revolution? T/F
false
Stone construction was revitalized in the middle ages by the roman catholic church? T/F
true
Skyscrapers came about in the late 1800s as a result of what? 1-electricity, 2-steel replacing iron, 3-portland cement, 4- reinforced concrete, 5-mass produced glass
All of these
the 20th century brought about building codes, standards, and specs to help regulate and control quality? T/F
true
The construction industry includes which of the following sectors? 1-industrial, 2-environmental, 3-residential, 4-commercial, 5-heavy civil
all of these
Most building construction projects are designed with an engineer leading the design process? T/F
false
Most construction projects in the United States are funded by public money? T/F
false
Heavy/Civil construction includes which of the following= 1-roadways, 2-bridges, 3-airport hangers, 4-railways, 5-data centers, 6-tunnels
1,2,4,6
No construciton project would exist without an?
owner
The book identifies a group of project values. Which one of the PV is most important?
Safety
The owner creates the basis for the design of a project and it is called the program of requirements? T/F
true
Most design build prjects are designer lead? T/F
False
CoSci has student chapters with all national construction organizations except which?
Design Build Institute of America
Which of these project delivery methods is thew contractor not involved in the deisgn?
Design-Bid-Build
The law requires contractors to provide certasin bonds on public projects, which are they? 1-construction, 2-payment, 3-bid, 4-performance, 5- project
2,4,5
Which of the following 2 items is generally the first to be utiliozed in contractor selection process?
RFQ-request for qualifcations
Now that you have been given the project, it is now the time to look closely at what exactly youre responsible for? T/F
false, look before you bid
The project manual, which includes the specs, defines the quanity of work-length, width, volume and so on? T/F
False
Which of these requests does not invlve pricing components
RFQ
The notice to proceed is the document issued by the owner authorizing the contractor to start-
Construction
The residential construction market is relatively easy to get into but many companies are small with high fail risk? T/F
True
Most environmental prjects are designed with an architect leading the design? T/F
False
In team dynamics, which of the following is not one of the 4 personality types? amiables, analyticals, drives, universalists
Universalists
_ and _ are the 2 major compnents that make up constarct documents
drawings and specifications
Cad stands for_
Computer Aided Design
There is a particular way in which drawings are organized in a set identify the correct order. a-architectural, b-structural, c-MEP, d-general, e-civil
deabc
WHat division would you find insulation?
Division 7
Which is not one of the four basic types of construction contracts?
Professional Services Agreement
Document used to make changes in a set of contract documents before trades are awarded?
Addenda
Which of the following is the preferred delivery method for public institutional commerical construction projects?
Design-Build
of the 4 distint stages of the design process, which is third? Schematic design, contrcat documents, programming and feasibility, design development
Design development
Who is responsible for adminstering local building codes?
Authority having Jurisdiction (AHJ)
Which of the following completes Big Guy's quote for preconstruction abilities? The ability to read in _ dimensions and see in _ dimensions
2 & 3
Charcateristics of good estimators would include what?
technical abilities, visualization skills, knows contract documents, detailed number skills
Are construction estimates typically organized by construction specification institute division of work? T/F
true
Name the 4 primary categoris of direct costs in construction estimates
labor, subcontracts, material, equipment
Lead time is the amount of time it takes for products or equipment to be delivered to job? T/F
true
Liquidated damages are the daily amount of time paid by the contractpr to the owner for each day that the proiject fails to meet the completion date specified in the contract? T/F
False
Which of the following does not belong to the 4 indirect costs ina construction esitmate?
Small tools for installation
General Conditions or Job overhead are calculated on basis of
Time
The benefit of a cost model is to guide design? T/F
true
Conceptual estimating through the design process can ensure that the completed design is in line with the budget? T/F
True
Who should perform the constructability review?
Construction manager
Which of the following would be included in feasibility study for a new school? traffic and parking, envrionment impacts, landscaping, proximity to fast food
Traffic and parking, environmental impacts
List the most common preconstruction services
Constructability reviews, life cycle analysis, target value design, value engineering
Proconstruction services is the process that represents the front end planning, cost estimation, and execution planning for a prject that gets the project to _
Start
What are 4 ways owners can benefit from alternative project methods?
higher quality, greater value, less waste, more innovation
Complete the following statement- The simplest ways to understand the difference is that we manage _ and lead _
things & people
Give 3 examples of effective speaking
review and summarize, set a "by when", watch nonverbal cues
Give 3 examples of effective listening
Positive listening energy, show respect and concern, stop talking
name 3 key members of the project team
owner, architect, GC/CM
The most underutilized resources available during the design phases is the engagement of the field personel who have experience installing the systems, equioment, and products? T/F
True
What marks the official end of the project?
substantial completion
Name the positions that make up the the memebrs of the on site construction management team
Field engineer, project manager, super intendent
Project close out includes which of the following?
final completion, certificate of occupancy, project punch lists, substantial completion
The AHJ is responsible for which?
Adminstering building bodes, issuing building permits, issuing certificates of occupancy, inspections for compliance
Which are the stages of the design process?
schematic design, programming/feasibility, construction documents, design development
What is the measure of a succesful project? profit goals achied, AHJ accepted building, Bank accepted building, budget aligned with program
All of the above
Its not _ until somebody _ it
architecture & builds
Which of the following is a means of contractor receiving clarification from the architect regarding details of the design after the contract documents have been publisbed and guaranteed max price executed? submittal approvals, addenda, RFI responses, Change order request
RFI responses
What is the purpose of a submittal?
color options, product data, product sample, product literature
The prupose of shop drawings is to supplement contract documents? T/F
True
What is the name of the document that establishes the template for measuring work progress as it related to requests for payment?
Schedule of values
Liquidated damages are assessed in lieu of actual damages? T/F
true
What is retainage? percentage established in contract to withhold from progress payments, amound that is deducted from the schedule of values, amount deducted from an approved change order
All of these
Which of the following is a form of dispute resolution?
mediation, binding arbitration, non binding arbitration
a site logistics plan should include all of the following-
location of temporary field offices, traffic routes, security measures for construction, site location and access
a mock up is seperate from the building? T/F
true
Which construction software will provide project management and document control?
Procore, E-builder, Newforma
Assignment 8 had you study 5 construction software packages. Which is the software package for scheduling
Ebuilder, newforma, primavera, procore( all)
Indetify 3 issues that the superintendent must be concerned with when trying to manage construction operations?
Material and equipment deliveries, subcontractor coordination, jobsite safety
When scheduling subcontractors, you should try to follow what fundamental rules?
are we ready for them? can we pay them? Has the mock up been reviewed and approved for their work? Do they have everything they need to complete their work?
Just in time deliveries focuses on planning for materials and equipment to arrive, be unloaded, and set in place? T/F
True
Identify factors that can negatively impact construction productivity
high rise construction, changes, crowded work spaces, inexperienced or poorly trained craftsmen
Identify environmental issues that might interfere with the project schedule and cause un-expected delays on the job
archaeological finds, endangered species, wetlands
Construction results in 40% of all waste in North America? T/F
true
How do we document DAILY work progress on our projects?
Personal diaries and cell phones
The SWPPP is to control soil erosion? T/F
true
The back charge is?
chagres for work failed to complete, charges for damages to others work, amount charged for work performed not per plans and specs
A site logistics plan should include
Material storage zones and their location, location of field offices, security measures
Quality control is the _ that ensures the quality required by the plans and specs
program
Quality assurance is the _ that achieve the quality required by the plans and specs
process
A trade partner is the same as a subcontractor? T/F
false
What are the most common types of schedules used in construction?
Network diagrams and Gantt charts
What are the funadamental stages of schedule development?
planning, schedule, sequencing
A 3WLA schedule is which level of schedule?
Level 4
Who are the stakeholders involved in the planning phase of a project?
CM, Owner, Architect
Name the 3 different types of activities that are included in the typical schedule
production, procurement, and administration activities
The critical path is the _ path through a network diagram schedule and includes those activities that have zero float
longest
Float and slack are the same? T/F
true
3WLA schedules are prepared by which of the following?
superintendent
in primavera the listing of items contained in the network diagram are called _
activities
The fundamental steps included in the project control cycle include a step for benchmarks. Which of the following 2 are used to establish those benchmarks?
Schedule and estimate
What are the 2 essential items of a effective project control system?
info such as man hours per task and accurate reporting
Name 3 factors that can impact project performance
inadequate tools and equipment, overcrowding, weather
A superintendent cant _ quality; they must _ for quality
ensure & inspect
What are the fundamental objectives of a quality management plan?
mistake prevention, do it right first time, continuous improvement
What is the difference between quality control and assurance? quality control addresses at the project level and deals with _ to the plans and specs
conformance