1/25
Looks like no tags are added yet.
Name | Mastery | Learn | Test | Matching | Spaced |
---|
No study sessions yet.
What is discharge of performance
Questions on this often state “Advise whether D is obliged to pay ….”
Contract is discharged when it has been performed or carried out
What is the complete performance rule + cases
Contract must be complete not half-done
(Cutter v Powell where wife could not claim dead husband's wages as his performance was incomplete)
Court developed exceptions to avoid harsh outcomes
What is acceptance of part performance
If party has only partly performed contract, the contract will only be discharged if the other party chooses to accept it
(Sumpter v Hedges where innocent party must choose to accept partial performance, S had no alternative other than to finish the house
What is substantial performance + case
Contract only discharged if a party has substantially completed what they were supposed to do, payment is made for the work done. Often occurs in large contracts where little things are not performed exactly. Only applies if breach of warranty not condition
(Hoenig v Issacs where most of work was done and only cost £53 to repair defects)
Substantial is defined on a case by case basis and depends on what remains unfinished and its value in comparison to the whole contract (Bolton v Mahadeva where the contract was £560 but cost £174 to fix his defects)
What is divisible contracts + case
If a contract can be divided into different parts which can be separately performed then complete performance of the whole contract will not apply
(Ritchie v Atkinson where ship owner agreed a rate per ton so could be payed for weight of cargo he transported, but liable for cargo he did not carry)
What is tender of performance + case
If one party prevents the other from completing it the innocent party can claim to be paid for the work done
(Planche v Colburn where author was entitled to a fee for wasted work when publisher hired them and then abandoned they series they wrote
What is delayed performance + case
The effect of delay to performance is treated as a condition if:
The parties have expressed performance in the contract is time critical
Time for completion is critical
One party has failed to perform on time and the other has insisted on a new date for completion (Making time of the essence)
If none of these are present then late performance is an innominate term and repudiation depends on severity of the consequence
(Union Eagle v Golden Achievement where the court decided the seller was entitled to repudiate the contract as time for completing was a condition )
What is frustration + case
Contract is discharged because through no fault of the parties it can no longer be performed
(Taylor v Caldwell where owners of a music hall could not complete contract as it burnt down)
What would be frustration
Intervening event which makes the performance impossible
Performance becomes illegal
Radical change of circumstances#
Not enough if purpose of only one party destroyed
What is Intervening event which makes the performance impossible +cases
Eg. destruction of the subject matter (Taylor v Caldwell), Death or unavailability of the party
(Robinson v Davison where piano player was ill),
Specific method of performance becomes impossible (Nickoll & Knight v Ashton Eldridge where the specifically named ship in contract ran aground)
What is performance becomes illegal + case
Performance becomes illegal due to a change in the law performing the contract would be illegal
(Fibrosa v Fairbairn where shipping a contract of machinery to a port in Poland was illegal)
What is radical change of circumstances + case
The event changes the main purpose of the contract for both parties
(Krell v Henry where D agreed to hire room from C to view coronation but was frustrated as the king was ill and the viewing was the foundation of contract)
What is Not enough if purpose of only one party destroyed case
(Herne Bay Steamboat v Hutton where the naval review by the king was not the main foundation of the contract and the cruise around the fleet was still possible)
What would not be frustration
Where parties have made express provision in the contract for the event
Performing a contract becomes more difficult or less profitable to perform
If the event was foreseeable when the parties contracted
The event is in control of one party (Self-induced)
What is where parties have made express provision in the contract for the event
If an event (such as a flood or war) is dealt with by a Force Majeure (Expressed term) stating what to in that situation such as suspend or terminate the contract
Case for Performing a contract becomes more difficult or less profitable to perform
Davis Contractors v Fareham the cost of building houses becoming more expensive was not frustration as the main reason to contract was still present
Case for If the event was foreseeable when the parties contracted
Amalgamated Investment v John Walker where the risk that the property could be listed was foreseen by C who inquired before
Case for The event is in control of one party (Self-induced)
The Super Servant 2, if D had not contracted with other ship in the contract he could have given it to C when the other one sank
What is consequences of frustration
The contract is automatically discharged from the moment the event occurs, existing obligations must be completed but futures ones terminated
When is the Law Reform (Frustrated Contracts) Act 1943 used
Law Reform (Frustrated Contracts) Act 1943 used unless parties have own terms
S.1(2) money paid in advance
is recoverable but money already due is not, however D is usually allowed to keep money for work done and expenses before
(Gamerco v ICM/Fair Warning where C was able to claim deposit back for stadium after safety concerns)
S.1(3) Performance which provides a valuable benefit
Where one party gains benefit before the contract is frustrated the court may order a just sum in return
(BP v Hunt where BP were entitled for a just sum as they helped H with valuable benefit)
What is breach of contract
Where one party fails to comply with a term of the contract either expressed or implied
Each breach of contract will give a right to claim damages
Unless breach is repudiatory (Serious) the contract will continue
Repudiatory breach gives innocent party option to discharge the contract it is not automatic
What is actual breach + case
When on party performs defectively, differently from agreed, or not at all on the date agreed (Poussard v Spiers where singer failed to turn up for 6 nights so the contract was due to be completed in the past)
What is anticipatory breach
When one party indicates before the date of performance they will not be performing the contract as agreed
Where an anticipatory breach occurs the other party can sue for break immediately, it is not necessary to wait (Hochster v De La Tour where tour guide was told 2 months before he was not needed)
Party may choose to wait until performance fails to see whether the party keeps the contract. Once they choose to wait they cannot change their mind (Avery v Bowden where contract was frustrated before date of performance so A lost his right to sue)
Can the contract be repudiated explained
Was the term clearly a condition
Can be by statute, precedent or parties
Time of performance not usually a condition unless a time of completion is critical (The Mihalis Angelos where in shipping the time a ship can be expected ready to load cargo is a condition) or the parties make it (Lombard v Butterworth where it was stated that time was of the essence)
Parties classification is not conclusive (Schuler v Wickman where the term was innominate even though stated to be “condition”)
If the term is not clearly a condition explained
If the term is not clearly a condition
Is innocent party deprived of substantially whole whole benefit of contracting(Hong Kong Fir Shipping v Kawasaki Kisen Kaisha where it was stated if a term is not clearly a condition it is an innominate term, in this case the effects of breach were not sufficiently serious)
If serious condition
If minor warranty