Project Management Exam 3

0.0(0)
studied byStudied by 0 people
0.0(0)
full-widthCall Kai
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/121

encourage image

There's no tags or description

Looks like no tags are added yet.

Study Analytics
Name
Mastery
Learn
Test
Matching
Spaced

No study sessions yet.

122 Terms

1
New cards

Project Risk

An uncertain event or condition that if it occurs positively or negatively impacts project objectives such as scope schedule cost and quality

2
New cards

Positive Risk (Opportunity)

A favorable event such as new technology or removal of trade barriers

3
New cards

Negative Risk (Threat)

An unfavorable event such as new regulations competition changes or technological obsolescence

4
New cards

Internal Risks

Risks arising within the organization such as inaccurate estimates scope creep schedule delays quality failures personnel issues or outdated technology

5
New cards

External Risks

Risks outside organizational control such as governance changes market shifts legal changes environmental events or supplier failures

6
New cards

Project Risk Management

The process of identifying analyzing and responding to risks throughout the project life cycle

7
New cards

Objectives of Risk Management

Increase probability and impact of positive events and reduce probability and impact of negative events

8
New cards

Risk Identification

Process of determining which risks may affect the project and documenting characteristics

9
New cards

Risk Identification Techniques

Brainstorming expert interviews lessons learned SWOT analysis and diagramming

10
New cards

Root Cause Analysis

Technique to identify underlying causes of risks and may reveal triggers

11
New cards

Risk Trigger

Indicator that a risk is about to occur and signals activation

12
New cards

Cause and Effect Diagram

Fishbone or Ishikawa diagram listing causes under categories such as people machine and methods

13
New cards

Risk Categories

Technical project management organizational and external

14
New cards

Risk Register

A living document listing identified risks causes categories probability impact and responses

15
New cards

Risk Response Planning

Process of selecting strategies and actions to address risks and assigning owners

16
New cards

Risk Strategy Acceptance

Take no action unless a trigger occurs used when mitigation is too costly

17
New cards

Risk Strategy Mitigation

Reduce probability or impact proactively through training design improvement or prototyping

18
New cards

Risk Strategy Transfer

Shift ownership through insurance or outsourcing

19
New cards

Risk Strategy Avoidance

Eliminate risk by changing approach or scope

20
New cards

Qualitative Risk Analysis

Prioritizing risks based on probability and impact

21
New cards

Risk Probability

Likelihood of a risk occurring measured from zero to one hundred percent

22
New cards

Risk Impact

Severity of consequences to cost schedule or performance

23
New cards

Quantitative Risk Analysis

Numerical evaluation of risk impact using tools such as EMV

24
New cards

Risk Formula

Risk is equal to probability times impact

25
New cards

Expected Monetary Value (EMV)

Calculation used to quantify cost impacts of risks

26
New cards

EMV Formula

EMV equals probability multiplied by impact

27
New cards

Positive EMV

Indicates potential benefit or opportunity

28
New cards

Negative EMV

Indicates potential cost or threat

29
New cards

Project Schedule

A timetable showing activities start and end dates resources and due date

30
New cards

Schedule Baseline

Approved version of the project schedule changed only through formal change control

31
New cards

Activity

A distinct scheduled portion of project work that starts with an action verb

32
New cards

Duration

Total work periods required to complete an activity

33
New cards

Activity Sequencing

Ordering project activities logically to form a network diagram

34
New cards

Project Network

Diagram of nodes representing activities and arrows representing dependencies

35
New cards

AON Network

Activity on Node method using boxes to represent activities

36
New cards

AOA Network

Activity on Arrow method where arrows represent activities

37
New cards

Milestone

A significant event with zero duration marking major deliverables or checkpoints

38
New cards

Path

A sequence of connected project activities

39
New cards

Critical Path

Longest path with zero slack determining overall project duration

40
New cards

Successor Activity

Activity that logically comes after another

41
New cards

Predecessor Activity

Activity that must be completed or started before the successor

42
New cards

Precedence Diagramming Method (PDM)

Shows activities as nodes connected by logical dependencies

43
New cards

Finish to Start (FS)

Successor starts after predecessor finishes

44
New cards

Finish to Finish (FF)

Successor cannot finish until predecessor finishes

45
New cards

Start to Start (SS)

Successor starts only after predecessor begins

46
New cards

Start to Finish (SF)

Successor finishes only after predecessor starts

47
New cards

Lead

Amount successor activity can be advanced relative to predecessor

48
New cards

Lag

Delay between predecessor finish and successor start

49
New cards

Activity Duration Estimating

Process of determining the amount of time each activity requires

50
New cards

Analogous Estimating (Duration)

Uses duration of similar past projects and is the least accurate but quickest

51
New cards

Parametric Estimating (Duration)

Uses a mathematical model such as quantity multiplied by rate

52
New cards

One Point Estimating

Expert judgment produces a single estimate

53
New cards

3 Point (PERT) Estimating

Uses optimistic most likely and pessimistic values formula equals O plus four M plus P divided by six

54
New cards

PERT Network

Probabilistic method visualizing sequences dependencies and expected time

55
New cards

CPM (Critical Path Method)

Uses deterministic single time estimates to compute project duration

56
New cards

Forward Pass

Calculates early start and early finish

57
New cards

Backward Pass

Calculates late start and late finish

58
New cards

Slack or Float

Amount of delay allowed without delaying the project equals LS minus ES or LF minus EF

59
New cards

Zero Slack

Indicates an activity lies on the critical path

60
New cards

Standard Deviation (PERT)

Standard deviation equals pessimistic minus optimistic divided by six

61
New cards

Variance (PERT)

Variance equals standard deviation squared

62
New cards

Expected Path Duration

Sum of expected durations of activities on a path

63
New cards

Project Cost

Resources measured in monetary terms needed to achieve project objectives

64
New cards

Cost Management

Planning estimating budgeting financing managing and controlling costs

65
New cards

Importance of Cost Management

Sets cost baseline supports control decisions and prevents overruns

66
New cards

Cost Management Challenges

Poor estimation lack of resources scope variation inefficient processes and inaccurate reporting

67
New cards

Requirements for Accurate Cost Estimates

Well defined scope detailed WBS complete schedule expert judgment and adequate planning time

68
New cards

Considerations for Cost Estimation

Life cycle cost alternatives historical data realistic assumptions and required change approvals

69
New cards

Fixed Cost

Cost that does not change with production such as rent licenses or setup

70
New cards

Variable Cost

Cost that changes with amount of work such as materials or usage based labor

71
New cards

Direct Cost

Cost directly attributable to project work such as labor travel or materials

72
New cards

Indirect Cost

Shared overhead not tied to a single project such as taxes benefits or utilities

73
New cards

Plan Cost Management

Defines how to estimate budget manage monitor and control costs

74
New cards

Estimate Costs

Process of approximating cost of all resources needed

75
New cards

Determine Budget

Aggregating all estimated activity costs to set the cost baseline

76
New cards

Control Costs

Monitoring spending and managing changes to the cost baseline

77
New cards

Cost Management Plan Units of Measure

Standard units such as hours weeks meters liters or dollars

78
New cards

Cost Management Plan Level of Precision

Rounding guidelines for cost estimates

79
New cards

Cost Management Plan Level of Accuracy

Acceptable range of estimate variance such as plus or minus ten percent

80
New cards

Activity Based Estimating

Cost based on labor and materials per activity

81
New cards

Analogous Cost Estimating

Uses past similar projects to estimate current costs

82
New cards

Parametric Estimating (Cost)

Uses mathematical models such as cost per unit

83
New cards

3 Point Cost Estimating

Weighted average using optimistic most likely and pessimistic values equals O plus four M plus P divided by six

84
New cards

Bottom Up Cost Estimating

Most detailed and accurate sums costs from lowest WBS levels

85
New cards

Contingency Reserve

Budget for known unknowns likely to be spent part of cost baseline

86
New cards

Management Reserve

Budget for unknown unknowns controlled by senior management and not part of baseline

87
New cards

Reserve

Extra money used for risk responses or unforeseen cost events

88
New cards

Quality (PMBOK definition)

The degree to which a set of inherent characteristics fulfills requirements

89
New cards

Importance of Quality

Defines stakeholder expectations and stresses that prevention is cheaper than fixing errors or rework

90
New cards

Project Quality Management (definition)

Processes and activities ensuring a project meets defined needs from the customer perspective with no deviations from requirements

91
New cards

Why Project Quality Management is Important

Helps manage projects control costs set standards reduce failure risk and ensure customer satisfaction

92
New cards

Plan Quality Management

Defines quality for the project and product and how it will be achieved

93
New cards

Manage Quality

Ensures the team follows organizational standards and identifies areas for process improvement

94
New cards

Control Quality

Monitors deliverables ensures correctness and finds sources of problems

95
New cards

Project Manager’s Role in Quality

Understand expectations determine metrics identify standards ensure adherence improve quality emphasize equal priority with scope time and cost and perform QA and QC

96
New cards

Impact of Poor Quality

Increased costs decreased profits low morale low satisfaction increased risk rework and delays

97
New cards

Philip Crosbys Four Absolutes of Quality

Quality equals conformance to requirements prevention over inspection zero defects and measurement in monetary terms

98
New cards

Main Goal of Project Quality Management

Ensure the project meets customer needs and expectations

99
New cards

Key Quality Management Concepts

ISO 9000 TQM Six Sigma JIT PDCA customer satisfaction and continuous improvement

100
New cards

ISO 9000 (definition)

Internationally accepted standards for quality management