1/121
Looks like no tags are added yet.
Name | Mastery | Learn | Test | Matching | Spaced |
|---|
No study sessions yet.
Project Risk
An uncertain event or condition that if it occurs positively or negatively impacts project objectives such as scope schedule cost and quality
Positive Risk (Opportunity)
A favorable event such as new technology or removal of trade barriers
Negative Risk (Threat)
An unfavorable event such as new regulations competition changes or technological obsolescence
Internal Risks
Risks arising within the organization such as inaccurate estimates scope creep schedule delays quality failures personnel issues or outdated technology
External Risks
Risks outside organizational control such as governance changes market shifts legal changes environmental events or supplier failures
Project Risk Management
The process of identifying analyzing and responding to risks throughout the project life cycle
Objectives of Risk Management
Increase probability and impact of positive events and reduce probability and impact of negative events
Risk Identification
Process of determining which risks may affect the project and documenting characteristics
Risk Identification Techniques
Brainstorming expert interviews lessons learned SWOT analysis and diagramming
Root Cause Analysis
Technique to identify underlying causes of risks and may reveal triggers
Risk Trigger
Indicator that a risk is about to occur and signals activation
Cause and Effect Diagram
Fishbone or Ishikawa diagram listing causes under categories such as people machine and methods
Risk Categories
Technical project management organizational and external
Risk Register
A living document listing identified risks causes categories probability impact and responses
Risk Response Planning
Process of selecting strategies and actions to address risks and assigning owners
Risk Strategy Acceptance
Take no action unless a trigger occurs used when mitigation is too costly
Risk Strategy Mitigation
Reduce probability or impact proactively through training design improvement or prototyping
Risk Strategy Transfer
Shift ownership through insurance or outsourcing
Risk Strategy Avoidance
Eliminate risk by changing approach or scope
Qualitative Risk Analysis
Prioritizing risks based on probability and impact
Risk Probability
Likelihood of a risk occurring measured from zero to one hundred percent
Risk Impact
Severity of consequences to cost schedule or performance
Quantitative Risk Analysis
Numerical evaluation of risk impact using tools such as EMV
Risk Formula
Risk is equal to probability times impact
Expected Monetary Value (EMV)
Calculation used to quantify cost impacts of risks
EMV Formula
EMV equals probability multiplied by impact
Positive EMV
Indicates potential benefit or opportunity
Negative EMV
Indicates potential cost or threat
Project Schedule
A timetable showing activities start and end dates resources and due date
Schedule Baseline
Approved version of the project schedule changed only through formal change control
Activity
A distinct scheduled portion of project work that starts with an action verb
Duration
Total work periods required to complete an activity
Activity Sequencing
Ordering project activities logically to form a network diagram
Project Network
Diagram of nodes representing activities and arrows representing dependencies
AON Network
Activity on Node method using boxes to represent activities
AOA Network
Activity on Arrow method where arrows represent activities
Milestone
A significant event with zero duration marking major deliverables or checkpoints
Path
A sequence of connected project activities
Critical Path
Longest path with zero slack determining overall project duration
Successor Activity
Activity that logically comes after another
Predecessor Activity
Activity that must be completed or started before the successor
Precedence Diagramming Method (PDM)
Shows activities as nodes connected by logical dependencies
Finish to Start (FS)
Successor starts after predecessor finishes
Finish to Finish (FF)
Successor cannot finish until predecessor finishes
Start to Start (SS)
Successor starts only after predecessor begins
Start to Finish (SF)
Successor finishes only after predecessor starts
Lead
Amount successor activity can be advanced relative to predecessor
Lag
Delay between predecessor finish and successor start
Activity Duration Estimating
Process of determining the amount of time each activity requires
Analogous Estimating (Duration)
Uses duration of similar past projects and is the least accurate but quickest
Parametric Estimating (Duration)
Uses a mathematical model such as quantity multiplied by rate
One Point Estimating
Expert judgment produces a single estimate
3 Point (PERT) Estimating
Uses optimistic most likely and pessimistic values formula equals O plus four M plus P divided by six
PERT Network
Probabilistic method visualizing sequences dependencies and expected time
CPM (Critical Path Method)
Uses deterministic single time estimates to compute project duration
Forward Pass
Calculates early start and early finish
Backward Pass
Calculates late start and late finish
Slack or Float
Amount of delay allowed without delaying the project equals LS minus ES or LF minus EF
Zero Slack
Indicates an activity lies on the critical path
Standard Deviation (PERT)
Standard deviation equals pessimistic minus optimistic divided by six
Variance (PERT)
Variance equals standard deviation squared
Expected Path Duration
Sum of expected durations of activities on a path
Project Cost
Resources measured in monetary terms needed to achieve project objectives
Cost Management
Planning estimating budgeting financing managing and controlling costs
Importance of Cost Management
Sets cost baseline supports control decisions and prevents overruns
Cost Management Challenges
Poor estimation lack of resources scope variation inefficient processes and inaccurate reporting
Requirements for Accurate Cost Estimates
Well defined scope detailed WBS complete schedule expert judgment and adequate planning time
Considerations for Cost Estimation
Life cycle cost alternatives historical data realistic assumptions and required change approvals
Fixed Cost
Cost that does not change with production such as rent licenses or setup
Variable Cost
Cost that changes with amount of work such as materials or usage based labor
Direct Cost
Cost directly attributable to project work such as labor travel or materials
Indirect Cost
Shared overhead not tied to a single project such as taxes benefits or utilities
Plan Cost Management
Defines how to estimate budget manage monitor and control costs
Estimate Costs
Process of approximating cost of all resources needed
Determine Budget
Aggregating all estimated activity costs to set the cost baseline
Control Costs
Monitoring spending and managing changes to the cost baseline
Cost Management Plan Units of Measure
Standard units such as hours weeks meters liters or dollars
Cost Management Plan Level of Precision
Rounding guidelines for cost estimates
Cost Management Plan Level of Accuracy
Acceptable range of estimate variance such as plus or minus ten percent
Activity Based Estimating
Cost based on labor and materials per activity
Analogous Cost Estimating
Uses past similar projects to estimate current costs
Parametric Estimating (Cost)
Uses mathematical models such as cost per unit
3 Point Cost Estimating
Weighted average using optimistic most likely and pessimistic values equals O plus four M plus P divided by six
Bottom Up Cost Estimating
Most detailed and accurate sums costs from lowest WBS levels
Contingency Reserve
Budget for known unknowns likely to be spent part of cost baseline
Management Reserve
Budget for unknown unknowns controlled by senior management and not part of baseline
Reserve
Extra money used for risk responses or unforeseen cost events
Quality (PMBOK definition)
The degree to which a set of inherent characteristics fulfills requirements
Importance of Quality
Defines stakeholder expectations and stresses that prevention is cheaper than fixing errors or rework
Project Quality Management (definition)
Processes and activities ensuring a project meets defined needs from the customer perspective with no deviations from requirements
Why Project Quality Management is Important
Helps manage projects control costs set standards reduce failure risk and ensure customer satisfaction
Plan Quality Management
Defines quality for the project and product and how it will be achieved
Manage Quality
Ensures the team follows organizational standards and identifies areas for process improvement
Control Quality
Monitors deliverables ensures correctness and finds sources of problems
Project Manager’s Role in Quality
Understand expectations determine metrics identify standards ensure adherence improve quality emphasize equal priority with scope time and cost and perform QA and QC
Impact of Poor Quality
Increased costs decreased profits low morale low satisfaction increased risk rework and delays
Philip Crosbys Four Absolutes of Quality
Quality equals conformance to requirements prevention over inspection zero defects and measurement in monetary terms
Main Goal of Project Quality Management
Ensure the project meets customer needs and expectations
Key Quality Management Concepts
ISO 9000 TQM Six Sigma JIT PDCA customer satisfaction and continuous improvement
ISO 9000 (definition)
Internationally accepted standards for quality management